Meadows v. Higgins

733 A.2d 172, 249 Conn. 155, 1999 Conn. LEXIS 152
CourtSupreme Court of Connecticut
DecidedJune 1, 1999
DocketSC 15997
StatusPublished
Cited by78 cases

This text of 733 A.2d 172 (Meadows v. Higgins) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meadows v. Higgins, 733 A.2d 172, 249 Conn. 155, 1999 Conn. LEXIS 152 (Colo. 1999).

Opinion

[157]*157 Opinion

KATZ, J.

The defendants Harrison Scott Higgins and Linda Plank Higgins (defendants)1 appealed to the Appellate Court from the judgment of the trial court rendered in favor of the plaintiff, Michael Meadows, doing business as Paper Pro, ordering strict foreclosure of his mechanic’s lien. The defendants claimed that the trial court had improperly: (1) determined that the Home Improvement Act (act),2 did not apply to the transaction between the plaintiff and the defendants; and (2) awarded attorney’s fees to the plaintiff pursuant to General Statutes § 52-249, which provides for such fees in foreclosure actions. Additionally, the defendants appealed from the judgment of the trial court rendered in favor of the plaintiff as to their counterclaim,3 which alleged that, by violating the act, the plaintiffs actions constituted an unfair or deceptive trade practice in violation of the Connecticut Unfair Trade Practices Act (CUTPA).4 The Appellate Court determined that, although the act does not apply to a subcontractor, it did apply to the transaction between the parties, and, therefore, the Appellate Court reversed the judgment of the trial court. Meadows v. Higgins, 49 Conn. App. 286, 296, 614 A.2d 51 (1998).

We conclude that the Appellate Court properly held that the act does not apply to a subcontractor. We also conclude, however, that the Appellate Court improperly rejected the trial court’s findings that the plaintiff was [158]*158acting as a subcontractor to a general contractor and that, therefore, there was no contract between the plaintiff and the defendants subject to the act. Accordingly, we reverse the judgment of the Appellate Court.

The Appellate Court set forth the following relevant factual history. “An attorney trial referee found the following facts. The defendants are the owners of a parcel of residential property located in the town of Greenwich. Sometime prior to November, 1992, the defendants entered into a written contract with BCS Construction, Inc. (BCS), pursuant to which BCS agreed to serve as a consultant to the defendants on a project to renovate the defendants’ single-family home. In accordance with that contract, Bruce Simon, a principal of BCS and a registered home improvement contractor, was designated the construction manager for the project. Simon subsequently arranged to have the plaintiff provide painting and wallpapering services to the defendants. There was no document or writing setting forth the terms of the agreement pursuant to which the plaintiff provided services and materials to the defendants. On January 15,1993, the plaintiff had completed approximately 90 to 95 percent of the painting and wallpapering work when he was directed by the defendants to stop all work and leave the premises. The reasonable value of the services and materials provided by the plaintiff to the defendants is $29,255. The defendants have paid the plaintiff $12,840.

“On April 6, 1993, the plaintiff filed a certificate of mechanic’s lien with the Greenwich town clerk, claiming a lien on the defendants’ property in the amount of $16,415. On January 3, 1994, the plaintiff filed a one count complaint seeking, inter alia, foreclosure of the mechanic’s lien, damages and attorney’s fees pursuant to § 52-249. On October 25, 1994, the defendants filed an answer, five special defenses and a two count counterclaim. The special defenses to the foreclosure action [159]*159were that (1) the mechanic’s lien was invalid because it allegedly was not filed within ninety days of the last date of any work performed by the plaintiff, (2) the plaintiff is a contractor within the meaning of the [act], who performed work on the defendants’ home without having obtained a certificate of registration, (3) the plaintiff failed to advise the defendants of their cancellation rights, (4) any contract pursuant to which the plaintiff provided materials and services to the defendants was not entered into by a registered salesman or registered contractor and (5) there was no written contract signed by the plaintiff and the defendants. In the first count of their counterclaim, the defendants sought damages for the plaintiffs allegedly unsatisfactory, defective and negligent work. In the second count of their counterclaim, the defendants alleged that the plaintiffs actions constitute an unfair or deceptive trade practice in violation of [CUTPA], and sought, inter alia, compensatory and punitive damages, attorney’s fees and interest.

“The case was tried to an attorney trial referee, who concluded that the mechanic’s lien was timely filed and that the provisions of the [act] do not apply to the transaction between the plaintiff and the defendants. He also concluded that the defendants failed to meet their burden of proof on the allegations of unsatisfactory work performance and that the CUTPA violations alleged in the defendants’ counterclaim were based on the [act], which does not apply to this case. The attorney trial referee recommended that the court render judgment in favor of the plaintiff as to the complaint, with reasonable attorney’s fees pursuant to § 52-249, and as to both counts of the defendants’ counterclaim.

“On February 26, 1997, the trial court, Lewis, J., rendered judgment in accordance with the attorney trial referee’s report. The trial court found that the provisions of the [act] do not apply to the transaction [160]*160between the plaintiff and the defendants because the plaintiff was acting as a subcontractor to Simon, who was a general contractor, and, therefore, there was no contract between the plaintiff and the defendants. The trial court concluded that ‘as to the plaintiff’s complaint, judgment is entered in favor of the plaintiff to foreclose his mechanic’s lien and the amount of the debt due the plaintiff at this time is established at $16,415. As to the defendants’ counterclaim, judgment is entered in favor of the plaintiff. This case should now be claimed for the foreclosure motion or short calendar to rule on the specifics of such foreclosure, including the amount of the debt with interest, the type and date of foreclosure, the value of the premises, etc.’

“On March 17, 1997, the defendants appealed from the judgment of the trial court. On June 25, 1997, [the Appellate Court] dismissed the defendants’ appeal for lack of a final judgment. On August 11, 1997, the trial court, Mintz, J., held a hearing on the plaintiffs motion for judgment of strict foreclosure. The trial court rendered judgment of strict foreclosure in favor of the plaintiff and set a law day of September 9, 1997. The trial court also determined the amount of the debt, $16,415, the appraisal fee, $450, and the title search fee, $150, and awarded the plaintiff attorney’s fees of $8295. On August 19, 1997, the defendants filed this appeal.” Meadows v. Higgins, supra, 49 Conn. App. 288-90.

On appeal to the Appellate Court, the defendants claimed that the trial court improperly had determined that the act did not apply to the transaction between the plaintiff and the defendants. The Appellate Court agreed with the trial court that the act does not apply to subcontractors. The Appellate Court determined, however, that because Simon had not served as a general contractor, the plaintiff had not served as a subcontractor, and that, consequently, the act applied. Id., 296.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winakor v. Savalle
343 Conn. 773 (Supreme Court of Connecticut, 2022)
Girolametti v. Michael Horton Assocs., Inc.
208 A.3d 1223 (Supreme Court of Connecticut, 2019)
Frauenglass & Associates, LLC v. Enagbare
88 A.3d 1246 (Connecticut Appellate Court, 2014)
Absolute Plumbing & Heating, LLC v. Edelman
77 A.3d 889 (Connecticut Appellate Court, 2013)
State v. Koslik
49 A.3d 1067 (Connecticut Appellate Court, 2012)
ANDY'S OIL SERVICE, INC. v. Hobbs
9 A.3d 433 (Connecticut Appellate Court, 2010)
Bahjat v. Dadi
1 A.3d 212 (Connecticut Appellate Court, 2010)
Taylor v. King
994 A.2d 330 (Connecticut Appellate Court, 2010)
Hees v. Burke Construction Inc.
961 A.2d 373 (Supreme Court of Connecticut, 2009)
Scrivani v. Vallombroso
916 A.2d 827 (Connecticut Appellate Court, 2007)
MD Electrical Contractors, Inc. v. Abrams
859 N.E.2d 1070 (Appellate Court of Illinois, 2006)
Baxter v. Aslansan
859 A.2d 57 (Connecticut Appellate Court, 2004)
Irving v. Firehouse Associates, LLC
846 A.2d 918 (Connecticut Appellate Court, 2004)
MJM Landscaping, Inc. v. Lorant
845 A.2d 382 (Supreme Court of Connecticut, 2004)
Messeka Sheet Metal v. Hodder
845 A.2d 646 (New Jersey Superior Court App Division, 2004)
Larobina v. Home Depot, USA, Inc.
821 A.2d 283 (Connecticut Appellate Court, 2003)
MacMillan v. Higgins
822 A.2d 246 (Connecticut Appellate Court, 2003)
Del Vento, Inc. v. Braca, No. Cv00 037 56 93s (Mar. 20, 2003)
2003 Conn. Super. Ct. 3512 (Connecticut Superior Court, 2003)
Tang v. Bou-Fakhreddine
815 A.2d 1276 (Connecticut Appellate Court, 2003)
Sawyer v. Arnold, No. Cv96 033 71 09s (Jan. 28, 2003)
2003 Conn. Super. Ct. 1636 (Connecticut Superior Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
733 A.2d 172, 249 Conn. 155, 1999 Conn. LEXIS 152, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meadows-v-higgins-conn-1999.