Wright Bros. Builders, Inc. v. Dowling

720 A.2d 235, 247 Conn. 218, 1998 Conn. LEXIS 393
CourtSupreme Court of Connecticut
DecidedNovember 3, 1998
DocketSC 15741
StatusPublished
Cited by48 cases

This text of 720 A.2d 235 (Wright Bros. Builders, Inc. v. Dowling) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wright Bros. Builders, Inc. v. Dowling, 720 A.2d 235, 247 Conn. 218, 1998 Conn. LEXIS 393 (Colo. 1998).

Opinion

Opinion

BERDON, J.

The dispositive issue in this certified appeal is whether a home improvement contract entered into by the plaintiff, Wright Brothers Builders, Inc., and the defendants, Sandra O. Dowling and her husband, Joseph A. Dowling, complied with the Home Improvement Act (HIA), General Statutes § 20-418 et seq.

[220]*220The plaintiff, a licensed home improvement contractor, instituted this action to foreclose a mechanic’s hen on property owned by Sandra Dowling.1 The plaintiff had filed the lien to secure payment for work that it performed on the residence of Sandra Dowling in accordance with a written home improvement contract (contract). In defending against foreclosure of the hen, the defendants claimed that the contract did not comply with the statutory requirements of General Statutes § 20-429 (a)2 of the HIA and, therefore, could not be enforced by an action for foreclosure of the lien or by any other means.

The attorney trial referee to whom the matter was initially referred in accordance with General Statutes § 52-434 (a) (4) and Practice Book § 19-1 et seq., formerly § 428 et seq., concluded (1) that the contract complied with the HIA and (2) that even if the contract failed to comply with the HIA, the defendants were precluded by their own bad faith from invoking the HIA as a defense to the contract. In accordance with his [221]*221findings, the attorney trial referee recommended judgment for the plaintiff in the amount of $101,275. The trial court rejected the attorney trial referee’s recommendations, finding that (1) the contract violated § 20-429 (a), and (2) there was insufficient evidence of bad faith to preclude the defendants from invoking the HIA as a defense to the contract. Consequently, the trial court rendered judgment in favor of the defendants.

On appeal to the Appellate Court, the judgment was affirmed in a per curiam decision. Wright Bros. Builders, Inc. v. Dowling, 45 Conn. App. 918, 694 A.2d 46 (1997). We granted the plaintiffs petition for certification limited to the following two issues: (1) “Did the Appellate Court properly affirm the trial court’s decision overruling the attorney trial referee’s conclusion that the agreement between the plaintiff and the defendants complied with [the HIA], General Statutes (Rev. to 1993) § 20-429 (a) (6);3 if so, did the Appellate Court also properly affirm the trial court’s conclusion that the plaintiff is not entitled to recover under its claim of unjust enrichment?”; and (2) “Did the Appellate Court properly affirm the trial court’s decision overruling the attorney trial referee’s conclusion that the defendants’ bad faith precluded their invocation of [the HIA] as a basis for repudiating the contract?” Wright Bros. Builders, Inc. v. Dowling, 242 Conn. 914, 914-15, 697 A.2d [222]*222369 (1997). We conclude that the contract complied with § 20-429 (a) (6) and, therefore, we do not address either the second part of the first certified question or the second certified question.

The attorney trial referee found the following facts, which are not in dispute. “The plaintiff is a licensed home improvement contractor engaged in the business of constructing residential and commercial structures. . . . Sandra Dowling is the record owner of the premises located at 13 Hitchcock Road, Westport, Connecticut, where she resides with her husband . . . Joseph Dowling.

“After several months of preliminary design and estimating work, the parties entered into the agreement dated January 11, 1993. The agreement provided that [the] plaintiff would renovate approximately 2817 square feet of the defendants’ house and construct an addition of approximately 3500 square feet. The plaintiff was to be paid on a cost plus basis (10 percent for overhead and 7 percent for profit), and the preliminary budget was set at $528,360. Although [Sandra] Dowling was the record owner, [Joseph] Dowling represented the two in all substantive dealings with [the] plaintiff.

“Work began on the project in February, 1993. Thereafter, the defendants initiated a number of changes and upgrades, which raised the total contract budget to $875,579 as of August 30,1993. Leading up to that point there had been a great deal of communication between the parties, and [the] plaintiff regularly updated [the] defendants regarding the cost and progress of the work. This information was conveyed orally, in correspondence and in periodic billings.

“Problems commenced when the work was nearing completion. After receiving billing no. 7, dated August 30,1993, which showed the revised budget of $875,579, [Joseph] Dowling expressed concerns about the cost of [223]*223the job. Whereas before [the] defendants had promptly paid [the] plaintiffs billings, they failed to pay billing no. 7 in a timely fashion. On September 20, 1993, [Joseph] Dowling and Kelly M. Wright, [the] plaintiffs president, signed a one page document entitled ‘Amendment to Contract dated 11 January, 1993 . . . .’ Among other things, [the amendment] provided that:

“ ‘1. Contractor agrees to finish Project at 13 Hitchcock Road, Westport, CT for a final guaranteed price of $835,579. . . .

“ ‘7. There will be no change in the plans for construction and no alteration of material. The house will be delivered to Owner in “Turnkey” condition. . . .

“ ‘9. The final payment ($67,474) shall be due sixty days after the issuance of Certificate of Occupancy and the approval of said work by the architect whose approval will not be unreasonably withheld. Builder agrees to assist Owner in preparing documents necessary for financing. . . .

“ ‘11. Owner will pay $75,000 towards Contract upon signing of this Agreement. . . .’

“Pursuant to this amendment, the [defendants] paid $75,000 to [the] plaintiff. Thereafter, the project was completed. [The] [p]laintiff claims that $141,275 is due, whereas [the] defendants claim only $67,474 is [owing], [The] [p]laintiff seeks the larger amount because it claims the scope of work was enlarged by the owner after the signing of the amendment. As a result, when [the] defendants tendered $67,474 in full and final settlement, [the] plaintiff refused the tender.”

In January, 1994, the plaintiff filed a multicount complaint4 against the defendants seeking, in part, to foreclose on the mechanic’s lien it had filed on Sandra [224]*224Dowling’s property. In the defendants’ answer, they interposed a special defense5 claiming that the contract failed to comply with General Statutes § 42-135a (2) and (3) of the Home Solicitation Sales Act (HSSA),6 the requirements of which are incorporated into § 20-429 (a) (6) of the HIA.

[225]*225The attorney trial referee, having found that the contract complied with the HIA, recommended judgment in the amount of $101,275 on the plaintiffs breach of contract claim, together with a dismissal of the defendants’ counterclaim.7 I*****7 The plaintiff moved that the trial court accept the attorney trial referee’s recommended ruling with respect to the award of monetary damages, but at the same time filed certain exceptions to the ruling.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meribear Productions, Inc. v. Frank
340 Conn. 711 (Supreme Court of Connecticut, 2021)
DeMattio v. Plunkett
199 Conn. App. 693 (Connecticut Appellate Court, 2020)
Connecticut Home Health Services, LLC v. Futterleib
160 A.3d 352 (Connecticut Appellate Court, 2017)
Burns v. Adler
155 A.3d 1223 (Supreme Court of Connecticut, 2017)
Ippolito v. Olympic Construction, LLC
Connecticut Appellate Court, 2016
Flodman v. Robinson
Nebraska Court of Appeals, 2015
Walpole Woodworkers, Inc. v. Manning
11 A.3d 165 (Connecticut Appellate Court, 2011)
ANDY'S OIL SERVICE, INC. v. Hobbs
9 A.3d 433 (Connecticut Appellate Court, 2010)
Blacker v. Crapo
964 A.2d 1241 (Connecticut Appellate Court, 2009)
Hees v. Burke Construction Inc.
961 A.2d 373 (Supreme Court of Connecticut, 2009)
New England Custom Concrete, LLC v. Carbone
927 A.2d 333 (Connecticut Appellate Court, 2007)
Economos v. Liljedahl Bros., Inc.
901 A.2d 1198 (Supreme Court of Connecticut, 2006)
D' Angelo Development & Construction Co. v. Cordovano
897 A.2d 81 (Supreme Court of Connecticut, 2006)
MJM Landscaping, Inc. v. Lorant
845 A.2d 382 (Supreme Court of Connecticut, 2004)
Pools By Murphy & Sons, Inc. v. Department of Consumer Protection
841 A.2d 292 (Connecticut Superior Court, 2003)
MacMillan v. Higgins
822 A.2d 246 (Connecticut Appellate Court, 2003)
State v. Courchesne
816 A.2d 562 (Supreme Court of Connecticut, 2003)
Chaves v. Arthur, No. Cv02 039 08 89 S (Feb. 20, 2003)
2003 Conn. Super. Ct. 2578-a (Connecticut Superior Court, 2003)
MacKie v. Hull, No. Cv 98-0078427s (Jan. 15, 2003)
2003 Conn. Super. Ct. 524 (Connecticut Superior Court, 2003)
Schwartz v. Singer, No. Cv 00-0083763 S (Jan. 10, 2003)
2003 Conn. Super. Ct. 251 (Connecticut Superior Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
720 A.2d 235, 247 Conn. 218, 1998 Conn. LEXIS 393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wright-bros-builders-inc-v-dowling-conn-1998.