DeMattio v. Plunkett

199 Conn. App. 693
CourtConnecticut Appellate Court
DecidedAugust 25, 2020
DocketAC41283
StatusPublished
Cited by6 cases

This text of 199 Conn. App. 693 (DeMattio v. Plunkett) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DeMattio v. Plunkett, 199 Conn. App. 693 (Colo. Ct. App. 2020).

Opinion

*********************************************** The “officially released” date that appears near the be- ginning of each opinion is the date the opinion will be pub- lished in the Connecticut Law Journal or the date it was released as a slip opinion. The operative date for the be- ginning of all time periods for filing postopinion motions and petitions for certification is the “officially released” date appearing in the opinion.

All opinions are subject to modification and technical correction prior to official publication in the Connecticut Reports and Connecticut Appellate Reports. In the event of discrepancies between the advance release version of an opinion and the latest version appearing in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports, the latest version is to be considered authoritative.

The syllabus and procedural history accompanying the opinion as it appears in the Connecticut Law Journal and bound volumes of official reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be reproduced and distributed without the express written permission of the Commission on Official Legal Publica- tions, Judicial Branch, State of Connecticut. *********************************************** ARTHUR M. DEMATTIO v. ROBERT PLUNKETT ET AL. (AC 41283) Moll, Devlin and Pellegrino, Js.*

Syllabus

The plaintiff, who had been hired by the defendants to perform certain home construction site work, sought to recover damages for, inter alia, breach of contract, after the defendants failed to make an installment payment under the parties’ contract. The contract set forth a schedule of six installment payments. Work was scheduled to begin on March 9, 2015, and was to be completed on May 11, 2015. As a result of delays, work did not begin until May, 2015. In October, 2015, the plaintiff ceased working for the defendants; the plaintiff maintained that he was termi- nated whereas the defendants claimed the plaintiff walked off the job. The plaintiff claimed he was entitled to the fourth installment payment. The defendants then hired V Co. to complete the work. The plaintiff thereafter brought the present action seeking damages for the defen- dants’ failure to remit the fourth installment payment. The defendants filed a counterclaim. Following a trial to the court, the trial court ren- dered judgment for the defendants on the complaint and on their counter- claim, from which the plaintiff appealed to this court. Held: 1. The trial court properly determined that the contract violated the Home Improvement Act (§ 20-418 et seq.) and was unenforceable against the defendants; the plaintiff failed to follow the statutorily (§ 42-135a (1) and (2)) prescribed language and form for the cancellation notice in the contract and failed to furnish the defendants with a detachable notice of cancellation as required by § 42-135a (2) and (3), and these failures amounted to material noncompliance with the act. 2. The trial court’s finding that the plaintiff caused the delay in the completion of the work was not clearly erroneous; the court had before it the testimony of the defendants’ expert regarding the percentage of work completed by the plaintiff and how much work was left to complete, which the court was free to credit, and the court did not have to credit the plaintiff’s testimony regarding his reasons for the project’s delay. 3. This court declined to review the plaintiff’s inadequately briefed claim that the trial court improperly refused to admit certain evidence proffered by the plaintiff; the plaintiff failed to identify with any specificity the exhibits he claims were improperly excluded and did not provide any legally relevant analysis as to why the court’s alleged refusal to admit certain evidence was error. 4. The trial court’s finding that the defendants did not receive a copy of the cancellation notice was not clearly erroneous; the court reasonably could have credited the defendant homeowner’s testimony and it was within its province as trier of fact to make credibility determinations and to find the homeowner credible and the plaintiff not credible. 5. This court declined to review the plaintiff’s unpreserved claim that the trial court should not have permitted the defendants’ expert witness to testify because he was not qualified as an expert; the plaintiff did not file a motion in limine to preclude or limit the testimony of that witness nor did he object to the witness’ testimony at trial. 6. The plaintiff could not prevail on his claim that the trial court failed to consider the defendants’ duty to mitigate their damages; the defendants promptly sought of the services of V Co. to complete the work and the court expressly credited the testimony of the defendants’ expert with respect to the amount of work necessary to complete the project and it implicitly found the expert’s estimates and V Co.’s pricing reasonable by virtue of its damages calculation; moreover, the burden of proving the defendants’ purported failure to mitigate rested with the plaintiff and he failed to present evidence beyond his argument that the pricing of V Co., the company the defendants hired to complete the work, was unreasonable. 7. The plaintiff could not prevail on his claim that the trial court erred with respect to its calculation of damages; the court’s damages calculations were supported by the evidence, and the court properly subtracted the unpaid balance due on the plaintiff’s contract from the adjusted cost of completion based on V Co.’s estimate, to come to the total actual loss that it awarded in damages to the defendants. 8. There was no merit to the plaintiff’s unpreserved claim of judicial bias and, under a comprehensive review of the record, reversal under the plain error doctrine was not appropriate. Argued October 22, 2019—officially released August 25, 2020

Procedural History

Action to recover damages for, inter alia, breach of contract, and for other relief, brought to the Superior Court in the judicial district of Stamford-Norwalk, where the defendants filed a counterclaim; thereafter, the matter was tried to the court, Hon. A. William Mottolese, judge trial referee; judgment for the defen- dants on the complaint and on the counterclaim, from which the plaintiff appealed to this court. Affirmed. Arthur M. DeMattio, self-represented, the appellant (plaintiff). Gregory J. Williams, with whom, on the brief, was Todd H. Lampert, for the appellees (defendants). Opinion

MOLL, J. The self-represented plaintiff contractor, Arthur M. DeMattio, appeals from the judgment of the trial court, rendered following a bench trial, in favor of the defendant homeowners, Robert Plunkett and Karen Plunkett, on the plaintiff’s complaint and the defen- dants’ counterclaim in the amount of $21,720.34. On appeal, the plaintiff’s claims distill to whether the trial court erred by (1) concluding that the home improve- ment contract entered into among the parties (contract) was invalid and unenforceable against the defendants as a result of the contract’s noncompliance with the Home Improvement Act (HIA), General Statutes § 20- 418 et seq., (2) making numerous factual findings con- trary to the evidence presented at trial, (3) failing to determine that the defendants did not mitigate their damages, (4) improperly calculating its damages award, and (5) acting in a biased manner toward the plaintiff.1 We affirm the judgment of the trial court. The trial court found the following facts. On January 12, 2015, the plaintiff and the defendants entered into the contract for the purpose of remodeling, and building an addition to, the defendants’ kitchen. The contract price totaled $86,300, to be paid in six installments throughout the course of the renovations. Pursuant to the contract, the start date was March 9, 2015, with a completion date of May 11, 2015.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Villwell Builders I, LLC v. Pereira
Connecticut Appellate Court, 2026
New Milford v. Standard Demolition Services, Inc.
212 Conn. App. 30 (Connecticut Appellate Court, 2022)
Mecartney v. Mecartney
206 Conn. App. 243 (Connecticut Appellate Court, 2021)
Johnson v. Johnson
203 Conn. App. 405 (Connecticut Appellate Court, 2021)
Batista v. Cortes
203 Conn. App. 365 (Connecticut Appellate Court, 2021)
A & R Enterprises, LLC v. Sentinel Ins. Co., Ltd.
202 Conn. App. 224 (Connecticut Appellate Court, 2021)
Costanzo v. Plainfield
200 Conn. App. 755 (Connecticut Appellate Court, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
199 Conn. App. 693, Counsel Stack Legal Research, https://law.counselstack.com/opinion/demattio-v-plunkett-connappct-2020.