Villwell Builders I, LLC v. Pereira

CourtConnecticut Appellate Court
DecidedJanuary 6, 2026
DocketAC48053
StatusPublished

This text of Villwell Builders I, LLC v. Pereira (Villwell Builders I, LLC v. Pereira) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Villwell Builders I, LLC v. Pereira, (Colo. Ct. App. 2026).

Opinion

************************************************ The “officially released” date that appears near the beginning of an opinion is the date the opinion will be published in the Connecticut Law Journal or the date it is released as a slip opinion. The operative date for the beginning of all time periods for the filing of postopin- ion motions and petitions for certification is the “offi- cially released” date appearing in the opinion. All opinions are subject to modification and technical correction prior to official publication in the Connecti- cut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports. In the event of discrepancies between the advance release version of an opinion and the version appearing in the Connecti- cut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports, the latest version is to be considered authoritative. The syllabus and procedural history accompanying an opinion that appear in the Connecticut Law Jour- nal and subsequently in the Connecticut Reports or Connecticut Appellate Reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be reproduced or distributed without the express written permission of the Commission on Official Legal Publications, Judicial Branch, State of Connecticut. ************************************************ Page 0 CONNECTICUT LAW JOURNAL 0, 0

2 ,0 0 Conn. App. 1 Villwell Builders I, LLC v. Pereira

VILLWELL BUILDERS I, LLC v. PHIL PEREIRA ET AL. VILLWELL BUILDERS I, LLC v. ANDREW BIAGIONI ET AL. VILLWELL BUILDERS I, LLC v. JULIA WEXLER VILLWELL BUILDERS I, LLC v. KARRIE SADLER (AC 48053) Clark, Seeley and Eveleigh, Js.

Syllabus

The plaintiff home improvement contractor appealed from the trial court’s judgments for the defendant condominium owners on their respective coun- terclaims for breach of contract and negligence. The plaintiff had com- menced a separate action for, inter alia, breach of contract against the owners of each of four condominium units following the owners’ termination of contracts to construct decks for their units. Prior to trial, the plaintiff withdrew its complaint in each case, and the court consolidated the cases for trial on the defendants’ counterclaims. On appeal, the plaintiff claimed, inter alia, that the court improperly found that it had materially breached the contracts it had entered with the respective defendants. Held:

The trial court’s finding that the plaintiff had materially breached the con- tracts was not clearly erroneous, as the court’s finding that the delay in construction was a material breach was supported by the evidence in the record even though the contracts did not specifically provide that time was of the essence in the completion of the construction projects.

The trial court improperly calculated the amount of damages that the defen- dants could recover on their breach of contract counterclaims because the defendants did not incur losses for which they could recover in contract, as the court expressly found that no defendant paid more than the original contract price for the completion of the work called for under the contracts, and, accordingly, this court vacated the damages awards and remanded the cases with direction to enter awards of nominal damages on the breach of contract counterclaims.

To the extent that the trial court’s damages awards included any amounts attributable to its finding that the plaintiff breached the implied covenant of good faith and fair dealing, the court erred in issuing those awards, as the defendants neither pleaded a claim for such a breach or alleged conduct 0, 0 CONNECTICUT LAW JOURNAL Page 1

0 Conn. App. 1 ,0 3 Villwell Builders I, LLC v. Pereira by the plaintiff that would support such a claim, and, accordingly, this court vacated any such damages awards.

Argued September 15, 2025—officially released January 6, 2026

Procedural History

Action, in each of four cases, to recover damages for, inter alia, breach of contract, and for other relief, brought to the Superior Court in the judicial district of Waterbury, where the defendants filed counterclaims; thereafter, the court, Cordani, J., granted the defen- dants’ motion to consolidate the cases for trial; subse- quently, in each case, the plaintiff withdrew its com- plaint; thereafter, the cases were tried to the court, M. Rodriguez, J.; subsequently, the court, M. Rodriguez, J., recused itself; thereafter, in each case, the court, Cordani, J., rendered judgment in part for the defen- dants on their counterclaim, from which the plaintiff appealed to this court. Reversed in part; judgments directed. Michael S. Wrona, for the appellant (plaintiff). Eddi Z. Zyko, for the appellees (defendants). Opinion

CLARK, J. The present appeal arises out of four sepa- rate actions commenced by the plaintiff home improve- ment contractor, Villwell Builders I, LLC, against the defendant condominium owners, Linda Biagioni, Andrew Biagioni, Phil Pereira, Gina Pereira, Karrie Sadler and Julia Wexler. The four cases were consolidated for trial. The plaintiff appeals from the judgments rendered by the trial court in favor of the defendants on their respec- tive counterclaims for breach of contract and negli- gence. On appeal, the plaintiff claims that the court improperly (1) found that the plaintiff materially breached the contracts by and between the plaintiff and the respective defendants regarding certain construction Page 2 CONNECTICUT LAW JOURNAL 0, 0

4 ,0 0 Conn. App. 1 Villwell Builders I, LLC v. Pereira

work to be completed on their condominiums; (2) calcu- lated damages on the breach of contract counterclaims; and (3) found that the plaintiff breached the implied covenant of good faith and fair dealing and awarded damages on the claim when no such claim was pleaded.1 We conclude that, although the trial court’s finding that the plaintiff breached the contracts was not clearly erroneous, it improperly calculated damages for the breach of contract counterclaims. We therefore reverse the judgments of the trial court as to the awards of damages, vacate those awards, and remand the cases with direction to award nominal damages to the defen- dants on their breach of contract counterclaims. The following facts and procedural history are rele- vant to the resolution of this appeal. The plaintiff is a home improvement contractor licensed in Connecticut. The defendants own condominiums in Beach Shore Village in Milford. Between October, 2020, and May, 2021, the plaintiff entered into four separate written contracts with each of the defendant condominium owners pursuant to which the plaintiff promised to provide materials and services for the construction of a second floor deck and an entrance and door leading from the interior of each of the four condominiums to the newly constructed decks. The contracts each included the following provision: ‘‘Work shall com- mence on TBD and shall be completed by within [thirty] The plaintiff also claims that the court erred in awarding inconvenience 1

damages on the defendants’ negligence counterclaims. Although the court rendered judgment in each case on both the breach of contract and negli- gence counterclaims and stated that it was awarding damages in the ‘‘aggre- gate,’’ it is clear from the memoranda of decision that the court awarded damages only on the breach of contract counterclaims. The court found that the proper measure of damages on the breach of contract claims was ‘‘equal to the amount of money paid by the [defendants] to [the plaintiff]’’ and, in each case, rendered judgment in the amount they paid the plaintiff under the respective contracts. See footnote 4 of this opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stamford Landing Condominium Ass'n v. Lerman
951 A.2d 642 (Connecticut Appellate Court, 2008)
Hees v. Burke Construction Inc.
961 A.2d 373 (Supreme Court of Connecticut, 2009)
Lydall, Inc. v. Ruschmeyer
919 A.2d 421 (Supreme Court of Connecticut, 2007)
O & G Industries, Inc. v. All Phase Enterprises, Inc.
963 A.2d 676 (Connecticut Appellate Court, 2009)
Willamette Management Associates, Inc. v. Palczynski
38 A.3d 1212 (Connecticut Appellate Court, 2012)
Northeast Electrical Contractors v. Udolf
469 A.2d 419 (Connecticut Appellate Court, 1983)
Bruno v. Whipple
199 A.3d 604 (Connecticut Appellate Court, 2018)
DeMattio v. Plunkett
199 Conn. App. 693 (Connecticut Appellate Court, 2020)
Regional School District 8 v. M & S Paving & Sealing, Inc.
206 Conn. App. 523 (Connecticut Appellate Court, 2021)
Bernstein v. Nemeyer
570 A.2d 164 (Supreme Court of Connecticut, 1990)
Christophersen v. Blount
582 A.2d 460 (Supreme Court of Connecticut, 1990)
Mihalyak v. Mihalyak
529 A.2d 213 (Connecticut Appellate Court, 1987)
669 Atlantic Street Associates v. Atlantic-Rockland Stamford Associates
682 A.2d 572 (Connecticut Appellate Court, 1996)
Strouth v. Pools by Murphy & Sons, Inc.
829 A.2d 102 (Connecticut Appellate Court, 2003)
Shah v. Cover-It, Inc.
859 A.2d 959 (Connecticut Appellate Court, 2004)
TD Bank, N.A. v. J & M Holdings, LLC
70 A.3d 156 (Connecticut Appellate Court, 2013)
Ray Weiner, LLC v. Connery
75 A.3d 771 (Connecticut Appellate Court, 2013)
Fezollari v. Jauzovic
232 Conn. App. 20 (Connecticut Appellate Court, 2025)
United Cleaning & Restoration, LLC v. Koskerides
234 Conn. App. 401 (Connecticut Appellate Court, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
Villwell Builders I, LLC v. Pereira, Counsel Stack Legal Research, https://law.counselstack.com/opinion/villwell-builders-i-llc-v-pereira-connappct-2026.