Opinion
NORCOTT, J.
The principal issue in this appeal is whether a violation of the Home Improvement Act (act), General Statutes § 20-418 et seq., and specifically, Gen[3]*3eral Statutes § 20-429 (a),1 precludes a home improvement contractor from reducing the damages that it owes for breach of contract to a nonbreaching homeowner by an amount equal to the unpaid balance remaining on the contract. The defendant, Burke Construction, Inc., appeals from the judgment of the trial court,2 accepting the report of the attorney trial referee, David Albert (referee), which found that the defendant had breached its contract with the plaintiff homeowners, Gerald Hees and Beatrice Hees, and recommended a damages award in the amount of $16,085.17.3 On appeal, the defendant claims that the referee improperly calculated the plaintiffs’ damages award. Specifically, the defendant claims that, although the failure of a home improvement contract to comply with § 20-429 (a) renders that contract unenforceable against a homeowner, § 20-429 (a) nevertheless does not preclude a contractor from reducing a damages award against it by the unpaid contract balance, in an action brought by the homeowner against the contractor. The defendant further claims that, when the award in this case is so reduced, the plaintiffs have not suffered any actual damages for [4]*4which they can recover. We agree with the defendant, and, accordingly, we reverse the judgment of the trial court.
The record reveals the following relevant facts and procedural history. The parties entered into a written home improvement contract on June 1, 2002, the terms of which provided that the defendant would provide various home improvement services and materials for $349,500. The original terms of the contract were changed periodically through the execution of thirty different change orders, which increased the price for the project by $42,354, to a total of $391,854. The terms of the contract required the plaintiffs to make monthly requisition payments for work already completed, the first nine of which the plaintiffs made in a timely fashion. The plaintiffs failed, however, to make the tenth requisition payment within thirty days, as required by the contract. By letter dated May 19,2003, the defendant advised the plaintiffs that it intended to terminate the contract, in accordance with its terms, if payment was not received within one week. Thereafter, the plaintiffs did not pay the defendant, which then terminated the contract on May 29, 2003. At the time of termination, the defendant had completed and billed the plaintiffs for $346,378 worth of work,4 in addition to $625 for which the plaintiffs were not billed. The plaintiffs, however, had only paid the defendant $330,531, which left an unpaid balance on the contract for work already performed of $16,472.5
The plaintiffs thereafter brought this action, alleging that the defendant had breached the contract by failing [5]*5to complete all of the work, and by performing some of that work in a defective manner. The complaint did not contain any reference to the act, nor did it assert a claim under the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes § 42-110a et seq. The defendant filed three counterclaims, seeking money damages for breach of contract, quantum meruit and foreclosure of its mechanic’s lien.
The court referred the case to the referee, who, after conducting a hearing, filed a report finding in favor of the plaintiffs with regard to both the breach of contract claim6 and the defendant’s three counterclaims. The referee concluded that, because the contract did not contain a right of rescission clause, it was unenforceable against the plaintiffs under § 20-429 (a) (6), and the defendant was, therefore, precluded from seeking recovery under the contract. The referee found that the plaintiffs had incurred $16,085.17 in costs to complete and repair the work, and recommended that judgment be rendered in favor of the plaintiffs in that amount. In so recommending, the referee declined the defendant’s request to reduce the damages award commensurate with the unpaid balance on the contract, namely, $16,472, on the ground that such an offset was precluded by the defendant’s violation of § 20-429 (a) (6).7 [6]*6The trial court accepted the referee’s report and rendered judgment for the plaintiffs. This appeal followed.
On appeal, the defendant contends that the plaintiffs’ damages award should have been reduced by an amount equal to the unpaid balance remaining on the contract, because, under traditional contract damages law, the appropriate measure of damages in a construction contract case is the plaintiffs’ reasonable cost to complete or repair the work, less the unpaid balance on the contract. The defendant further contends that the trial court improperly accepted the referee’s conclusion that a violation of § 20-429 (a) serves to alter this well established principle of contract damages law. We agree with the defendant in both respects, and conclude, therefore, that the referee improperly failed to reduce the plaintiffs’ damages by the unpaid balance remaining on the contract.
We begin by determining the appropriate standard of review. “While the reports of [attorney trial referees] . . . are essentially of an advisory nature, it has not been the practice to disturb their findings when they are properly based upon evidence, in the absence of errors of law, and the parties have no right to demand that the court shall redetermine the fact[s] thus found. ...
“A reviewing authority may not substitute its findings for those of the trier of the facts. This principle applies no matter whether the reviewing authority is the Supreme Court . . . the Appellate Court ... or the [7]*7Superior Court reviewing the findings of . . . attorney trial referees. . . . This court has articulated that attorney trial referees and factfinders share the same function . . . whose determination of the facts is reviewable in accordance with well established procedures prior to the rendition of judgment by the court.
“Although it is true that when the trial court reviews the attorney trial referee’s report the trial court may not retry the case and pass on the credibility of the witnesses, the trial court must review the referee’s entire report to determine whether the recommendations contained in it are supported by findings of fact in the report. . . .
“Finally, we note that, because the attorney trial referee does not have the powers of a court and is simply a fact finder, [a]ny legal conclusions reached by an attorney trial referee have no conclusive effect. . . . The reviewing court is the effective arbiter of the law and the legal opinions of [an attorney trial referee], like those of the parties, though they may be helpful, carry no weight not justified by their soundness as viewed by the court that renders judgment. . . . Where legal conclusions are challenged, we must determine whether they are legally and logically correct and whether they find support in the facts found by the . . . referee.” (Citations omitted; internal quotation marks omitted.) Alliance Partners, Inc. v. Oxford Health Plans, Inc., 263 Conn. 191, 201-202, 819 A.2d 227 (2003).
I
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion
NORCOTT, J.
The principal issue in this appeal is whether a violation of the Home Improvement Act (act), General Statutes § 20-418 et seq., and specifically, Gen[3]*3eral Statutes § 20-429 (a),1 precludes a home improvement contractor from reducing the damages that it owes for breach of contract to a nonbreaching homeowner by an amount equal to the unpaid balance remaining on the contract. The defendant, Burke Construction, Inc., appeals from the judgment of the trial court,2 accepting the report of the attorney trial referee, David Albert (referee), which found that the defendant had breached its contract with the plaintiff homeowners, Gerald Hees and Beatrice Hees, and recommended a damages award in the amount of $16,085.17.3 On appeal, the defendant claims that the referee improperly calculated the plaintiffs’ damages award. Specifically, the defendant claims that, although the failure of a home improvement contract to comply with § 20-429 (a) renders that contract unenforceable against a homeowner, § 20-429 (a) nevertheless does not preclude a contractor from reducing a damages award against it by the unpaid contract balance, in an action brought by the homeowner against the contractor. The defendant further claims that, when the award in this case is so reduced, the plaintiffs have not suffered any actual damages for [4]*4which they can recover. We agree with the defendant, and, accordingly, we reverse the judgment of the trial court.
The record reveals the following relevant facts and procedural history. The parties entered into a written home improvement contract on June 1, 2002, the terms of which provided that the defendant would provide various home improvement services and materials for $349,500. The original terms of the contract were changed periodically through the execution of thirty different change orders, which increased the price for the project by $42,354, to a total of $391,854. The terms of the contract required the plaintiffs to make monthly requisition payments for work already completed, the first nine of which the plaintiffs made in a timely fashion. The plaintiffs failed, however, to make the tenth requisition payment within thirty days, as required by the contract. By letter dated May 19,2003, the defendant advised the plaintiffs that it intended to terminate the contract, in accordance with its terms, if payment was not received within one week. Thereafter, the plaintiffs did not pay the defendant, which then terminated the contract on May 29, 2003. At the time of termination, the defendant had completed and billed the plaintiffs for $346,378 worth of work,4 in addition to $625 for which the plaintiffs were not billed. The plaintiffs, however, had only paid the defendant $330,531, which left an unpaid balance on the contract for work already performed of $16,472.5
The plaintiffs thereafter brought this action, alleging that the defendant had breached the contract by failing [5]*5to complete all of the work, and by performing some of that work in a defective manner. The complaint did not contain any reference to the act, nor did it assert a claim under the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes § 42-110a et seq. The defendant filed three counterclaims, seeking money damages for breach of contract, quantum meruit and foreclosure of its mechanic’s lien.
The court referred the case to the referee, who, after conducting a hearing, filed a report finding in favor of the plaintiffs with regard to both the breach of contract claim6 and the defendant’s three counterclaims. The referee concluded that, because the contract did not contain a right of rescission clause, it was unenforceable against the plaintiffs under § 20-429 (a) (6), and the defendant was, therefore, precluded from seeking recovery under the contract. The referee found that the plaintiffs had incurred $16,085.17 in costs to complete and repair the work, and recommended that judgment be rendered in favor of the plaintiffs in that amount. In so recommending, the referee declined the defendant’s request to reduce the damages award commensurate with the unpaid balance on the contract, namely, $16,472, on the ground that such an offset was precluded by the defendant’s violation of § 20-429 (a) (6).7 [6]*6The trial court accepted the referee’s report and rendered judgment for the plaintiffs. This appeal followed.
On appeal, the defendant contends that the plaintiffs’ damages award should have been reduced by an amount equal to the unpaid balance remaining on the contract, because, under traditional contract damages law, the appropriate measure of damages in a construction contract case is the plaintiffs’ reasonable cost to complete or repair the work, less the unpaid balance on the contract. The defendant further contends that the trial court improperly accepted the referee’s conclusion that a violation of § 20-429 (a) serves to alter this well established principle of contract damages law. We agree with the defendant in both respects, and conclude, therefore, that the referee improperly failed to reduce the plaintiffs’ damages by the unpaid balance remaining on the contract.
We begin by determining the appropriate standard of review. “While the reports of [attorney trial referees] . . . are essentially of an advisory nature, it has not been the practice to disturb their findings when they are properly based upon evidence, in the absence of errors of law, and the parties have no right to demand that the court shall redetermine the fact[s] thus found. ...
“A reviewing authority may not substitute its findings for those of the trier of the facts. This principle applies no matter whether the reviewing authority is the Supreme Court . . . the Appellate Court ... or the [7]*7Superior Court reviewing the findings of . . . attorney trial referees. . . . This court has articulated that attorney trial referees and factfinders share the same function . . . whose determination of the facts is reviewable in accordance with well established procedures prior to the rendition of judgment by the court.
“Although it is true that when the trial court reviews the attorney trial referee’s report the trial court may not retry the case and pass on the credibility of the witnesses, the trial court must review the referee’s entire report to determine whether the recommendations contained in it are supported by findings of fact in the report. . . .
“Finally, we note that, because the attorney trial referee does not have the powers of a court and is simply a fact finder, [a]ny legal conclusions reached by an attorney trial referee have no conclusive effect. . . . The reviewing court is the effective arbiter of the law and the legal opinions of [an attorney trial referee], like those of the parties, though they may be helpful, carry no weight not justified by their soundness as viewed by the court that renders judgment. . . . Where legal conclusions are challenged, we must determine whether they are legally and logically correct and whether they find support in the facts found by the . . . referee.” (Citations omitted; internal quotation marks omitted.) Alliance Partners, Inc. v. Oxford Health Plans, Inc., 263 Conn. 191, 201-202, 819 A.2d 227 (2003).
I
We begin our analysis by briefly addressing the defendant’s first claim, namely, that the trial court improperly accepted the referee’s report because the referee failed to use an appropriate method to calculate the plaintiffs’ damages. “It is axiomatic that the sum of damages awarded as compensation in a breach of contract action [8]*8should place the injured party in the same position as he would have been in had the contract been performed. . . . The injured party, however, is entitled to retain nothing in excess of that sum which compensates him for the loss of his bargain. . . . Guarding against excessive compensation, the law of contract damages limits the injured party to damages based on his actual loss caused by the breach. . . . The concept of actual loss accounts for the possibility that the breach itself may result in a saving of some cost that the injured party would have incurred if he had had to perform. ... In such circumstances, the amount of the cost saved will be credited in favor of the wrongdoer . . . that is, subtracted from the loss . . . caused by the breach in calculating [the injured party’s] damages. . . . It is on this ground that . . . when an owner receives a defective or incomplete building, any part of the price that is as yet unpaid is deducted from the cost of completion that is awarded to him .... Otherwise, the owner would be placed in a better position than full performance would have put him, thereby doubly compensating him for the injury occasioned by the breach.” (Citations omitted; internal quotation marks omitted.) Argentinis v. Gould, 219 Conn. 151, 157-58, 592 A.2d 378 (1991).
Thus, we agree with the defendant that the referee used an improper method to calculate the plaintiffs’ damages. The parties do not dispute the fact that, at the time of the breach, there remained an unpaid balance on the contract of $16,472. They also do not dispute the fact that, as a result of the breach, the plaintiffs incurred expenses to complete and repair the work in the amount of $16,085.17. Accordingly, in the absence of some legal justification for not doing so, the referee should have subtracted any unpaid amount remaining on the contract from the extra costs incurred by the plaintiffs, so as to avoid placing the plaintiffs in a better position than they would have been in had the contract been [9]*9fully performed. See id. Had the referee done so, it becomes apparent that the plaintiffs in this case have, if anything, actually saved $386.83 as a result of the defendant’s breach.8 Thus, unless § 20-429 (a) requires an alteration of the traditional approach of calculating contract damages, and prevents the defendant from reducing the plaintiffs’ damages by the outstanding balance on the contract, it cannot be said that the plaintiffs have incurred any actual loss for which they can recover.
II
We turn, then, to the principal issue in this appeal, namely, whether the trial court improperly accepted the referee’s legal conclusion that the defendant’s violation of § 20-429 (a) precluded a reduction in the plaintiffs’ damages by an amount equal to the unpaid balance on the contract. The defendant claims that there is nothing in the language of § 20-429 (a), or our cases interpreting it, that mandates an abandonment of the traditional approach to contract damages by allowing a homeowner to recover damages against a contractor when they have not, in fact, suffered any actual loss or injury. To hold otherwise, the defendant contends, would give the plaintiffs a windfall double recovery that the legislature did not intend when it passed the act. In response, the plaintiffs claim that § 20-429 (a) prohibits a contractor who has violated the act from using its own damages under the contract to offset the homeowner’s damages, since the contractor’s damages are, [10]*10standing alone, unenforceable and uncollectible. We agree with the defendant, and conclude that, in a breach of contract case brought by a homeowner against a contractor, § 20-429 (a) does not preclude a trial court from reducing the homeowner’s damages by the amount left unpaid under the contract.
Whether § 20-429 (a) precludes the defendant from reducing the plaintiffs’ damages in the present case “raises a question of statutory construction, which is a [question] of law, over which we exercise plenary review. . . . The process of statutory interpretation involves the determination of the meaning of the statutory language as applied to the facts of the case, including the question of whether the language does so apply. . . .
“When construing a statute, [o]ur fundamental objective is to ascertain and give effect to the apparent intent of the legislature. ... In other words, we seek to determine, in a reasoned manner, the meaning of the statutory language as applied to the facts of [the] case, including the question of whether the language actually does apply. ... In seeking to determine that meaning, General Statutes § l-2z directs us first to consider the text of the statute itself and its relationship to other statutes. If, after examining such text and considering such relationship, the meaning of such text is plain and unambiguous and does not yield absurd or unworkable results, extratextual evidence of the meaning of the statute shall not be considered. . . . The test to determine ambiguity is whether the statute, when read in context, is susceptible to more than one reasonable interpretation.” (Internal quotation marks omitted.) Slate v. Marsh & McLennan Cos., 286 Conn. 454, 464-65, 944 A.2d 315 (2008).
We begin our statutory analysis, then, with the language of § 20-429 (a). Section 20-429 (a) provides in [11]*11relevant part: “No home improvement contract shall be valid or enforceable against an owner unless it: (1) Is in writing, (2) is signed by the owner and the contractor, (3) contains the entire agreement between the owner and the contractor, (4) contains the date of the transaction, (5) contains the name and address of the contractor and the contractor’s registration number, (6) contains a notice of the owner’s cancellation rights in accordance with the provisions of chapter 740, (7) contains a starting date and completion date, and (8) is entered into by a registered salesman or registered contractor. ...” (Emphasis added.) We have previously concluded that this language clearly and unambiguously precludes a contractor from affirmatively seeking recovery against a homeowner on a contract that is in violation of § 20-429 (a). See, e.g., Wright Bros. Builders, Inc. v. Dowling, 247 Conn. 218, 228, 720 A.2d 235 (1998) (“[i]n construing § 20-429 [a], this court consistently has held that the requirements of that section are mandatory and that a contractor is precluded from enforcing a home improvement contract that does not satisfy its requirements”); Caulkins v. Petrillo, 200 Conn. 713, 717-18, 513 A.2d 43 (1986) (“The language of § 20-429 [a] is clear and unambiguous. . . . Read literally ... it is clear that the plain language of the statute does not provide an exception to the requirement that home improvement contracts be in writing.” [Citations omitted; internal quotation marks omitted.]). The question in the present case, however, which is a matter of first impression, is whether the legislature intended § 20-429 (a) to prohibit a contractor from in any way using the contract against the interests of the homeowner, even in the procedural context of an action brought by the homeowner against the contractor.9 The [12]*12language of the statute, however, does not indicate whether it applies exclusively to affirmative enforcement efforts by the contractor, or whether it also precludes any use of the contract against the interests of the homeowner, regardless of the procedural context. Because both readings of the statute are reasonable, we conclude that the statutory language is ambiguous in this case.
Accordingly, we now turn to an analysis of the relevant extratextual sources in order to determine the scope of § 20-429 (a). Although the legislative history of § 20-429 (a) is silent on this specific question, the history of the act, more broadly, indicates that § 20-429 (a) was intended to protect homeowners, rather than, to serve as a tool for them to enhance their own interests at the expense of contractors. Representative William P. Candelori, for example, remarked that “ [t]he purpose of the bill is to provide minimal, and I stress minimal, safeguards for the consumer who contracts for home improvement work to be done on or in the home.” 22 H.R. Proc., Pt. 33, 1979 Sess., p. 11,613. Similarly, Senator Audrey P. Beck indicated that the purpose of the bill was not only to “provide some safeguards for consumers who contract for home improvement work,” but also to benefit the majority of home improvement [13]*13contractors. 22 S. Proc., Pt. 17,1979 Sess., p. 5796. More importantly, although the legislative history is replete with references to the act’s protective nature, there is not a single instance in the legislative history of § 20-429 (a) in which the drafters even contemplated that the statute could, or should, be used by a homeowner to enhance his own damages award. Thus, we agree with the defendant that the legislative history of § 20-429 (a) does not support the plaintiffs’ contention that the act was intended to supersede established principles of contract damages, and allow a homeowner affirmatively to recover damages to which he would not otherwise be entitled.
Moreover, the only cases disclosed by our research in which § 20-429 (a) has been used offensively by a homeowner arise in the context of CUTPA claims, wherein that statute provides the basis for recovery, not § 20-429 (a) itself.10 Thus, under General Statutes [14]*14§ 20-427 (c),11 any violation of the act is aper se violation of CUTPA. See, e.g., Woronecki v. Trappe, 228 Conn. 574, 579, 637 A.2d 783 (1994). Once a violation of the act has been established, however, our cases make clear that the homeowners still must prove that they have suffered an injury or actual loss in order to recover damages under CUTPA. See, e.g., Rizzo Pool Co. v. Del Grosso, 232 Conn. 666, 684-85, 657 A.2d 1087 (1995) (denying recovery on CUTPA claim based on § 20-429 [a] because counterclaim plaintiffs “presented no evidence that they had suffered an ascertainable loss of money or property”); Woronecki v. Trappe, supra, 581-82 (remanding case to trial court to determine damages, after concluding that CUTPA violation had occurred); A. Secondino & Son, Inc. v. LoRicco, 215 Conn. 336, 343-44, 576 A.2d 464 (1990) (denying recovery on CUTPA claim on ground that homeowner had not proven any loss or injury for which he could recover); Scrivani v. Vallombroso, 99 Conn. App. 645, 653-54, 916 A.2d 827 (“[w]e do not read our law to dispense with the [proof of damages] requirement once a violation of the ... act is established”), cert. denied, 282 Conn. 904,920 A.2d 309 (2007). Our research does not disclose any CUTPA case in which our courts have either dispensed with the proof of damages requirement, or held that the traditional methods of calculating such damages should be altered by virtue of the simple fact that § 20-429 (a) serves as the basis for the CUTPA violation. Thus, if § 20-429 (a) does not affect the damages calculation in actions brought under CUTPA, we do not see [15]*15why it should alter such a calculation in an action for breach of contract.12
Furthermore, were we to agree with the plaintiffs’ position in this case, we would, in effect, award them an unwarranted windfall that the legislature could not have intended. The plaintiffs essentially claim that, not only does § 20-429 (a) relieve them of their obligation to pay the defendant for work already completed, but it also serves to punish the defendant by obligating it to reimburse the plaintiffs for any costs incurred to complete the contract, regardless of whether such costs are over and above the original contract price. Thus, according to the plaintiffs, if a contractor discovers that the contract violates § 20-429 (a) the day after it is entered into, and then immediately terminates the contract rather than risk doing work on a contract that it [16]*16cannot enforce,13 § 20-429 (a) allows the homeowner to hire another contractor to do the same work, for the same price, and then sue the original contractor to reimburse it for the entire cost of construction. Under the plaintiffs’ theory, therefore, § 20-429 (a) could be read to allow a homeowner affirmatively to obtain a free home improvement project from the contractor, rather than simply to prevent the contractor from enforcing otherwise valid claims against the homeowner. Indeed, the plaintiffs contended at oral argument before this court that, although such a result may be harsh, the act was intended to provide such a windfall to homeowners. Although § 20-429 (a) may result in a windfall to the homeowner in certain prescribed circumstances, such as its preclusion of affirmative enforcement by the contractor of otherwise valid claims under the contract, we do not believe that the legislature intended for § 20-429 (a) to provide the type or magnitude of windfall claimed by the plaintiffs herein.14
[17]*17We conclude that, in an action brought by a homeowner against a home improvement contractor for breach of contract, § 20-429 (a) does not preclude the damages award from being reduced by an amount equal to the unpaid balance remaining on the contract. Accordingly, the trial court’s acceptance of the referee’s report, which failed to reduce the damages award by that amount, was improper. Because application of this conclusion means that the plaintiffs’ damages are completely offset by the amount they owed the defendant under the contract, judgment should have been rendered in favor of the defendant.
The judgment is reversed and the case is remanded with direction to render judgment in favor of the defendant.
In this opinion ROGERS, C. J., and PALMER and ZARELLA, Js., concurred.