Bailey v. Lanou

54 A.3d 198, 138 Conn. App. 661, 2012 WL 4800972, 2012 Conn. App. LEXIS 466
CourtConnecticut Appellate Court
DecidedOctober 16, 2012
DocketAC 33632
StatusPublished
Cited by5 cases

This text of 54 A.3d 198 (Bailey v. Lanou) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bailey v. Lanou, 54 A.3d 198, 138 Conn. App. 661, 2012 WL 4800972, 2012 Conn. App. LEXIS 466 (Colo. Ct. App. 2012).

Opinion

Opinion

GRUENDEL, J.

This case is about a paved driveway. The defendant, Vernon L. Lanou, Jr.,1 appeals from the [663]*663judgment of the trial court in favor of the plaintiff, William S. Bailey. He claims that the court (1) made erroneous factual findings, (2) improperly admitted and credited the testimony of the plaintiffs expert, (3) rendered an erroneous award of damages, (4) improperly awarded the plaintiff damages pursuant to the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes § 42-110a et seq., and (6) erroneously awarded the plaintiff attorney’s fees. We dismiss for lack of a final judgment that portion of the appeal contesting the award of attorney’s fees and otherwise affirm the judgment of the trial court.

In its memorandum of decision, the court found the following relevant facts. The plaintiff owns real property known as 33 Knowles Road in Middle Haddam. The defendant is a paving contractor who employed his son, Keith Lanou, among other individuals. On August 20, 2008, Keith Lanou submitted a written proposal to the plaintiff on behalf of the defendant to construct a paved driveway and cart path on the property. That proposal stated that the defendant was a licensed home improvement contractor. On August 26, 2008, the parties entered into a written contract.2 Its plain terms provided that the defendant would excavate the existing driveway and then install a six to eight inch base of reprocessed stone for the new driveway and cart path. After permitting that base to settle for a period of one month, the new driveway was to be paved with “class II bituminous” asphalt. The contract further provided that “[a]ll material is guaranteed to be as specified, and the above work to be performed . . . and completed in a substantial workmanlike manner for the sum of . . . $25,000 . . . .” When the parties modified the contract approximately two weeks later to encompass additional work, the contractprice was increased to $31,300.

[664]*664Like the written proposal, the contract represented that the defendant was a licensed home improvement contractor, listing “CT LIC. 645061” under the defendant’s address. The court specifically found that “[t]he plaintiff relied upon the representation that the defendant was a licensed home improvement contractor. When the contract was executed and when the work was performed, the defendant was not a licensed home improvement contractor as required by law.”

The court found that “ [t]he excavation and placement of the driveway base materials was performed in September, 2008. The paving was done in October, 2008. The driveway is approximately 10,000 square feet in size. It took a number of truck loads of asphalt to pave this large area. The paving process involved the placement of hot asphalt into a paving machine. This machine then spreads out the material. The asphalt is then rolled. There are times when hand raking also is required. There were four men performing the paving work— [the defendant], Keith Lanou, and two other employees. The plaintiff was present while the paving was taking place. He observed that some of the asphalt contained much larger stones than specified in the class II [bituminous asphalt] mix. The plaintiff also observed that it contained other contaminates such as pieces of rubber material. The plaintiff requested that the defendant reject truck loads containing the larger stones and contaminates. The defendant refused this request. Most of the substandard asphalt was paved in . . . [an] area [that] is approximately 2500 square feet in size. The defendant’s workers attempted to remove the large stones by picking them out of the pavement. This was unsuccessful because of the significant [number] of large stones. The large stones give the driveway a rough and coarse appearance.

“It is extremely important to roll the driveway when the asphalt material is at the optimum temperature. If [665]*665asphalt is rolled when it is either too hot or cold, it produces unacceptable results. This requires effective job planning which includes coordination of asphalt deliveries with the pace of the work being performed on the site by the paving machine and roller. A paving machine spreads asphalt in strips of pavement up to thirteen feet in width. It is then rolled and compacted by a roller. If the asphalt is rolled when it has cooled, it produces a cold seam between the adjoining strips of pavement. A cold seam is visible and is more likely to crack over time. Cold rolled pavement also produces what is referred to as ‘orange peel flaking.’ This is a condition in which you have rough areas with loose paving stones. If asphalt is rolled when it is too hot, it stretches the material and produces a rough and unacceptable surface. Asphalt which is rolled either too hot or cold does not result in proper compaction of the material.

“The plaintiffs driveway was paved over a period of two days. The work was slowed because at times the [defendant’s] roller was not working properly and was unable to keep up with the pace of the work. Many areas of the driveway were cold rolled. This resulted in improper compaction, numerous cold seams, loose stones, and a rough and coarse appearance. The driveway was not installed in a workmanlike manner in accordance with standards in the paving industry.”

The plaintiff paid the defendant $30,300 for the work performed. Although the parties thereafter had numerous discussions concerning corrective work on the driveway, no agreement was reached.

The plaintiff commenced the present action in March, 2010. His three count complaint alleged negligence, breach of contract and a CUTPA violation on the part of the defendant. In response, the defendant filed an [666]*666answer with ten special defenses, as well as a counterclaim alleging breach of an implied covenant of good faith and fair dealing, breach of contract and defamation on the part of the plaintiff. Following a two day bench trial, the court found in favor of the plaintiff on all of his claims, the defendant’s special defenses and the defendant’s counterclaim. On the issue of damages, the court found that the defendant had failed to fulfill his obligations to construct the driveway “in a substantial workmanlike manner” and with the material “guaranteed to be as specified . . . .” It further found that “[t]he credible evidence proves that the driveway can be satisfactorily repaired by removing defective pavement in the areas adjacent to the garage and bam, then repave the driveway. The cost to perform this work is $18,000. The plaintiff has proven his entitlement to damages in this amount.” The court declined to award punitive damages but indicated that “[i]f the plaintiff seeks attorney’s fees pursuant to [General Statutes] § 42-1 lOg (d), his counsel shall submit an affidavit of attorney’s fees along with contemporaneous records no later than June 1, 2011.” The defendant subsequently filed a motion for reconsideration on May 31, 2011. The plaintiff filed an objection to that motion, which the court sustained, and this appeal followed.3

I

The defendant first assails numerous factual findings made by the court, which do not merit substantial discussion. We conclude that all of the challenged findings are supported by the record before us and address [667]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of Ledyard v. WMS Gaming, Inc.
191 A.3d 983 (Supreme Court of Connecticut, 2018)
Ledyard v. WMS Gaming, Inc.
Connecticut Appellate Court, 2017
Villages, LLC v. Enfield Planning & Zoning Commission
89 A.3d 405 (Connecticut Appellate Court, 2014)
Treglia v. Santa Fuel, Inc.
83 A.3d 1222 (Connecticut Appellate Court, 2014)
Petrucelli v. Travelers Property Casualty Insurance Co.
79 A.3d 895 (Connecticut Appellate Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
54 A.3d 198, 138 Conn. App. 661, 2012 WL 4800972, 2012 Conn. App. LEXIS 466, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bailey-v-lanou-connappct-2012.