FCM Group, Inc. v. Miller

17 A.3d 40, 300 Conn. 774, 2011 Conn. LEXIS 153
CourtSupreme Court of Connecticut
DecidedMay 10, 2011
DocketSC 18074
StatusPublished
Cited by39 cases

This text of 17 A.3d 40 (FCM Group, Inc. v. Miller) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FCM Group, Inc. v. Miller, 17 A.3d 40, 300 Conn. 774, 2011 Conn. LEXIS 153 (Colo. 2011).

Opinion

Opinion

PALMER, J.

In this breach of contract and hen foreclosure action arising out of a dispute concerning the construction of a single-family home in the town of Greenwich, the named defendant, Jeffrey T. Miller, who owns the home, and the defendant Cheryl Miller, his *778 wife, 1 appeal, and the plaintiff, The FCM Group, Inc., the builder of the home, and the third party defendant, Frank C. Mercede III, 2 cross appeal 3 from the judgment of the trial court. The trial court, Hon. William B. Lewis, judge trial referee, rendered partial judgment awarding the plaintiff $266,846 in damages, including $3660.67 in lost profit, and awarding the defendants $5000 in damages under General Statutes § 49-8 (c). 4 Thereafter, *779 the trial court, Karazin, J., awarded the plaintiff $64,405.17 in attorney’s fees under General Statutes § 52-249 (a) 5 and rendered judgment of strict foreclosure. On appeal, the defendants challenge all aspects of the trial court’s judgment in favor of the plaintiff except that portion of the judgment awarding the plaintiff lost profit in the amount of $3660.67. Specifically, the defendants claim that the trial court improperly accepted the recommendations of the attorney trial referee that (1) Cheryl Miller was liable for breach of contract even though she was not a party to the contract, (2) the plaintiff was entitled to delay damages under the terms of the parties’ contract, and (3) the plaintiff was entitled to foreclose on a mechanic’s lien 6 in the amount of $30,761.98. The defendants further claim that the trial court improperly (1) awarded the plaintiff the remaining balance due under the parties’ contract, (2) awarded the plaintiff attorney’s fees under § 52-249 (a), and (3) failed to award them attorney’s *780 fees under § 49-8 (c) in connection with their successful challenge to a second mechanic’s hen in the amount $343,351.47. The plaintiff claims in its cross appeal that the trial court improperly accepted the attorney trial referee’s determination that the $343,351.47 mechanic’s hen was invalid and, therefore, improperly awarded the defendants $5000 in damages under § 49-8 (c). We agree with the defendants’ claims and reject the plaintiffs claims. 7 Accordingly, we reverse in part the judgment of the trial court.

The following facts and procedural history are relevant to our disposition of the defendants’ appeal and the plaintiff and Mercede’s cross appeal. On June 11, 1998, the plaintiff and Jeffrey Miller entered into a contract for the construction of a 5000 square foot, single-family home on property located at 134 Butternut Hollow Road in Greenwich. Jeffrey Miller was married to Cheryl Miller at the time, but Jeffrey Miller held title to the property in his name alone, and he and the plaintiff were the sole signatories to the construction contract. In addition, by its express terms, the contract binds only the “[o]wner” of the property, who is identified in the contract as Jeffrey Miller.

*781 The plaintiff is a general contractor and builder of residential and commercial properties. Its founder and president, Mercede, an experienced contractor, runs the company’s daily operations. Prior to entering into the contract, Mercede and Jeffrey Miller were social acquaintances and previously had worked together on another project. Pursuant to the terms of the contract, Jeffrey Miller agreed to pay the plaintiff $648,394 for the construction of his home, but reserved the right, under article 12 of the contract, to perform a portion of the construction work himself and to hire his own subcontractors to do that work. In a rider attached to the contract, several items, including the garage, the kitchen cabinets and most of the wall coverings and flooring, were expressly excluded from the scope of the work covered by the contract so that Jeffrey Miller could hire his own vendors to install those items. The same rider also provided a “Schedule of Alternates,” which permitted the “[o]wner” to “add back in” several of the items that had been excluded from the contract, with a corresponding price for each item. 8 Under article 13 of the contract, the “[o]wner,” without invalidating the contract, could order “changes in the [w]ork” con *782 sisting of “additions, deletions or modifications, [with] the [c]ontract [s]um and [c]ontract [t]ime being adjusted accordingly.” Such changes had to be authorized by a written change order form signed by the owner, the contractor and the architect.

Pursuant to article 2, the contract was to commence “[u]pon issuance of a [b]uilding [p]ermit,” and the plaintiff was to achieve “[substantial [c]ompletion of the entire [w]ork not later than . . . 240 [c]a!endar [d]ays from the commencement of work,” subject to any time adjustments as provided under the contract. Although it was the responsibility of the plaintiff to secure all building permits, Jeffrey Miller was required to furnish all other “approvals,” including wetlands approval. On June 18,1998, the plaintiff applied to the town of Greenwich (town) for a building permit, but the application was denied due to certain unresolved wetlands issues. The town, however, eventually issued the wetlands approval on September 2,1998, and the town also issued the foundation permit on October 6, 1998.

The defendants had agreed that Cheryl Miller could communicate directly with Mercede about any changes to the design of the house, or any problems with the project. From June, 1998, through December, 1999, she visited the property two to three times a week and requested numerous changes. As a general matter, Cheryl Miller would request a change on behalf of Jeffrey Miller, and the plaintiff would quote a price for the change. The defendants then would decide whether to proceed with the change depending on the price. As of November 10,1999, the parties had agreed to four written change orders, which included a total of 113 changes to the contract. 9 These changes had increased the con *783 tract price to $803,090.98, and had added a total of eighty-six business days to the schedule. Several of the changes constituted credits to Jeffrey Miller for items that the parties had agreed to subtract from the contract.

Article 4 of the contract provided for “progress payments” to be made by the “[o]wner” on the basis of the applications for payment submitted by the “[contractor” and approved by the architect. Article 5 provided that “[f]inal payment” was due when all of the work had been completed, the contract had been “fully performed,” and a final certificate for payment had been issued by the architect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cruz v. Waterbury
235 Conn. App. 259 (Connecticut Appellate Court, 2025)
Centerplan Construction Co., LLC v. Hartford
343 Conn. 368 (Supreme Court of Connecticut, 2022)
New Milford v. Standard Demolition Services, Inc.
212 Conn. App. 30 (Connecticut Appellate Court, 2022)
Watson Real Estate, LLC v. Woodland Ridge, LLC
208 Conn. App. 115 (Connecticut Appellate Court, 2021)
Regional School District 8 v. M & S Paving & Sealing, Inc.
206 Conn. App. 523 (Connecticut Appellate Court, 2021)
RCN Capital, LLC v. Chicago Title Ins. Co.
Connecticut Appellate Court, 2020
Knight Capital Partners Corp. v. Henkel AG & Co.
930 F.3d 775 (Sixth Circuit, 2019)
Abrams v. PH Architects, LLC
193 A.3d 1230 (Connecticut Appellate Court, 2018)
Com. v. Johnson, T.
Superior Court of Pennsylvania, 2017
Com. v. Garlock, T.
Superior Court of Pennsylvania, 2017
Szynkowicz v. Bonauito-O'Hara
Connecticut Appellate Court, 2017
Whitney v. J.M. Scott Associates, Inc.
Connecticut Appellate Court, 2016

Cite This Page — Counsel Stack

Bluebook (online)
17 A.3d 40, 300 Conn. 774, 2011 Conn. LEXIS 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fcm-group-inc-v-miller-conn-2011.