Centerplan Construction Co., LLC v. Hartford

343 Conn. 368
CourtSupreme Court of Connecticut
DecidedMay 24, 2022
DocketSC20526
StatusPublished
Cited by10 cases

This text of 343 Conn. 368 (Centerplan Construction Co., LLC v. Hartford) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Centerplan Construction Co., LLC v. Hartford, 343 Conn. 368 (Colo. 2022).

Opinion

*********************************************** The “officially released” date that appears near the be- ginning of each opinion is the date the opinion will be pub- lished in the Connecticut Law Journal or the date it was released as a slip opinion. The operative date for the be- ginning of all time periods for filing postopinion motions and petitions for certification is the “officially released” date appearing in the opinion.

All opinions are subject to modification and technical correction prior to official publication in the Connecticut Reports and Connecticut Appellate Reports. In the event of discrepancies between the advance release version of an opinion and the latest version appearing in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports, the latest version is to be considered authoritative.

The syllabus and procedural history accompanying the opinion as it appears in the Connecticut Law Journal and bound volumes of official reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be reproduced and distributed without the express written permission of the Commission on Official Legal Publica- tions, Judicial Branch, State of Connecticut. *********************************************** CENTERPLAN CONSTRUCTION COMPANY, LLC, ET AL. v. CITY OF HARTFORD (SC 20526) Robinson, C. J., and D’Auria, Kahn, Ecker and Suarez, Js.

Syllabus

The plaintiffs, C Co. and D Co., which had contracted with the defendant, the city of Hartford, to construct a baseball stadium, appealed from the judgment of the trial court in favor of the city. The city had entered into an agreement with an architectural firm, P Co., to design the stadium. After P Co. began work, the city, in February, 2015, entered into a development agreement with D Co. whereby D Co. would serve as the developer and administer and complete P Co.’s plans. In turn, C Co. and D Co. entered into a builder agreement with each other, and they both entered into a direct agreement with the city. In May, 2015, the city assigned its agreement with P Co. to C Co. and D Co. In December, 2015, a dispute arose between the parties. C Co. and D Co. claimed that they had never been given control over P Co. or its design of the stadium, and that the scope of the project had increased because of design changes made by the city and the team that would be occupying the stadium. The city and D Co. resolved the dispute in January, 2016, by executing a term sheet that increased the budget for the project and extended the substantial completion deadline from March 11 to May 17, 2016. The term sheet, which C Co. did not sign, also prevented changes to the project without the city’s consent and modified the liquidated damages provision in the city’s agreement with D Co. After C Co. and D Co. failed to meet the extended substantial completion deadline, the city terminated its contractual relationship with C Co. and D Co. on the grounds that C Co. and/or D Co. had failed to construct the ballpark in a workmanlike manner and to pay the city liquidated damages that had accrued since their failure to substantially complete the project. C Co. and D Co. thereafter brought the present action against the city, claiming that the city had breached its contracts with them by failing to provide them with notice and an opportunity to cure the alleged defaults before terminating their contractual relationship. The city filed a counterclaim, alleging breach of contract against C Co. and breach of the implied covenant of good faith and fair dealing against C Co. and D Co. Prior to trial, and in response to various motions filed by the parties, the trial court determined that the city’s contracts with C Co., D Co., and P Co. granted the city the right to approve the architectural plans and changes to them but granted C Co. and D Co. the right to control how the plans were carried out, including control over P Co. and responsibility for P Co.’s errors and omissions. The court further determined that the city’s agreement with D Co. vested the city with the right of commercially reasonable approval over the project plans but that it was the parties’ intention that D Co. would have complete control over the stadium design and construction. With respect to the assignment of the city’s agreement with P Co. to C Co. and D Co., the court determined that C Co. and D Co. were able to present evidence at trial only as to the city’s interference with their legal control over P Co. and the stadium’s design after the term sheet was executed. The court instructed the jury that the only issue for it to decide was who was to blame for the stadium’s not being ready by the May 17, 2016 deadline. The jury found C Co. and D Co. responsible for failing to complete the stadium by the contractually agreed on deadline, returned a verdict against C Co. and D Co. on their breach of contract claim against the city, and awarded the city $335,000 in liquidated damages in connection with its counterclaim. The trial court rendered judgment for the city, and C Co. and D Co. appealed. Held: 1. D Co. did not waive its right to contest errors by the city that occurred prior to the execution of the term sheet, including any architectural or design errors over which the city previously had control; accordingly, the trial court improperly precluded D Co. from presenting evidence of such errors and pursuing the claims against the city that it was entitled to pursue under the term sheet. 2. The parties plainly and unambiguously provided in their agreements that, until the city assigned the agreement that it had with P Co. to C Co. and D Co., the city maintained legal control of and responsibility for P Co.’s work, including any errors or omissions that occurred between February and May, 2015; the city’s assignment of its agreement with P Co. in May, 2015, to C Co. and D Co. would have been superfluous if C Co. and D Co. already had legal control of and responsibility for P Co.’s work prior to that assignment, and the assignment’s recitals comported with the understanding that it was the parties’ intent that there would be a subsequent assignment to C Co. and D Co. of the agreement between the city and P Co. 3. The clear language of the city’s assignment of its agreement with P Co. to C Co. and D Co. plainly and unambiguously provided that C Co. and D Co. had legal control of and responsibility for P Co. and the stadium design upon the execution of that assignment in May, 2015, until January, 2016, when the term sheet was executed, including responsibility for any design errors committed during that time period; contrary to the trial court’s determination, however, the assignment’s plain and unam- biguous language established that the city retained all obligations as to P Co. arising out of P Co.’s services before the assignment in May, 2015, including responsibility for any of P Co.’s errors or omissions before May, 2015. 4. This court determined that it was unclear under the term sheet whether the city, on the one hand, or C Co. and D Co., on the other, had control of P Co. and the stadium design after the execution of the term sheet in January, 2016, until June, 2016, when the city terminated its contractual relationship with C Co. and D Co.; accordingly, that issue was to be determined by the fact finder on remand. 5. The term sheet did not unambiguously divest C Co. of the right, in its agreement with D Co., to notice and an opportunity to cure any default prior to termination, the issue of whether the city improperly failed to provide C Co. with the required notice and cure period was a question of fact for the fact finder, and the city and C Co. should have been permitted to introduce evidence regarding whether the city gave C Co. notice and an opportunity to cure prior to terminating their contractual relationship: a.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
343 Conn. 368, Counsel Stack Legal Research, https://law.counselstack.com/opinion/centerplan-construction-co-llc-v-hartford-conn-2022.