Stamford Wrecking Co. v. United Stone America, Inc.

912 A.2d 1044, 99 Conn. App. 1, 2007 Conn. App. LEXIS 6
CourtConnecticut Appellate Court
DecidedJanuary 2, 2007
DocketAC 26572
StatusPublished
Cited by6 cases

This text of 912 A.2d 1044 (Stamford Wrecking Co. v. United Stone America, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stamford Wrecking Co. v. United Stone America, Inc., 912 A.2d 1044, 99 Conn. App. 1, 2007 Conn. App. LEXIS 6 (Colo. Ct. App. 2007).

Opinion

*3 Opinion

HARPER, J.

This appeal arises out of an action by the plaintiff, the Stamford Wrecking Company (Stamford Wrecking), against the defendants United Stone America, Inc. (United Stone), and Carlos A. Costa 1 to recover damages for failure to subcontract abatement and demolition work as promised. After trial, the jury returned a verdict in favor of the plaintiff with regard to its promissory estoppel and unjust enrichment claims. The trial court subsequently denied the defendants’ motion to set aside the verdict and rendered judgment, awarding the plaintiff $455,000. On appeal, the defendants claim that (1) the court improperly excluded evidence on whether federal law prohibited them from awarding the promised amount of work, (2) the court improperly denied their motion to set aside the verdict, which was based in part on the plaintiffs ineligibility for equitable relief in quasi contract, and (3) there was insufficient evidence to support the verdict on unjust enrichment. 2 We affirm the judgment of the trial court.

The record reveals the following pertinent facts and procedural history. The plaintiff and United Stone are both contractors engaged in the construction business. In May, 2000, the United States Navy (Navy) sent out a solicitation for bids on a demolition project that was known as the Dolphin Gardens Demolition, located at the Navy submarine base in Groton (project). The solicitation specified, inter alia, that only general contractors that qualified as “small disadvantaged business concerns” under 13 C.F.R. § 124-(8) (a) ([8] [a] contractors) *4 were eligible to submit bids for the project. United Stone was an (8) (a) contractor and was therefore eligible to serve as the general contractor on the project. The plaintiff did not qualify as an (8) (a) contractor and, consequently, was unable to bid directly on the project.

In early September, 2000, negotiations took place between the plaintiff and United Stone involving the possibility of submitting a collaborative bid for the project. On September 12, 2000, the presidents of both companies signed a short writing (subcontracting agreement) affirming that United Stone, if awarded the project, would “subcontract the abatement and demolition work to [the plaintiff] or its designee while retaining a certain portion of the work for its own forces pursuant to the Specifications.” Although the subcontracting agreement did not specify the percentage of work allocation, both parties understood at the time of its execution that United Stone would perform 15 percent of the work on the project and subcontract the rest of the work to the plaintiff. 3 Further, at the time they signed the subcontracting agreement, both parties intended for the phrase “pursuant to the Specifications” to incorporate provisions from the contract between the Navy and United Stone.

On the same day that the parties executed the subcontracting agreement, United Stone formally submitted a bid for the project to the Navy. The cover letter accompanying the bid described the plaintiff as United Stone’s subcontractor and stated that the proposed methodology for completing the project was “originally developed by Stamford Wrecking . . . .” Attached to the *5 bid were several exhibits. One exhibit described the qualifications of the plaintiff. Another exhibit was entitled “Abatement and Demolition Work Plan” and contained a breakdown of the proposed demolition and abatement subcontract work for the project. Included within this exhibit was a document stating that “[t]his work plan is based upon consolidated work efforts of [United Stone] as the general contractor, and [Stamford Wrecking] as the abatement and demolition subcontractor.”

On December 15, 2000, the Navy sent United Stone a package containing an award letter and a signed copy of the construction contract (Dolphin Gardens contract). The Dolphin Gardens contract included a provision that required the general contractor, United Stone, to perform “work equivalent to at least [15] percent of the total amount of work to be performed under the contract.” 4 Yet, the Dolphin Gardens contract also described the project as having a Standard Industrial Classification (SIC) code of 1795. Under the Small Business Administration’s (SBA) classification system, the SIC code number 1795 applies to special trade contracts for which (8) (a) contractors are required to perform a minimum of 25 percent of the cost of the contract, not including the cost of materials, with its own employees. See 13 C.F.R. § 125.6 (4) (2006). Despite the contradictory provisions in the contract, on December 21, 2000, the defendants sent the Navy a letter confirming that United Stone would “self perform no less than 15% of the total Contract Value with [its] own forces and equipment.”

On December 26, 2000, United Stone sent the plaintiff a letter announcing its receipt of the Dolphin Gardens *6 contract. The letter also stated that the September 12, 2000 subcontracting agreement had “lapsed,” yet reassured the plaintiff that it would still be afforded “the opportunity to subcontract specific abatement and demolition work for the [p]roject as shown on bid documents.” Further, the letter indicated that the opportunity for the plaintiff to serve as subcontractor was contingent on its submitting to United Stone an anticipated work schedule and breakdown of tasks by January 2, 2001.

The next day, December 27, 2000, the plaintiff sent United Stone further documentation regarding its expected performance of its duties as the project’s subcontractor, along with a letter asserting that the subcontracting agreement was a binding contract that had not lapsed. After at least two telephone conversations between agents of the companies, United Stone informed the plaintiff via letter dated January 3, 2001, that, in its belief, the plaintiff had not complied satisfactorily with its information request and, consequently, would not serve as United Stone’s subcontractor on the project.

On January 9, 2001, the plaintiff initiated the present action, alleging various contractual and equitable bases for requiring the defendants to award the plaintiff the project’s abatement and demolition work pursuant to the subcontracting agreement. According to the plaintiff, the subcontracting agreement was a binding contract that obligated United Stone to subcontract to it “the abatement and demolition work,” which constituted approximately 85 percent of the project’s total work. As amended, the complaint alleged that the defendants’ refusal to subcontract the agreed on amount of work to the plaintiff constituted a breach of contract or, alternatively, a ground for recovery on the basis of the equitable doctrines of promissory estoppel and unjust enrichment. The plaintiff further claimed that *7 the defendants’ actions constituted a violation of the Connecticut Unfair Trade Practices Act (CUTPA),Gen-eral Statutes § 42-110a et seq., and fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SMDV 1, LLC v. 459-461 Pacific Street, LLC
Connecticut Appellate Court, 2025
Centerplan Construction Co., LLC v. Hartford
343 Conn. 368 (Supreme Court of Connecticut, 2022)
Schwartz v. Family Dental Group, P.C.
943 A.2d 1122 (Connecticut Appellate Court, 2008)
Landry v. Spitz
925 A.2d 334 (Connecticut Appellate Court, 2007)
Stamford Wrecking Co. v. United Stone America, Inc.
281 Conn. 917 (Supreme Court of Connecticut, 2007)
STAMFORD WRECKING COMPANY v. United Stone America, Inc.
917 A.2d 999 (Supreme Court of Connecticut, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
912 A.2d 1044, 99 Conn. App. 1, 2007 Conn. App. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stamford-wrecking-co-v-united-stone-america-inc-connappct-2007.