McClain v. Kimbrough Const. Co., Inc.

806 S.W.2d 194, 1990 Tenn. App. LEXIS 886
CourtCourt of Appeals of Tennessee
DecidedDecember 19, 1990
StatusPublished
Cited by100 cases

This text of 806 S.W.2d 194 (McClain v. Kimbrough Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McClain v. Kimbrough Const. Co., Inc., 806 S.W.2d 194, 1990 Tenn. App. LEXIS 886 (Tenn. Ct. App. 1990).

Opinion

OPINION

KOCH, Judge.

This appeal involves a dispute between a general contractor and a brick mason concerning work on a condominium project in Nashville. After the general contractor unilaterally terminated the subcontract before the work was complete, the brick mason filed an action in the Chancery Court for Davidson County to recover its lost profits. The contractor counterclaimed for the cost to correct portions of the brick mason’s work and for overpayments. The trial court awarded the brick mason $6,798 and dismissed the contractor’s counterclaim. The contractor has appealed. While we concur with the trial court’s finding that the subcontractor was damaged by the general contractor’s unilateral termination of the contract, we do not concur with the manner in which the trial court calculated the damages. Accordingly, we vacate the damage award and remand the case for further proceedings.

I.

The Kimbrough Construction Company (“Kimbrough”) was the general contractor on a condominium project in Nashville called the Woodlawn Court Condominiums. On November 6, 1987, it entered into a subcontract with Harrison McClain Masonry Company (“McClain”) to do the brick work for the project. McClain agreed “to complete the work in a timely fashion and in a good and workmanlike manner,” and in return, Kimbrough agreed to pay McClain $25,450. 1

McClain began work in mid-November, 1987. Its employees laid over 20,000 bricks during the ensuing three weeks but were forced to stop work because Kimbrough had not completed the grading around the buildings. Mr. McClain and Kimbrough’s project superintendent discussed the situation on December 3, 1987 and agreed that McClain’s crew could begin work on another job and that Kimbrough would call them back when the brick work could be completed.

Several problems concerning the brick work arose while McClain’s crew was on the job. Kimbrough’s superintendent was dissatisfied with the color of the brick. 2 *197 He also questioned several other portions of McClain’s work, particularly a chimney chase, a “soldier course” on the top of a wall, 3 and some brick work around a garage door. While Mr. McClain agreed to replace the brick in these areas, he did not follow the superintendent’s instructions to do the remedial work so that the bricks could be reused. The superintendent and Mr. McClain’s brother also became involved in a heated argument concerning the chimney chase.

Kimbrough’s superintendent never called McClain’s crew back. Instead, he decided that McClain’s work had been unacceptable and that he would retain another brick mason to complete the job. Without notice to Mr. McClain, the superintendent entered into a contract with another brick mason to complete the job and to repair or replace portions of McClain’s work. 4

Mr. McClain did not discover that Kim-brough had retained another brick mason until early February, 1988 when he observed other bricklayers working on the project. Three months later, he filed a breach of contract action against Kim-brough seeking lost profits and the retain-age on the work his crew had performed. Kimbrough counterclaimed for the expenses it incurred in replacing portions of McClain’s work and for overpayments.

The trial court concluded that Kim-brough breached its contract with McClain by interfering with McClain’s work and by failing to give McClain an opportunity to correct its defective work or to complete the job before hiring another brick mason. The trial court also found that Kim-brough’s unilateral action prevented it from recovering the additional expenses it incurred in completing the job and correcting the defective work.

II.

The parties’ agreement was embodied in a one-page document prepared by Kim-brough. The “subcontract agreement” identified the contracting parties, described the scope of the work, and set forth the amount of the contract and the terms of payment. It also contained the usual provisions regarding written change orders and retainage.

The subcontract did not, however, contain many of the provisions normally found in construction contracts. It did not, for example, contain a “flow down” clause tying the subcontractor’s performance to the contractor to the contractor’s obligations to the owner. In addition, it lacked a construction schedule, an inspection and acceptance process, and a dispute resolution procedure.

Of primary importance to this case, the subcontract did not contain a “take over” clause permitting Kimbrough to terminate the subcontract and to take over the work. Typically, a “take over” clause permits a contractor to assume control of and to carry out a defaulting subcontractor’s work after giving the subcontractor reasonable notice and an opportunity to correct its defective performance. 5 In the absence of a “take over” clause, Kimbrough must find some other support for its claimed right to terminate the subcontract before its completion without first giving McClain notice and an opportunity to cure. Kimbrough has pointed to no other support, and, under the facts of this case, we can find none.

A contracting party may terminate the contract when the other party (1) is wholly unable to complete the contract, City of Bristol v. Bostwick, 146 Tenn. 205, 211, 240 S.W. 774, 776 (1922); (2) manifests an intent to abandon the contract, Brady v. *198 Oliver, 125 Tenn. 595, 614, 147 S.W. 1135, 1139 (1911); (3) manifests an intent to no longer be bound by the contract, Church of Christ Home for Aged, Inc. v. Nashville Trust Co., 184 Tenn. 629, 642, 202 S.W.2d 178,183 (1947); or (4) commits fraud on the party seeking to terminate the contract. W.F. Holt Co. v. A & E Elec. Co., 665 S.W.2d 722, 730 (Tenn.Ct.App.1983).

The record contains no proof that McClain committed fraud or that he was unable to complete or intended to abandon the contract. On the contrary, McClain stopped work because Kimbrough could not provide a site suitable for finishing the job. McClain left the job with Kim-brough’s assent in order to avoid idling its crew and was prepared to return as soon as Kimbrough gave notice that the conditions at the job site would permit him to complete the work.

III.

Contracting parties should endeavor to define their respective rights and obligations precisely. See V.L. Nicholson Co. v. Transcon Inv. & Fin. Ltd., 595 S.W.2d 474, 482 (Tenn.1980); Forrest, Inc. v. Guaranty Mortgage Co., 534 S.W.2d 853, 857 (Tenn.Ct.App.1975). As a practical matter, however, contracting parties are not always precise and frequently leave material provisions out of their contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wade v. Newport Group, Inc.
W.D. Tennessee, 2025
Lou Ann Zelenik v. Crowell Homebuilding, LLC
Court of Appeals of Tennessee, 2025
Robert Ferguson v. M. Brown Construction, Inc.
Court of Appeals of Tennessee, 2024
Melanie Culp v. John Trimberger
Michigan Court of Appeals, 2024
Centerplan Construction Co., LLC v. Hartford
343 Conn. 368 (Supreme Court of Connecticut, 2022)
Merritt v. MGC Sports LLC
M.D. Tennessee, 2020
Gerald Brown v. Waddell Wright
Court of Appeals of Tennessee, 2019
Rashell Holt v. John Robert Whedbee
Court of Appeals of Tennessee, 2019

Cite This Page — Counsel Stack

Bluebook (online)
806 S.W.2d 194, 1990 Tenn. App. LEXIS 886, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcclain-v-kimbrough-const-co-inc-tennctapp-1990.