Lou Ann Zelenik v. Crowell Homebuilding, LLC

CourtCourt of Appeals of Tennessee
DecidedAugust 14, 2025
DocketM2021-00735-COA-R3-CV
StatusPublished

This text of Lou Ann Zelenik v. Crowell Homebuilding, LLC (Lou Ann Zelenik v. Crowell Homebuilding, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lou Ann Zelenik v. Crowell Homebuilding, LLC, (Tenn. Ct. App. 2025).

Opinion

08/14/2025 IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE April 4, 2023 Session

LOU ANN ZELENIK v. CROWELL HOMEBUILDING, LLC ET AL.

Appeal from the Chancery Court for Rutherford County No. 17CV-849 L. Craig Johnson, Judge1 ___________________________________

No. M2021-00735-COA-R3-CV ___________________________________

A buyer signed an agreement with a contractor for the construction of a custom home. After disagreements arose over the construction and its pace, the buyer sued the contractor and its owner seeking damages and to quiet title to the property. The trial court awarded the buyer damages, title to the property, and attorney’s fees and costs. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Case Remanded

W. NEAL MCBRAYER, J., delivered the opinion of the court, in which ANDY D. BENNETT and THOMAS R. FRIERSON II, JJ., joined.

Kirk D. Catron, Murfreesboro, Tennessee, for the appellants, Crowell Homebuilding, LLC and Jeffrey Crowell.

Joshua A. Jenkins, Murfreesboro, Tennessee, for the appellee, Lou Ann Zelenik.

OPINION

I.

A.

Sometime in 2015, Lou Ann Zelenik began discussions with Jeffrey Crowell about having his company, Crowell Homebuilding, LLC, build her a home. The home was to be constructed on a 7.6-acre property in Smyrna, Tennessee, which Ms. Zelenik had

1 Judge L. Craig Johnson of the Fourteenth Judicial District heard the case by interchange. See Tenn. Code Ann. § 17-2-202 (2021). purchased earlier in the year for $140,500. In December 2015, Ms. Zelenik transferred the Smyrna property to Crowell Homebuilding by quitclaim deed for a stated consideration of $10. The parties intended for the property to serve as collateral for a construction loan to be taken out by Crowell Homebuilding; the loan proceeds would be used to build Ms. Zelenik’s new home.2

In March 2016, Ms. Zelenik and Mr. Crowell on behalf of Crowell Homebuilding signed a two-page “New Construction Contract.” Under the contract, Crowell Homebuilding agreed to construct a new home “as per plans” on the Smyrna property, and Ms. Zelenik agreed to purchase the property for $550,000. The contract specified that the closing would take place on October 1, 2016, and that possession would be given with the deed. The contract further acknowledged that “[t]ime is of the essence.”

A few days later, Crowell Homebuilding and First National Bank of Middle Tennessee signed a Construction Loan Agreement. The agreement authorized a loan of up to $420,000 to be used solely for improvements to the Smyrna property. Crowell Homebuilding also signed a promissory note in favor of the bank and a deed of trust granting the bank a security interest in the Smyrna property.

Work began on the new home, but issues soon arose. According to Mr. Crowell, the issues stemmed, at least in part, from the plans referred to in the parties’ contract. He claimed that the plans, drafted by another company, were incomplete. As a result, the construction was slowed by having to wait on Ms. Zelenik to make decisions about materials and design details not reflected in the plans. And the parties had different views about the suppliers for the project. Mr. Crowell contended that Ms. Zelenik’s choices often resulted in costs that exceeded what he budgeted for the project. Ms. Zelenik also wanted the home built in a different location on the property than he had planned. Mr. Crowell later testified that the final location had a severe slope resulting in even more unplanned costs.

Both parties acknowledged that work was performed outside the scope of the parties’ contract. Work on the home went beyond or differed from what the plans specified. And Crowell Homebuilding did work on a preexisting, detached garage on the Smyrna property that was never part of the contract. Ms. Zelenik claimed that Mr. Crowell did not inform her when her decisions would result in extra costs. She anticipated that work on the detached garage would be covered under a separate contract.

2 The reason for this unusual arrangement was disputed. Ms. Zelenik claimed that Mr. Crowell suggested it, purportedly so that he could leverage a banking relationship for favorable financing terms or perhaps lower closing costs. The arrangement also allowed her to delay selling her current home until after construction was complete; she planned to use the proceeds from the sale to pay for her new home. Mr. Crowell claimed the arrangement arose from Ms. Zelenik’s distrust of banks and unwillingness to obtain financing on her own. 2 As the October 1, 2016, deadline for completion of the home came and went, the parties continued to work together despite the issues. Ms. Zelenik made payments to Crowell Homebuilding of $40,000 and $50,000 in early 2017. Including her original earnest money deposit, this brought her total payments to $110,000. But the question of payment for work outside the contract or beyond what Mr. Crowell had budgeted came to a head on April 13, 2017, when he walked off the job. At that point, he had exhausted the draws he could make under the construction loan based on progress of the work. Mr. Crowell estimated that the home was 88 percent complete when he quit.

B.

Ms. Zelenik sued Crowell Homebuilding and Mr. Crowell. The final version of her complaint asserted seventeen separate counts, including claims for breach of contract, violations of the Contractor’s Licensing Act and Tennessee Consumer Protection Act (“TCPA”), and to quiet title to the property. Crowell Homebuilding and Mr. Crowell counterclaimed, asserting breach of contract and claims of negligent misrepresentation, quantum meruit, and unjust enrichment.

Ms. Zelenik moved for partial summary judgment on several of her claims. Among other things, she contended that the undisputed facts established that Crowell Homebuilding and Mr. Crowell were the first to materially breach the construction contract. She pointed to several facts as establishing a breach, including the failure to deliver the property as required by the contract, unauthorized draws against the construction loan, and the monetary limit on the contractor’s license held by Crowell Homebuilding. Regarding the contractor’s license, which had a monetary limit of $250,000, Ms. Zelenik argued that, “[u]nquestionably, Defendants’ possession of a contractor’s license with a sufficient monetary limit is a material term [of the construction contract].” She also argued that, “[b]y offering, bidding, [and] entering into a construction agreement” for $550,000 and “by performing construction service in excess of [its] monetary limit,” Crowell Homebuilding “committed a per se violation of the [TCPA].”

Another aspect of the motion for partial summary judgment concerned the priority of interests in the property. During the case, the Construction Loan Agreement and the promissory note held by First National Bank of Middle Tennessee went into default, and the unfinished home and the property were placed into a receivership.3 Ms. Zelenik purchased the loan, making her the beneficiary of the deed of trust on the property. See W.C. Early Co. v. Williams, 186 S.W. 102, 103-04 (Tenn. 1916) (holding that a deed of trust securing a promissory note passes to a transferee of the note). Around the time that Ms. Zelenik acquired the promissory note, Crowell Homebuilding recorded a

3 There are some indications in the record that Crowell Homebuilding was placed into receivership as well. For example, the receiver signed a restated and renewal promissory note in favor of the bank “in his official capacity as Receiver for Crowell Home Building, LLC.” 3 materialmen’s lien on the property. See Tenn. Code Ann.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hensley v. Eckerhart
461 U.S. 424 (Supreme Court, 1983)
Tennie Martin, et.al. v. Southern Railway Company, et.al.
271 S.W.3d 76 (Tennessee Supreme Court, 2008)
Eadie v. Complete Co., Inc.
142 S.W.3d 288 (Tennessee Supreme Court, 2004)
Blair v. West Town Mall
130 S.W.3d 761 (Tennessee Supreme Court, 2004)
Kyle v. Williams
98 S.W.3d 661 (Tennessee Supreme Court, 2003)
Whitehaven Community Baptist Church v. Holloway
973 S.W.2d 592 (Tennessee Supreme Court, 1998)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Doe v. HCA Health Services of Tennessee, Inc.
46 S.W.3d 191 (Tennessee Supreme Court, 2001)
In Re the Adoption of E.N.R.
42 S.W.3d 26 (Tennessee Supreme Court, 2001)
Paschall's, Inc. v. Dozier
407 S.W.2d 150 (Tennessee Supreme Court, 1966)
ARC LifeMed, Inc. v. AMC-Tennessee, Inc.
183 S.W.3d 1 (Court of Appeals of Tennessee, 2005)
Samuels v. Strain
11 S.W.3d 404 (Court of Appeals of Texas, 2000)
Killingsworth v. Ted Russell Ford, Inc.
205 S.W.3d 406 (Tennessee Supreme Court, 2006)
Byrd v. Hall
847 S.W.2d 208 (Tennessee Supreme Court, 1993)
Elizabeth Eberbach v. Christopher Eberbach
535 S.W.3d 467 (Tennessee Supreme Court, 2017)
TWB Architects, Inc. v. The Braxton, LLC
578 S.W.3d 879 (Tennessee Supreme Court, 2019)
Helton v. Angelopoulos
629 S.W.2d 15 (Tennessee Supreme Court, 1982)
Emory v. Memphis City Schools Board of Education
514 S.W.3d 129 (Tennessee Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Lou Ann Zelenik v. Crowell Homebuilding, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lou-ann-zelenik-v-crowell-homebuilding-llc-tennctapp-2025.