Greg Calfee Builders LLC v. Neill Magee and Diane Magee

CourtCourt of Appeals of Tennessee
DecidedJune 29, 2020
DocketE2019-00905-COA-R3-CV
StatusPublished

This text of Greg Calfee Builders LLC v. Neill Magee and Diane Magee (Greg Calfee Builders LLC v. Neill Magee and Diane Magee) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greg Calfee Builders LLC v. Neill Magee and Diane Magee, (Tenn. Ct. App. 2020).

Opinion

06/29/2020 IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE June 9, 2020 Session

GREG CALFEE BUILDERS LLC v. NEILL MAGEE AND DIANE MAGEE

Appeal from the Chancery Court for Bradley County No. 2016-CV-068 Jerri S. Bryant, Chancellor

No. E2019-00905-COA-R3-CV

This appeal concerns an alleged breach of contract. Greg Calfee (“Mr. Calfee”), on behalf of Greg Calfee Builders LLC (“GCB”), and Neill MaGee (“Mr. MaGee”) signed an agreement (“the Contract”) whereby GCB would custom-build a home for Mr. MaGee and his wife, Diane MaGee (“the MaGees,” collectively). Mr. MaGee, citing a number of construction defects, later terminated GCB from the job and told Mr. Calfee that GCB could not come back despite GCB’s willingness and offer to correct the defects. GCB sued the MaGees in the Chancery Court for Bradley County (“the Trial Court”) seeking to recover money it alleged was still owed to it. Mr. MaGee filed a counterclaim. GCB filed a motion for summary judgment, which the Trial Court granted. The MaGees appeal. We find and hold, inter alia, that under both Tennessee caselaw and the Contract, Mr. MaGee was required to give GCB notice and a reasonable opportunity to cure the defects, yet he failed to do so. GCB is entitled to judgment as a matter of law. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Case Remanded

D. MICHAEL SWINEY, C.J., delivered the opinion of the court, in which JOHN W. MCCLARTY and THOMAS R. FRIERSON, II, JJ., joined.

W. Lewis Jenkins, Jr., Dyersburg, Tennessee, for the appellants, Neill MaGee and Diane MaGee.

Stuart F. James, Chattanooga, Tennessee, and, Michael E. Jenne, Cleveland, Tennessee, for the appellee, Greg Calfee Builders LLC. OPINION

Background

In 2014, Mr. Calfee of GCB and Mr. MaGee signed the Contract. Under the Contract, GCB was to build a home for the MaGees in Bradley County, Tennessee for $694,175. The home was to be custom-built with a number of highly particularized features such as floors made from reclaimed cypress wood. The Contract provided for an initial down payment by the MaGees to be followed by “progress payments” as GCB completed work. The Contract also provided for final payment prior to occupancy after final walkthrough and corrections. As pertinent to the issues on appeal, the Contract provided these additional terms:

10. Contractor Warranties: . . . . (d) . . . If a defect appears which Owner believes is covered by the Contractor’s duty of quality workmanship, Owner shall notify Contractor in writing describing such defect, also stating the times during the day Owner will be available at the improvements so Contractor can schedule service calls appropriately. Upon receipt of Owner’s written report of a defect, if the defective item is covered by the Contractor’s duty and quality workmanship, Contractor shall repair or replace it at no charge to Owner within thirty (3)1 days (unless due to delays caused by weather conditions, labor problems or material shortages). Notwithstanding the foregoing Contractor and Owner expressly waive the statutory limitations on actions for defective improvements of real estate, as provided by TCA 28-3-201 et. seq., and in lieu thereof covenant and agree that all actions recoverable under the statutory provision shall be brought within one (1) year after substantial completion of the improvements.

***

19. Termination by Owner: If the Contractor materially defaults or materially neglects to carry out the work in accordance with the contract documents, Owner may, after five (5) days written notice to the Contractor and without prejudice to any other remedy they may have, make good such deficiencies and may deduct the cost thereof from the payment then or thereafter due the Contractor, or, at their option, may terminate the contract and take possession of the site and of all materials, and may finish the work by whatever method they may deem expedient, and if the unpaid balance of the contract price exceeds the expense of finishing the work, such excess 1 This discrepancy between “thirty” and “(3)” is contained within the Contract. -2- shall be paid to the Contractor, but if such expense exceeds such unpaid balance, the Contractor shall pay the difference to the Owner.

20. Litigation Fees: The parties agree that in the event either party breaches this agreement, the non-defaulting party as additional damages shall be entitled to the cost of litigation, including reasonable attorney’s fees to enforce this agreement.

Work began on the home, and time passed. In late July 2015, Mr. MaGee sent Mr. Calfee a “punch list” via email of items he felt needed correcting. On July 31, 2015, Mr. Calfee met Mr. MaGee at the home and went through the punch list items room by room. Mr. Calfee told Mr. MaGee that he would correct these problems. Mr. MaGee agreed that Mr. Calfee could return on August 3, 2015 to begin making the corrections.

However, when Mr. Calfee returned on August 3, 2015, Mr. MaGee told him “I don’t want you back into my home. I don’t want your subcontractors back in the home.” Mr. Calfee left. Later that day, Mr. Calfee sent Mr. MaGee an email stating that he still wanted to make the corrections. Mr. MaGee responded with an email confirming that “Neill and Diane do not want Greg Calfee or his subcontractors to work on the punch list items in the home.” On August 24, 2015, counsel for Mr. Calfee and GCB sent a letter to the MaGees stating that Mr. Calfee stood ready, willing and able to complete the items on the punch list at their earliest convenience.

Meanwhile, Robert Thompson, an attorney and mutual friend of the parties, tried to help resolve the dispute. Mr. Thompson wrote a letter to both parties dated August 10, 2015 containing these key points:

--the balance owed to GCB was $163,770.22; --the MaGees would pay $138,351.71 in exchange for GCB executing a Contractor’s affidavit reflecting that all bills had been paid and there were no materialmen’s liens; --the only issue that remained was the floor repair; and, --the MaGees would initially retain $25,418.51 for the floor repairs.

A follow-up letter from Mr. Thompson dated August 11, 2015 reflected that the matter had not been fully settled. Mr. Thompson updated where things stood:

--the parties were at an impasse regarding the remaining balance of $25,418.51;

-3- --per Mr. MaGee’s instruction, Robert Thompson had delivered the $138,351.71 check to GCB and was now providing the executed Contractor’s Affidavit to the MaGees; and, --the outstanding balance of $25,418.51 remained in dispute.

In the August 11 letter, Mr. Thompson wrote also: “Both of you have reserved all of your rights to pursue whatever action you deem appropriate with respect to this dispute. I regret that I was unable to assist you in reaching a complete resolution. Therefore, neither of you owe me anything for my services.”

Some three months after Mr. Calfee and GCB were told unequivocally that they were not allowed to come back, the MaGees finally relented. In a letter to GCB’s counsel dated November 23, 2015, counsel for the MaGees wrote:

I have had lengthy conversations with Mr. & Mrs. MaGee concerning the numerous problems with their home. Based on those conversations they are willing to have Mr. Calfee and his subcontractors return and perform corrective work to bring the entire house into compliance with the plans, specifications and contract documents. . . .

However, GCB did not return. Instead, in March 2016, GCB sued the MaGees in the Trial Court “for enforcement of lien, breach of Contract and/or quantum meruit.” The MaGees filed an answer. Mr. MaGee, for his part, filed a counterclaim seeking an accounting of funds paid under the Contract. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Estate of Ina Ruth Brown
402 S.W.3d 193 (Tennessee Supreme Court, 2013)
R. Douglas Hughes v. New Life Development Corporation
387 S.W.3d 453 (Tennessee Supreme Court, 2012)
84 Lumber Co. v. Smith
356 S.W.3d 380 (Tennessee Supreme Court, 2011)
Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
Madden Phillips Construction, Inc. v. GGAT Development Corp.
315 S.W.3d 800 (Court of Appeals of Tennessee, 2009)
Abshure v. Methodist Healthcare-Memphis Hospitals
325 S.W.3d 98 (Tennessee Supreme Court, 2010)
United Brake Systems, Inc. v. American Environmental Protection, Inc.
963 S.W.2d 749 (Court of Appeals of Tennessee, 1997)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Bain v. Wells
936 S.W.2d 618 (Tennessee Supreme Court, 1997)
Carter v. Krueger
916 S.W.2d 932 (Court of Appeals of Tennessee, 1995)
Michelle RYE Et Al. v. WOMEN’S CARE CENTER OF MEMPHIS, MPLLC Et Al.
477 S.W.3d 235 (Tennessee Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Greg Calfee Builders LLC v. Neill Magee and Diane Magee, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greg-calfee-builders-llc-v-neill-magee-and-diane-magee-tennctapp-2020.