Carter v. Krueger

916 S.W.2d 932, 1995 Tenn. App. LEXIS 627
CourtCourt of Appeals of Tennessee
DecidedSeptember 29, 1995
StatusPublished
Cited by31 cases

This text of 916 S.W.2d 932 (Carter v. Krueger) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carter v. Krueger, 916 S.W.2d 932, 1995 Tenn. App. LEXIS 627 (Tenn. Ct. App. 1995).

Opinion

OPINION

McMURRAY, Judge.

This is an action arising from a suit to enforce a materialman’s and laborer’s hen against a building belonging to the appellant. The appellant insists that the appellee breached his contract with her and that he, therefore, is not entitled to enforce a lien. Additionally, appellant filed a counter-complaint seeking damages for breach of contract. The trial court, after a bench trial, entered judgment in favor of the appellee. This appeal resulted.

The defendant-appellant, Sylvia L. Krueger, M.D., is a medical doctor practicing her profession in Cleveland. Her professional practice offices are located in a building owned by her. The plaintiff-appellee is a building contractor also practicing his profession in the Cleveland area. The parties apparently have been acquaintances for some time. The appellee had previously constructed an addition to the appellant’s professional office building.

In the case at hand, the parties entered into an oral agreement whereby the appellee was to construct a new addition to the appellant’s building of some 3400 to 3500 additional square feet. The appellant presented to the appellee a simple sketch of the floor plan of the addition. The appellant hired an engineer to redraw the plan in such a fashion *934 that it could be used to obtain a building permit. Other than the sketch of the floor plan there was no other written documentation relating to the addition. There were no specifications agreed upon.

By subsequent agreement the parties increased the finished area of the building to 6700 square feet by finishing the attic space and basement. 1 Appellee asserts that he was to be paid fifty dollars ($50.00) per square foot for the construction based upon finished area. There appears to be no real dispute that $50.00 was the agreed upon price. The appellant, although verbose in her explanation of the costs for the project, does admit that the agreed upon price was $50.00 per square foot. In her testimony, the appellant was asked the following questions and gave the following answers:

Q. ... You entered into a contract and agreement with Mr. Carter to construct this addition to your building; is that correct?
A. That’s correct.
Q. And the price was agreed to at $50.00 per square foot of finished space; is that correct?
A. That was the price we agreed to later on, not originally, no.
* * ⅜ * * ⅜
Q. You stated in your deposition that the price was $50.00 per square foot.
A. That’s what Richard [the appellee] told me, but it was really on this one meeting that day, as I remember, that he gave me the total figure because originally as we said, the floor plan was for 3500 square feet.

The appellant moved into the new addition before a certificate of occupancy had been issued by the City of Cleveland. After his inspection the city building inspector presented the appellee with a punch list of items to be completed before a certificate would be issued. In due course, the items were corrected and a certificate of occupancy was issued.

The appellee, Mr. Carter, acknowledged that there was some $2,000.00 of work that had not been completed and that some of the work that had been done was improperly done. He complains primarily that he was not allowed to correct the problems or deficiencies; that the appellant removed him from the job and that she [the appellant] began paying the appellee’s subcontractors directly; that she hired an architect and professional engineer to inspect the new premises and report any problems they found to her; and subsequently, she hired another contractor, ISI General Contractor, to make the repairs deemed necessary by the architect and engineer to complete the project. She claims to have expended $41,790.58 in payment to the appellee’s subcontractors and $127,420.00 in repair costs to the substitute contractor. (Payments to the architect and engineer resulted in a total cost of $134,-217.78).

The trial court entered a judgment against the appellant in the amount of $70,000.00. He ordered “that plaintiff, James R. Carter, shall have a valid and enforceable lien and a judgment against the defendant, Sylvia L. Krueger, M.D., after giving defendant all credits and offsets for her counter-complaint. ...”

From this judgment the appellant appeals to this court and asks us to review the following issue:

The trial judge erred in failing to award judgment to the appellant for $77,508.00 on her counter-claim and erred in awarding judgment against appellant in favor of ap-pellee for $70,000.00 when the appellee breached his contract with appellant.

Firstly, we note that the appellant’s issue is argumentative in that it asserts as a fact that the appellee breached his contract with the appellant. This is a matter of fact which *935 is properly addressed to the trier of fact. We, therefore, will consider the issue as a challenge to the preponderance of the evidence.

The appellee also asserts two issues for our consideration. The first is basically a restatement of the issue raised by the appellant. The second issue raised by the appel-lee is whether it was error for the trial court to allow a $52,000.00 credit to the appellant in computation of the amount of the judgment. Again, we observe that these issues are nothing more than a challenge to the preponderance of the evidence.

We enter upon our review mindful of our duty pursuant to Rule 13(d), Tennessee Rules of Appellate Procedure. “Unless otherwise required by statute, review of findings of fact by the trial court in civil actions shall be de novo upon the record of the trial court, accompanied by a presumption of the correctness of the finding, unless the preponderance of the evidence is otherwise.” In a de novo review, the parties are entitled to a reexamination of the whole matter of law and fact and this court should render the judgment warranted by the law and evidence. Thornburg v. Chase, 606 S.W.2d 672 (Tenn.App.1980); American Buildings Co. v. White, 640 S.W.2d 569 (Tenn.App.1982); Tennessee Rules of Appellate Procedure, Rule 36. We note that no such presumption attaches to conclusions of law. See Adams v. Dean Roofing Co., 715 S.W.2d 341, 343 (Tenn.App.1986).

BREACH OF CONTRACT

In this case, the material facts leading up to the cessation of work by the appel-lee are basically undisputed. It is clear from the record that the appellant failed to give notice to the appellee of the deficiencies in the structure and offer him an opportunity to correct any substantial and material defects falling below the standard of workmanship prevailing in the area.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holton v. Peerbolte
M.D. Tennessee, 2024
Mark Leedy v. Hickory Ridge, LLC
Court of Appeals of Tennessee, 2022
Old Hickory Coaches, LLC v. Star Coach Rentals, Inc.
Court of Appeals of Tennessee, 2021
Joseph Christopher Archer v. Ron Noonan
Court of Appeals of Tennessee, 2021
Liberty Construction Company, LLC v. Peter H. Curry
Court of Appeals of Tennessee, 2020
The Manor Homes, LLC v. . Ashby Communities, LLC
Court of Appeals of Tennessee, 2018
Patricia Harper v. Eric Dixon
Court of Appeals of Tennessee, 2016
Robert McCollum v. Darrell Peters
Court of Appeals of Tennessee, 2015
Janice Bunch v. Tiffany Jones
Court of Appeals of Tennessee, 2015
SecurAmerica Business Credit v. Karl Schledwitz
Court of Appeals of Tennessee, 2014
Advanced Concrete Tools, Inc. v. Herman Beach
525 F. App'x 317 (Sixth Circuit, 2013)
Mark Brewer v. Kitchen Designs and Cabinetry
Court of Appeals of Tennessee, 2013
Robert Thomas Edmunds v. Delta Partners, L.L.C.
403 S.W.3d 812 (Court of Appeals of Tennessee, 2012)
Northwest Tennessee Motorsports Park, LLC v. Tennessee Asphalt Company
410 S.W.3d 810 (Court of Appeals of Tennessee, 2011)
Hosie Johnson v. Nick Dattilo
Court of Appeals of Tennessee, 2011
Roger Wilkes v. Shaw Enterprises, LLC
Court of Appeals of Tennessee, 2011
Norman Lee Robinson v. Mers, Inc.
Court of Appeals of Tennessee, 2011

Cite This Page — Counsel Stack

Bluebook (online)
916 S.W.2d 932, 1995 Tenn. App. LEXIS 627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carter-v-krueger-tennctapp-1995.