The Manor Homes, LLC v. . Ashby Communities, LLC

CourtCourt of Appeals of Tennessee
DecidedAugust 10, 2018
DocketM2017-01369-COA-R3-CV
StatusPublished

This text of The Manor Homes, LLC v. . Ashby Communities, LLC (The Manor Homes, LLC v. . Ashby Communities, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Manor Homes, LLC v. . Ashby Communities, LLC, (Tenn. Ct. App. 2018).

Opinion

08/10/2018 IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE June 6, 2018 Session

THE MANOR HOMES, LLC V. ASHBY COMMUNITIES, LLC, ET AL.

Appeal from the Chancery Court for Williamson County No. 41081 Deanna B. Johnson, Chancellor

No. M2017-01369-COA-R3-CV

This is a contract dispute between the developer and the builder of a residential property. The developer claimed that the builder was not in compliance with the terms of the contract and removed the builder from the project. The trial court found that the developer breached the contract first by removing the builder from the property without providing it with an opportunity to cure the problems the developer identified and awarded damages to the builder. The developer appeals the decision by the trial court, and we affirm the trial court’s judgment.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed

ANDY D. BENNETT, J., delivered the opinion of the Court, in which FRANK G. CLEMENT, JR., P.J., M.S., and RICHARD H. DINKINS, J., joined.

Phillip Byron Jones, Nashville, Tennessee, for the appellants, Ashby Communities, LLC and John Powell.

Casey Adam Long, Franklin, Tennessee, for the appellee, The Manor Homes, LLC.

OPINION

I. FACTUAL AND PROCEDURAL BACKGROUND

This case involves the construction of a house in Arrington, Tennessee. Ashby Communities, LLC (“Ashby Communities”) was the developer and owner of a piece of property referred to as Lot 239, and John Powell was its sole member and manager. Michael Cude was the builder on Lot 239, and disagreements that arose between Mr. Powell/Ashby Communities and Mr. Cude form the basis of this lawsuit. Mr. Cude was a long-time friend of Mr. Powell’s brother, JP Powell (“JP”). Mr. Cude had built his own house with the help of Paul Brown, who had a general contractor’s license, and Mr. Powell learned from JP that Mr. Cude was interested in building the house on Lot 239. Mr. Cude’s wife at the time, Tracy Lytle, set up a company called The Manor Homes, LLC (“Manor Homes”) in April 2010, and Mr. Cude treated Manor Homes as his company for purposes of working as a builder in the construction industry. Mr. Powell met with Mr. Cude at different times in 2010 and 2011, and the two men ultimately agreed that Mr. Cude, with the help of Mr. Brown, would build the house on Lot 239 starting in the spring of 2011.

Mr. Powell prepared an agreement titled “Profit Sharing Agreement – Kings’ Chapel Subdivision” (“the PSA” or “the agreement”) that the parties signed on March 23, 2011. Mr. Powell testified that he revised another document he had to create the PSA. The record contains no evidence that anyone other than Mr. Powell participated in the drafting of the PSA. The signatories to the agreement included Mr. Cude, on behalf of Manor Homes, and John Powell, in his personal capacity and on behalf of Ashby Communities.

In the section of the PSA called “Profit Sharing Understanding,” the parties agreed to use a software program called Lodis to track expenses of the project and to pay invoices relating to the construction of the house. Ashby Communities and Mr. Powell agreed to open a checking account at Synergy Bank, with checks to “be titled as ‘The Manor Homes, LLC’ so that all vendors recognize payments.” Manor Homes agreed to deposit $20,000 in this account, “which funds shall be returned to Builder when house has obtained a C.O.[1] or Developer is satisfied with completed house.”

Ashby Communities, Mr. Powell, and Manor Homes also agreed in this section of the agreement to a “non-equity net profit sharing agreement on the sale of the house based upon a 50/50 division of net profits between Builder and Developer.” Ashby Communities and Mr. Powell had “sole discretion” to determine the price at which the house would be sold, and Manor Homes “specifically waive[d] any rights to impede, lien, impair or delay any closings of the property described herein and/or to attach the proceeds thereof.”

Mr. Cude started on the project to build the house on Lot 239 in May 2011. He testified that he and Mr. Powell had some disagreements at the beginning of the project regarding (1) whether the topsoil had to be removed before the footings were poured and (2) which lumber supplier to use. Once they resolved those issues, Mr. Cude testified that the project moved ahead smoothly until January 2012. Mr. Powell agreed that he did not express any concerns about the house after these initial two issues were resolved until January 2012.

1 As used in the PSA, “C.O.” refers to a certificate of occupancy. -2- In late January 2012, Mr. Brown informed Mr. Cude that “there was a lot of activity surrounding the trim out at our house on lot 239.” By this time, the house on Lot 239 was in the final stages of construction, with tile, bathtubs, and appliances being installed, walls being painted, and fixtures being hung. Mr. Cude was not aware of any third parties who were or should be involved in the project, so he sent Mr. Powell an e- mail to find out what was going on. Mr. Powell responded to Mr. Cude by e-mail, and he explained that he had hired two independent designers who told him “there are problems with the house.” Mr. Powell specified that “[e]lements of design and colors are just not working . . . .” Mr. Powell continued:

I have asked Paul [Brown] to halt ALL tile work [--] this includes laundry room, all bathrooms, and fireplaces. Please do not have any other paint continue anywhere upstairs, if they are not done removing tape putting doors back etc. stop them – [w]e feel almost the entire 2nd floor needs [to be] repainted.

Mr. Cude testified that this was the first he had heard of any concerns Mr. Powell had with the house since the initial hiccups regarding the topsoil and lumber supplier. Mr. Cude asked for a meeting, and the two met at the house on January 29, 2012, at which time Mr. Powell pointed out his concerns. Mr. Cude testified that he was then “separated from the project.” Mr. Cude explained that he wanted to know specifically what Mr. Powell believed was wrong with the house so he could fix it, but Mr. Powell did not return Mr. Cude’s phone calls or e-mails, and Mr. Cude was not able to resume working on the house. Mr. Powell also failed to approve for payment the last batch of invoices Mr. Cude submitted, which included subcontractors’ work and other project- related expenses. Mr. Cude paid from his own funds outstanding invoices that exceeded $20,000 when he realized Mr. Powell was not going to approve these payments.

The house on Lot 239 was ultimately completed by a third-party contractor. A purchase and sale agreement for the house was signed on September 5, 2012, and the agreed-upon price was $574,500. A certificate of occupancy was obtained on October 26, 2012, and the house closed some time thereafter.

Manor Homes initially filed a complaint in June 2012, which it amended in August 2012 and again in May 2013. The second amended complaint named John Powell and Ashby Communities as defendants. Manor Homes claimed the defendants “constructively ejected and excluded” Manor Homes from the construction project in January 2012 and that they breached the PSA by interfering with Manor Homes’ performance of its responsibilities under the agreement. Manor Homes asserted that the PSA constituted a partnership. Manor Homes sought the following relief: (1) the appointment of a receiver to secure and marshal the assets of the project; (2) an accounting by the defendants of all money they have had or that is related to the project or the appointment of a special master for this purpose; (3) an impoundment of all

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re ESTATE OF Raymond L. SMALLMAN
398 S.W.3d 134 (Tennessee Supreme Court, 2013)
Tina Marie Hodge v. Chadwick Craig
382 S.W.3d 325 (Tennessee Supreme Court, 2012)
Anthony Ray Adkins v. Bluegrass Estates, Inc.
360 S.W.3d 404 (Court of Appeals of Tennessee, 2011)
Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
Madden Phillips Construction, Inc. v. GGAT Development Corp.
315 S.W.3d 800 (Court of Appeals of Tennessee, 2009)
Mike Allmand v. Jon Pavletic
292 S.W.3d 618 (Tennessee Supreme Court, 2009)
Ganzevoort v. Russell
949 S.W.2d 293 (Tennessee Supreme Court, 1997)
United Brake Systems, Inc. v. American Environmental Protection, Inc.
963 S.W.2d 749 (Court of Appeals of Tennessee, 1997)
Wood v. Starko
197 S.W.3d 255 (Court of Appeals of Tennessee, 2006)
Allstate Insurance Co. v. Watson
195 S.W.3d 609 (Tennessee Supreme Court, 2006)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Rainey v. Stansell
836 S.W.2d 117 (Court of Appeals of Tennessee, 1992)
Real Estate Management, Inc. v. Giles
293 S.W.2d 596 (Court of Appeals of Tennessee, 1956)
Knierim v. Leatherwood
542 S.W.2d 806 (Tennessee Supreme Court, 1976)
Planters Gin Co. v. Federal Compress & Warehouse Co.
78 S.W.3d 885 (Tennessee Supreme Court, 2002)
White v. Early
211 S.W.3d 723 (Court of Appeals of Tennessee, 2006)
Correll v. E.I. DuPont De Nemours & Co.
207 S.W.3d 751 (Tennessee Supreme Court, 2006)
Maggart v. Almany Realtors, Inc.
259 S.W.3d 700 (Tennessee Supreme Court, 2008)
Farmers-Peoples Bank v. Clemmer
519 S.W.2d 801 (Tennessee Supreme Court, 1975)
Hanover Insurance Company v. Haney
425 S.W.2d 590 (Tennessee Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
The Manor Homes, LLC v. . Ashby Communities, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-manor-homes-llc-v-ashby-communities-llc-tennctapp-2018.