George Sanders, Individually and d/b/a SMS Contractors, Inc. v. Breath of Life Christian Church, Inc.

CourtCourt of Appeals of Tennessee
DecidedJanuary 13, 2012
DocketW2010-01801-COA-R3-CV
StatusPublished

This text of George Sanders, Individually and d/b/a SMS Contractors, Inc. v. Breath of Life Christian Church, Inc. (George Sanders, Individually and d/b/a SMS Contractors, Inc. v. Breath of Life Christian Church, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George Sanders, Individually and d/b/a SMS Contractors, Inc. v. Breath of Life Christian Church, Inc., (Tenn. Ct. App. 2012).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON November 15, 2011 Session

GEORGE SANDERS, Individually and d/b/a SMS Contractors, Inc. v. BREATH OF LIFE CHRISTIAN CHURCH, INC., ET AL.

Direct Appeal from the Chancery Court for Shelby County No. CH-05-0577-2 Arnold B. Goldin, Chancellor

No. W2010-01801-COA-R3-CV - Filed January 13, 2012

This is a contract case. The construction contract at issue provided for a specific contract amount plus a commission to the general contractor on any work done beyond the additional contract amount. After being dismissed from the job, the project manager for the general contractor sued both the general contractor and the owner of the property. The general contractor and the property owner then both sued the project manager and each other. After the property owner failed to satisfactorily respond to discovery requests, the trial court excluded all evidence of the property owner’s damages that had not already been provided in detail in discovery. The parties proceeded to trial, at which point the chancellor ordered that all issues of damages beyond the base contract damages would be referred to a special master. After trial, the chancellor found that the property owner materially breached the contract and awarded the remaining balance to be paid on the contract to the general contractor. The special master awarded the project manager damages for work performed as a direct subcontractor on the project and awarded the general contractor delay damages and the commission on all extra work done on the project. The trial court concurred in the findings of the special master and the property owner appealed, raising a number of issues. We affirm in part, vacate in part, and remand for further proceedings.

Tenn. R. App. P. 3. Appeal as of Right; Judgment of the Chancery Court Affirmed in Part; Vacated in Part; and Remanded

J. S TEVEN S TAFFORD, J., delivered the opinion of the Court, in which A LAN E. H IGHERS, P.J., W.S., and D AVID R. F ARMER, J., joined.

Addie M. Burks and Stacy A. Clinton, Memphis, Tennessee, for the appellant, Breath of Life Christian Center Church, Inc. Stephen H. Biller, Memphis, Tennessee, for the appellee, George Sanders, Individually and d/b/a SMS Contractors, Inc.

Elizabeth B. Stengel and Joseph T. Getz, Memphis, TN, for the appellee, Bricks, Inc.

OPINION

I. Background

This action arises from a contract for the construction of a new church building for Defendant/Appellant Breath of Life Christian Church, Inc. (“the Church”)1 in Memphis, Tennessee. The Church had previously entered into a contract with Capstone Construction Co. (“Capstone”) to build the Church; however that contract was terminated and the project went unfinished for a number of months, during which time the structure was exposed to the elements.

In order to complete the new church building, Tanner George, the project manager for the Church, contacted George Sanders of SMS Contractors, Inc. (“SMS”). Because Mr. Sanders was unable to obtain the proper licensing and bonding requirements for a project of this magnitude, he brought in another general contractor, Bricks, Inc. (“Bricks”), which did have the necessary licensing and bonding requirements. On or about September 24, 2003, the Church entered into a general contract with Bricks to build the Church’s new building. The contract provided that Bricks would be the general contractor on the project. Although Bricks and the Church were the only parties to the contract, Mr. Sanders was involved in the negotiations and entered into a separate contract with Bricks to serve as Bricks’ project manager on this job.2 The Church was aware that while Bricks was the general contractor, Mr. Sanders would be the point-person for the project and would be responsible for the direct supervision of the work on the site.

The contract price was $4,163,786.95, including $468,284.00 for the contractor’s

1 It is undisputed that the Church is incorporated under the laws of Tennessee. However, in negotiating and signing the contract, Pastor Sammy Holloway did not represent that the Church was a non- profit corporation or that he was president of that corporation. Due to the Pastor Holloway’s failure to sign as a corporate representative, the Church argued at trial that it could not be liable on the contract. However, the trial court found that, despite the various “aliases” used by the Church throughout the contract and this litigation, including Breath of Life Christian Church, Breath of Life Christian Center, Inc., Breath of Life Ministries, and the Breath of Life Evangelistic Ministries, the Church remained liable on the contract. The Church does not take issue with the chancellor’s conclusion on appeal. 2 The contract between Mr. Sanders d/b/a SMS is not involved in this appeal.

-2- profit.3 The contract provided that progress payments would be made by the Church to the Contractor for work completed on the project, less a 10% retainage on each payment, which would be held by the bank until the conclusion of the contract. Final payment constituting the entire unpaid balance of the contract price was due upon completion of the project and the issuance of the certificate of payment from the architect. The contract states that the project should be completed within 365 days of commencement of the project. However, the contract also notes that:

Cost listed below [i.e., the $4,163,786.95 contract price] applies to a 12 month period. Contractor will be paid additional time in the event the construction time exceeds the 12 months through no fault of the contractor. Extension/delay and or suspensions which are not the fault of the Owner shall be excluded from the 12 month period.

The contract also provides that payments due and unpaid under the contract accrue interest at a rate of 2.5% from the date payment is due.

Attached to the form contract were several exhibits that supplemented the terms of the agreement. Included was Exhibit D, which states that:

It is understood and agreed that the contractor who initiated construction on the contract has defaulted and that Bricks, Inc. has been persuaded to recommence and be responsible for the completion of the project; however, in any circumstance, Bricks, Inc. must rely upon the estimates of costs submitted by Breath of Life Christian Church subject to the adjustments of this Cost Addendum, Exhibit “D.” Bricks, Inc. Agrees to complete construction of the Breath of Life Christian Church for the sum of . . . [$4,163,786.95], which contract sum is subject to the additions and deletions herein provided according to the Schedule of Values (Exhibit “E”) presented to Bricks, Inc. by Breath of Life Christian Church. In the event that the Schedule of Values submitted by the Breath of Life Christian Church is insufficient in any item or if required items are not there listed, and then the owner shall be required to pay those costs and Bricks, Inc. shall be entitled to receive 11% of the increased cost of those items.

3 Later in the contract, the document makes clear that the contractor’s profit is 11% of the total cost of the contract, which is $458,016.46. This miscalculation was corrected by the chancellor in his judgment and neither party takes issue with this change on appeal.

-3- * * *

It is agreed and understood that some work has been provided by the initial contractor and others . . . . Therefore Bricks, Inc. will not be liable and does not guarantee any work performed by the previous contractor or others liable and will be paid as above provided for alternations [sic] additions, or corrections as needed. The Church may at its election purchase materials, fixtures, and equipment in order to avoid payment of sales tax and thereby reduce its costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gasoline Products Co. v. Champlin Refining Co.
283 U.S. 494 (Supreme Court, 1931)
Hensley v. Eckerhart
461 U.S. 424 (Supreme Court, 1983)
Beatrice D. Saxion v. Titan-C-Manufacturing, Inc.
86 F.3d 553 (Sixth Circuit, 1996)
Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
Madden Phillips Construction, Inc. v. GGAT Development Corp.
315 S.W.3d 800 (Court of Appeals of Tennessee, 2009)
Lamar Advertising Co. v. By-Pass Partners
313 S.W.3d 779 (Court of Appeals of Tennessee, 2009)
German v. Ford
300 S.W.3d 692 (Court of Appeals of Tennessee, 2009)
State v. Watson
227 S.W.3d 622 (Court of Criminal Appeals of Tennessee, 2006)
Lee Medical, Inc. v. Paula Beecher
312 S.W.3d 515 (Tennessee Supreme Court, 2010)
Mercer v. Vanderbilt University, Inc.
134 S.W.3d 121 (Tennessee Supreme Court, 2004)
Woodlawn Memorial Park, Inc. v. Keith
70 S.W.3d 691 (Tennessee Supreme Court, 2002)
Eldridge v. Eldridge
42 S.W.3d 82 (Tennessee Supreme Court, 2001)
Ganzevoort v. Russell
949 S.W.2d 293 (Tennessee Supreme Court, 1997)
Boyd v. Comdata Network, Inc.
88 S.W.3d 203 (Court of Appeals of Tennessee, 2002)
Scholz v. S.B. International, Inc.
40 S.W.3d 78 (Court of Appeals of Tennessee, 2000)
Walker v. Sidney Gilreath & Associates
40 S.W.3d 66 (Court of Appeals of Tennessee, 2000)
Stalsworth v. Grummons
36 S.W.3d 832 (Court of Appeals of Tennessee, 2000)
White v. Vanderbilt University
21 S.W.3d 215 (Court of Appeals of Tennessee, 1999)
Realty Shop, Inc. v. RR Westminster Holding, Inc.
7 S.W.3d 581 (Court of Appeals of Tennessee, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
George Sanders, Individually and d/b/a SMS Contractors, Inc. v. Breath of Life Christian Church, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-sanders-individually-and-dba-sms-contractor-tennctapp-2012.