Joseph Christopher Archer v. Ron Noonan

CourtCourt of Appeals of Tennessee
DecidedAugust 18, 2021
DocketM2020-01266-COA-R3-CV
StatusPublished

This text of Joseph Christopher Archer v. Ron Noonan (Joseph Christopher Archer v. Ron Noonan) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph Christopher Archer v. Ron Noonan, (Tenn. Ct. App. 2021).

Opinion

08/18/2021 IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE Assigned on Briefs May 3, 2021

JOSEPH CHRISTOPHER ARCHER, ET AL. v. RON NOONAN

Appeal from the Circuit Court for Putnam County No. 2018-CV-88 Jonathan L. Young, Judge ___________________________________

No. M2020-01266-COA-R3-CV ___________________________________

This case involves an action filed by homeowners against their contractor for breach of contract regarding the installation of a swimming pool. The general sessions court entered judgment for plaintiffs. Defendant appealed to the circuit court which also entered judgment for the plaintiffs. The defendant appeals. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed

CARMA DENNIS MCGEE, J., delivered the opinion of the court, in which D. MICHAEL SWINEY, C.J., and FRANK G. CLEMENT, JR., P.J., M.S., joined.

William A. Cameron and Bradford G. Wood, Jr., Cookeville, Tennessee, for the appellant, Ron Noonan.

Austin T. Warehime, Nashville, Tennessee, for the appellees, Joseph Christopher Archer, and Margaret Rose Archer.

OPINION

I. FACTS & PROCEDURAL HISTORY

On July 17, 2016, Ron Noonan (“the Contractor”) entered into a contract for the installation of a swimming pool on the property of Joseph Christopher Archer and Margaret Rose Archer (“the Archers”). The contract did not contain a date for completion or a “time is of the essence” provision. The contract stated in article 4 that “. . . [the Contractor] will remedy any defect in the workmanship of which it receives WRITTEN notice within one year after connection of the filter, WITHOUT ADDITIONAL COST to the OWNERS.” On June 5, 2017, the Archers sent a certified letter to the Contractor. This letter stated that the initial estimate to build the pool was 45 days and that the pool was filled with water for the first time on April 2, 2017. The letter further stated that the Contractor had 30 days to fix a pool leak and have the pool properly functioning to full depth. The Archers also informed the Contractor that if there was not significant progress to fix the pool leak within 10 days, then they would be forced to “accelerate further action.” This letter was not received by the Contractor. However, the Archers provided notice of the problems with the pool to the Contractor through text messages. The text messages showed that the Contractor was working with the Archers to resolve the issues. Although the pool did not hold its intended amount of water, the Archers continued to use the pool.

The Archers sought a second opinion from Mr. Dave Sherman of Straight Arrow Construction who inspected the pool and completed his report on August 25, 2017. Mr. Sherman stated in his report that “[t]he pool is losing water at a rate of 6 inches per 12[- ]hour period when the pool is filled to operation height.” After finding and filling 75 holes and 3 major leaks in the pool, Mr. Sherman stated in the report that “12 hours later the pool still lost 6 inches of water.” Mr. Sherman concluded in the report that “I don’t believe that this pool can be fixed as it has been built[.] I believe that the only option is to start over with a new pool.” Thereafter, the Archers had the pool dug up.

On August 22, 2017, the Archers filed a civil summons in the Putnam County General Sessions Court. After several failed attempts to serve the Contractor which necessitated filing additional civil summons, and multiple continuances, the case was set for final hearing in the general sessions court on May 15, 2018. The general sessions court entered judgment for the Archers against the Contractor in the amount of $24,999.00, plus interest at the rate of 6.50% and costs for suit.

The Contractor timely filed a notice of appeal in the Putnam County Circuit Court, which held a final hearing on the matter on August 5, 2020. At the final hearing, the Archers presented two witnesses: Mr. Archer and Mr. Dave Sherman, who testified as an expert witness. Mr. Sherman testified that the cause of the continued pool leakage was improper pool construction by the Contractor. There was no cross-examination of Mr. Sherman. The Contractor testified for himself, but called no other witnesses. He testified that he worked with the Archers to fix the problems with the pool. He further testified that he went to work on the pool a few days later, after Labor Day 2017, as requested by the Archers. When he arrived, the Archers had already dug the pool up.

Based upon the testimony presented, the circuit court entered judgment for the Archers against the Contractor in the amount of $22,000.00, plus court costs and costs of the appeal from the general sessions court. The court found that there was a valid contract enforceable against both parties and that the pool was partially usable, but leaked and was not constructed such as was contracted for by the parties. The Contractor timely filed a -2- notice of appeal.

II. ISSUES PRESENTED

The Contractor presents the following issue for review on appeal, which we have slightly restated:

1. Whether the trial court erred in determining that the [Contractor] was in breach of contract and awarding judgment to the [Archers] when the evidence shows that the [Archers] were the first and only party to materially breach the contract.

For the following reasons, we affirm the decision of the circuit court.

III. STANDARD OF REVIEW

On appeal, we review the trial court’s findings of fact de novo with a presumption of correctness unless the evidence preponderates otherwise. Tenn. R. App. P. 13(d); In re Angela E., 303 S.W.3d 240, 246 (Tenn. 2010). Factual determinations based on a trial judge’s assessment of witness credibility receive a higher degree of deference. Madden Phillips Const., Inc. v. GGAT Dev. Corp., 315 S.W.3d 800, 809 (Tenn. Ct. App. 2009). We will not reverse a finding of the trial court based on credibility unless clear and convincing evidence shows the finding to be in error. Id. (citation omitted). Questions of law are also reviewed de novo but with no presumption of correctness. Eberbach v. Eberbach, 535 S.W.3d 467, 473 (Tenn. 2017) (citing Barnes v. Barnes, 193 S.W.3d 495, 498 (Tenn. 2006); Taylor v. Fezell, 158 S.W.3d 352, 357 (Tenn. 2005)).

IV. DISCUSSION

The trial court found that a contract existed between the parties to install a pool and that there was pool leakage. On appeal, the Contractor argues that the trial court erred in finding that he was in breach of contract and awarding judgment to the Archers. Instead, the Contractor argues that the Archers were the first and only party to materially breach the contract by denying him the right to cure the defects when they dug the pool up.

From the record, there is no evidence that this argument was presented to the trial court. There is not a transcript of the proceedings. The Statement of the Evidence filed in this matter only briefly describes the Contractor’s testimony as follows:

The Defendant-Appellant testified that he worked with the Plaintiffs- Appellants to fix the problems with the pool.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
Madden Phillips Construction, Inc. v. GGAT Development Corp.
315 S.W.3d 800 (Court of Appeals of Tennessee, 2009)
In Re Angela E.
303 S.W.3d 240 (Tennessee Supreme Court, 2010)
Barnes v. Barnes
193 S.W.3d 495 (Tennessee Supreme Court, 2006)
Taylor v. Fezell
158 S.W.3d 352 (Tennessee Supreme Court, 2005)
In Re the Adoption of E.N.R.
42 S.W.3d 26 (Tennessee Supreme Court, 2001)
Carter v. Krueger
916 S.W.2d 932 (Court of Appeals of Tennessee, 1995)
Wilhite v. Brownsville Concrete Co., Inc.
798 S.W.2d 772 (Court of Appeals of Tennessee, 1990)
Elizabeth Eberbach v. Christopher Eberbach
535 S.W.3d 467 (Tennessee Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Joseph Christopher Archer v. Ron Noonan, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-christopher-archer-v-ron-noonan-tennctapp-2021.