Sturdy Concrete Corp. v. NAB Construction Corp.

65 A.D.2d 262, 411 N.Y.S.2d 637, 1978 N.Y. App. Div. LEXIS 13417
CourtAppellate Division of the Supreme Court of the State of New York
DecidedDecember 26, 1978
StatusPublished
Cited by25 cases

This text of 65 A.D.2d 262 (Sturdy Concrete Corp. v. NAB Construction Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sturdy Concrete Corp. v. NAB Construction Corp., 65 A.D.2d 262, 411 N.Y.S.2d 637, 1978 N.Y. App. Div. LEXIS 13417 (N.Y. Ct. App. 1978).

Opinion

OPINION OF THE COURT

Per Curiam.

In an action by a subcontractor to recover (1) the balance due on the subcontract and (2) the value of extra work allegedly performed, in which the general contractor counterclaimed to recover the value of work it was allegedly required to perform due to the subcontractor’s unsatisfactory performance, plaintiff appeals from portions of a judgment of the Supreme Court, Queens County, entered March 1, 1977, which, after a nonjury trial, awarded it the sum of only $900 on the complaint and dismissed the remainder thereof, and awarded defendant the sum of $120,889.74, together with interest, costs and disbursements, on the counterclaim.

The judgment should be modified by (1) deleting therefrom (a) the decretal paragraph directing defendant to reduce the money it has retained under the provisions of article XIII of the subcontract to 5% and to pay the balance of said retain-age to plaintiff, and (b) the decretal paragraph awarding defendant judgment on the counterclaim and (2) dismissing so much of the counterclaim as seeks to recover for work which defendant alleges, upon information and belief, that it will be required to perform. As so modified, the judgment should be affirmed insofar as appealed from, and the action remitted to Trial Term for a new trial.

Defendant NAB Construction Corp. (NAB) was awarded a contract by the Port Authority of New York and New Jersey (Port Authority) for the reconstruction of roof structures on North River Piers 88, 90 and 92 on Manhattan’s West Side. On September 7, 1972 NAB entered into a subcontract with plaintiff Sturdy Concrete Corp. (Sturdy), by which the latter was to perform certain construction work on the project [266]*266having mostly to do with the pouring of concrete. The subcontract price was $655,000.

According to Sturdy, it commenced work in December, 1972 and had substantially completed its work on or about February 1, 1974. Sturdy further alleged that, as of that date, the sum of $77,909.20 was still owing on the subcontract price.

Sturdy subsequently brought this action to recover the balance due on the subcontract, as well as the sum of $305,974.70, representing the fair and reasonable value of work, labor, services and materials alleged to have been performed or provided as extras.

Sturdy’s bill of particulars separated its claim for extras into seven categories, as follows:

(1) $4,547.13 for extra work in connection with certain concrete footings;
(2) $12,442.63 for extra work on Pier 88, ordered by the Port Authority;
(3) $11,659.37 for extra work on Pier 90, also ordered by the Port Authority;
(4) $11,867.25 for various extra work authorized in writing by NAB (this item was settled during the trial);
(5) $23,833.14 for various extra work not authorized in writing by NAB;
(6) $5,032.98 for the patching of "birdbaths” in pre-existing concrete decks; and
(7) $236,591.20 for extra concrete alleged to have been required because of unanticipated deflection of the metal deck structure upon which Sturdy poured new roof slabs.

NAB interposed a general denial and raised the following affirmative defenses pertinent to this appeal:

(1) the claims set forth as items two and three in Sturdy’s bill of particulars were premature, because the value of the extra work had not been determined by the Port Authority engineer, as required by the subcontract;
(2) the claim set forth as item five was not authorized in writing by NAB, as required by the subcontract; and
(3) the claim for final payment on the subcontract was premature, because NAB had not received final payment from the Port Authority, a condition precedent to Sturdy’s payment.

In addition, NAB counterclaimed for the sum of $125,000, [267]*267alleged to be its damages suffered by reason of deficiencies in Sturdy’s performance of subcontract work.

The counterclaim is analytically separable into three components:

(1) $26,947.32 for subcontract work which NAB allegedly performed itself, and for which it backcharged Sturdy;
(2) $43,000 for subcontract work which NAB alleged it would be required to perform but which it had not performed as of the time the action was commenced; and
(3) $64,931.88 for subcontract work allegedly performed by Brisk Waterproofing Co., another subcontractor on the project, on Sturdy’s behalf, which sum was allegedly paid to Brisk by NAB, and which sum was backcharged to Sturdy.

After a lengthy trial, the court dismissed the complaint in its entirety, with the exception of $900 of item five, for which sum judgment for Sturdy was entered. The court awarded NAB the sum of $120,889.74 on its counterclaim. This sum represented the full amount of the claim for work done by Brisk, $64,931.88, plus 80% of the claim for the work performed or to be performed by NAB. The court excluded from this latter item 15% representing overhead and 5% representing profit. Sturdy has appealed.

Of the six items of Sturdy’s claim for extras upon which Trial Term ruled, only the dismissal of item one is not cited by Sturdy as erroneous. As to the five remaining items, we affirm Trial Term’s disposition, although we differ in some particulars with its reasoning. We deal with those items seriatim.

As to items two and three, it is not disputed that the extra work claimed was authorized by the Port Authority. The question posed as to these items is whether Sturdy is entitled to immediate payment, or whether such payment must await a determination by the Port Authority’s engineer as to the value of the work performed. We agree with Trial Term that these claims are premature, but we reach this result upon a different interpretation of the relevant provisions of the general contract and the subcontract.

The specific subcontract provision pertaining to payment for extra work is a typewritten addendum to article II: "All extra work will be done as agreed by the parties concerned and paid for on an agreed lump sum basis and/or time and material plus over head. This work is to be done with normal standards [268]*268used in the building industry. Payments on extra work will be done on a monthly requisition as work progresses and they will be paid in full without retainage.”

Paragraph 17 of the general contract sets forth the manner in which contract disputes were to be resolved: "to resolve all disputes and to prevent litigation the parties to this Contract authorize the Engineer acting personally, to decide all questions of any nature whatsoever arising out of, under, or in connection with, or in any way related to or on account of, this Contract * * * and his decision shall be conclusive, final and binding on the parties.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Old Hickory Coaches, LLC v. Star Coach Rentals, Inc.
Court of Appeals of Tennessee, 2021
Dean Bldrs. Group, P.C. v. M.B. Din Constr., Inc.
2020 NY Slip Op 05185 (Appellate Division of the Supreme Court of New York, 2020)
CNP MECHANICAL, INC. v. ALLIED BUILDERS, INC.
Appellate Division of the Supreme Court of New York, 2011
J.J. Juliano Construction, Inc. v. Burgio & Campofelice, Inc.
273 A.D.2d 921 (Appellate Division of the Supreme Court of New York, 2000)
Windsor Metal Fabrications, Ltd. v. General Accident Insurance
722 N.E.2d 58 (New York Court of Appeals, 1999)
Greeter Construction Co. v. Tice
11 S.W.3d 907 (Court of Appeals of Tennessee, 1999)
Windsor Metal Fabrications, Ltd. v. General Accident Insurance Co. of America
250 A.D.2d 148 (Appellate Division of the Supreme Court of New York, 1998)
Martin Iron & Construction Corp. v. E.W. Howell Co.
242 A.D.2d 608 (Appellate Division of the Supreme Court of New York, 1997)
Maguire Co., Inc. v. Herbert Const. Co., Inc.
945 F. Supp. 72 (S.D. New York, 1996)
Carter v. Krueger
916 S.W.2d 932 (Court of Appeals of Tennessee, 1995)
J & J Structures, Inc. v. Callanan Industries, Inc.
215 A.D.2d 890 (Appellate Division of the Supreme Court of New York, 1995)
Otis Elevator Co. v. George A. Fuller Co.
172 A.D.2d 732 (Appellate Division of the Supreme Court of New York, 1991)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Crown Plastering Corp. v. Elite Associates, Inc.
166 A.D.2d 495 (Appellate Division of the Supreme Court of New York, 1990)
Mrozik Construction, Inc. v. Lovering Associates, Inc.
461 N.W.2d 49 (Court of Appeals of Minnesota, 1990)
Action Interiors, Inc. v. Component Assembly Systems Inc.
144 A.D.2d 606 (Appellate Division of the Supreme Court of New York, 1988)
Mel-Stu Construction Corp. v. Melwood Construction Corp.
131 A.D.2d 823 (Appellate Division of the Supreme Court of New York, 1987)
A. A. Conte, Inc. v. Campbell-Lowrie-Lautermilch Corp.
477 N.E.2d 30 (Appellate Court of Illinois, 1985)
Lowy & Donnath, Inc. v. City of New York
98 A.D.2d 42 (Appellate Division of the Supreme Court of New York, 1983)
Sturdy Concrete Corp. v. NAB Construction Corp.
89 A.D.2d 588 (Appellate Division of the Supreme Court of New York, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
65 A.D.2d 262, 411 N.Y.S.2d 637, 1978 N.Y. App. Div. LEXIS 13417, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sturdy-concrete-corp-v-nab-construction-corp-nyappdiv-1978.