Windsor Metal Fabrications, Ltd. v. General Accident Insurance

722 N.E.2d 58, 94 N.Y.2d 124, 700 N.Y.S.2d 90, 1999 N.Y. LEXIS 3742
CourtNew York Court of Appeals
DecidedNovember 30, 1999
StatusPublished
Cited by7 cases

This text of 722 N.E.2d 58 (Windsor Metal Fabrications, Ltd. v. General Accident Insurance) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Windsor Metal Fabrications, Ltd. v. General Accident Insurance, 722 N.E.2d 58, 94 N.Y.2d 124, 700 N.Y.S.2d 90, 1999 N.Y. LEXIS 3742 (N.Y. 1999).

Opinion

OPINION OF THE COURT

Bellacosa, J.

This case presents the puzzle of when the one-year limitations period for suing a surety on a public improvement construction bond begins to run, within the meaning of State Finance Law • § 137 (4) (b). Also implicated is whether contractual provisions in a subcontract can effectively toll the statutory time period.

We conclude that the one-year period starts to be counted as of the time when a subcontractor has demanded final payment from the general contractor with whom it contracted, and 90 days have passed since the subcontractor ceased work on the project. This time frame may not be extended or overridden by any provisions of the subcontract.

I.

This controversy arises out of a public improvement contract for the construction of a health care facility at Green Haven *129 Correctional Facility. Eberhard Construction Company, the general contractor, held the prime contract with the State of New York. Plaintiff Windsor subcontracted with Eberhard to provide and erect all structural steel for the project, at a cost of $404,000.

Defendant General Accident provided the statutory payment bond for the project. The document stated that it was a Comptroller’s Form Bond issued pursuant to State Finance Law § 137 and that “all rights and remedies on this bond * * * shall be determined in accordance with the provisions, conditions and limitations of said Section.”

Windsor started its work on the project on April 12, 1994. The State terminated its prime contract with Eberhard on March 28, 1995. This resulted in the termination of the subcontract with Windsor and in Windsor’s cessation of work on the project. Windsor’s president later asserted in an affidavit:

“Prior to the termination, Eberhard had already fallen behind in payments to Windsor. Following the termination, I contacted Eberhard on several occasions in an attempt to secure final payment, all to no avail.”

On March 31, 1995, three days after the State terminated the contract with Eberhard, Windsor wrote to General Accident, stating:

“As of this date we are owed the amount of $211,192.00. Plus, we are awaiting charges from our erector for changing opening and delays.
“For you [sic] convenience we have hereby attached a copy of our request for payment sent to Eberhard Construction.
“Please regard this as a notice for payment. Please be kind enough to inform us as to when we can expect the monies due to us.”

At all relevant times, Eberhard and General Accident denied owing Windsor additional compensation and rejected Windsor’s payment demands. Indeed, Eberhard took the position that Windsor’s failure to fulfill its obligations under the subcontract caused the State to terminate the prime contract with Eberhard.

On April 19, 1995, Windsor filed a notice of mechanics’ lien in the amount of $214,036.36, which Windsor indicated was *130 due on March 1, 1995. The lien was discharged when Eberhard and General Accident posted a $250,000 bond, separate from the initial statutory payment bond.

On April 19, 1995, Windsor also filed a demand for arbitration against Eberhard, seeking the $214,036.36. Windsor immediately notified General Accident of the arbitration, and General Accident participated in the proceedings to the extent that it joined Eberhard in the attempt to prove Windsor had breached its subcontract; General Accident also asserted that Windsor was responsible for General Accident’s own losses incurred as a result of its having to arrange to complete the project following the termination of Eberhard, its principal.

Windsor won an arbitration award against only Eberhard on April 2, 1996 in the sum of $231,678.20. Supreme Court confirmed the award and, on December 24, 1996, entered a $255,130.22 judgment against Eberhard. Unfortunately for Windsor, Eberhard was apparently insolvent by this time. Windsor, thus turned its recovery effort toward General Accident, which denied its demand for payment.

In early 1997, Windsor sued General Accident, seeking $255,130.22, the amount of the judgment entered against Eberhard. General Accident raised the Statute of Limitations as an affirmative defense (State Finance Law § 137 [4] [b]), and Supreme Court granted summary judgment to General Accident on this ground.

The Appellate Division disagreed. It relied on specific provisions of Windsor’s subcontract and found that none of the “final payment” provisions in the subcontract could operate to raise a time bar. As pertinent to this appeal, the Appellate Division unanimously reversed and granted that part of Windsor’s motion seeking summary judgment on its first cause of action pursuant to the payment bond.

This Court granted General Accident leave to appeal. We now reverse, reinstate the Supreme Court ruling, and dismiss Windsor’s complaint.

II.

State Finance Law § 137 (4) (b) states:

“No action on a payment bond furnished pursuant to this section shall be commenced after the expiration of one year from the date on which final payment under the claimant’s subcontract became due” (emphasis added).

*131 Section 137 (3) of State Finance Law provides that anyone who has furnished labor or material pursuant to a subcontract made directly with the contractor and who is not paid within 90 days “after the day on which the last of the labor was performed or material was furnished * * * shall have the right to sue” on the surety payment bond.

Together, subdivisions (3) and (4) set the beginning and endpoint measurements for a lawsuit against a surety in these circumstances. They establish a date upon which the claim against a surety becomes ripe (State Finance Law § 137 [3]) and a date after which time has run out for an action on the claim (State Finance Law § 137 [4] [b]). The pinpointing of this latter date is the operative question in this case; it hinges on the definition of “the date on which final payment under the claimant’s subcontract became due” (State Finance Law § 137 [4] [b]).

This date is critical because the lawsuit must be started within one year from that fixed point. In this case, Windsor proffers as the date upon which this one-year period begins the date of the favorable arbitration determination. To so calculate this date, it relies on a combination of the final payment provision (“when the Subcontractor’s work is fully performed in accordance with the requirements of the Contract Documents, the Architect has issued a Certificate for Payment covering the Subcontractor’s completed Work and the Contractor has received payment from the Owner”) and the arbitration clause (“[a]ny controversy or claim between the Contractor and the Subcontractor arising out of or related to this Subcontract, or the breach thereof, shall be settled by arbitration”). We reject Windsor’s contract-based calculation of the measuring date.

Our holding focuses principally on when the one-year limitations period begins to run, within the meaning of State Finance Law § 137 (4) (b).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clean Earth of North Jersey, Inc. v. Northcoast Maintenance Corp.
142 A.D.3d 1032 (Appellate Division of the Supreme Court of New York, 2016)
American Architectural, Inc. v. Marino
34 Misc. 3d 194 (New York Supreme Court, 2011)
Phelps Guide Rail v. United States Fidelity & Guaranty Co.
26 A.D.3d 838 (Appellate Division of the Supreme Court of New York, 2006)
Specialty Products & Insulation Co. v. St. Paul Fire & Marine Insurance
788 N.E.2d 604 (New York Court of Appeals, 2003)
Windsor Metal Fabrications, Ltd. v. General Accident Insurance Co. of America
295 A.D.2d 502 (Appellate Division of the Supreme Court of New York, 2002)
Windsor Metal Fabrications, Ltd. v. Scott & Schechtman
286 A.D.2d 732 (Appellate Division of the Supreme Court of New York, 2001)
A. Servidone, Inc. v. Bridge Technologies, L. L. C.
280 A.D.2d 827 (Appellate Division of the Supreme Court of New York, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
722 N.E.2d 58, 94 N.Y.2d 124, 700 N.Y.S.2d 90, 1999 N.Y. LEXIS 3742, Counsel Stack Legal Research, https://law.counselstack.com/opinion/windsor-metal-fabrications-ltd-v-general-accident-insurance-ny-1999.