American Architectural, Inc. v. Marino

34 Misc. 3d 194
CourtNew York Supreme Court
DecidedOctober 3, 2011
StatusPublished
Cited by2 cases

This text of 34 Misc. 3d 194 (American Architectural, Inc. v. Marino) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Architectural, Inc. v. Marino, 34 Misc. 3d 194 (N.Y. Super. Ct. 2011).

Opinion

[196]*196OPINION OF THE COURT

Carolyn E. Demarest, J.

In this action by plaintiff American Architectural, Inc. (AAI) arising out of a subcontract in connection with a public improvement construction project, defendants AMCC Corp. (AMCC), Charles Marino, and Liberty Mutual Insurance Company (Liberty) (collectively, defendants) move for an order, pursuant to CPLR 3211, dismissing AAI’s entire complaint as against them for failure to comply with a contractual dispute resolution procedure, and dismissing the second and third causes of action of AAI’s complaint based upon a contractual “no damages for delay” clause.

Facts

On February 3, 2006, AMCC, as general contractor, entered into a prime contract with the Dormitory Authority of the State of New York (DASNY) with respect to a public improvement construction project known as Brooklyn College New West Quad Building, at 2900 Bedford Avenue, in Brooklyn, New York (the project). Pursuant to the requirements of the prime contract and State Finance Law § 137, on February 9, 2006, Liberty, as surety, issued a labor and material payment bond (the payment bond) to AMCC, as principal, in the amount of $58,439,000, naming DASNY, as the owner and obligee. On August 8, 2006, AMCC, as contractor, entered into a written subcontract agreement (the subcontract), dated as of April 7, 2006, with AAI, as subcontractor, whereby AAI agreed to furnish and install certain specified steel, aluminum, and glass systems and elements for the project for a price of $7,754,000.

Article XXXXI of the subcontract, entitled “Dispute Resolution Procedure,” provided, in pertinent part, as follows:

“XXXXI. DISPUTE RESOLUTION PROCEDURE: Notwithstanding anything in this Subcontract and Prime Contract to the contrary, any disputes, claims or questions which arise during the Work shall be resolved in accordance with Contractor’s dispute resolution procedures as amended from time to time. A copy of the current dispute resolution procedure is attached hereto as Rider B and made a part hereof.”

Rider B to the subcontract, in turn, provided, in pertinent part, as follows:

“No claim, dispute, or questions arising out of or in [197]*197relation to the Subcontract, including without limit its interpretation, enforcement, performance, or application, shall give rise to, or be the subject of, an action or proceeding against the Contractor unless, as an express condition precedent thereto: (a) Subcontractor has exhausted all applicable procedures provided by Contractor, this Subcontract and/or the Prime Contract to requisition payments or, as the case may be, to apply for a change order, supplemental agreement or any other type or form of relief; and, in the case of an application for a payment, change order, supplemental agreement or any other type or form of relief which has already been denied or opposed by Contractor, has filed a written and verified notice of claim (‘Notice of Claim’) setting forth: (i) the dollar amount or other particular relief applied for; (ii) a specific and detailed description of the ground for the application for a payment, relating the dollar amount or other particular relief applied for to the events or occurrences referred to by the application; (iii) the manner in which the dollar amount applied for was calculated, or the manner in which any other relief applied for was formulated and how such relief is expected to assist or benefit the Subcontractor or the Work; and (iv) the date (or dates) of any events or occurrences underlying the application or pertaining to it. The failure to include all pertinent dates shall constitute an absolute and unconditional waiver of Subcontractor’s right to recover compensation under its Notice of Claim, and a Res Judicata bar to any action Subcontractor commences concerning that Notice of Claim.
“The Notice of Claim must be served on Contractor by filing an original with Contractor’s home office and a copy to Contractor’s field superintendent within seven (7) working days of Contractor’s action that Subcontractor disputes, questions, or seeks to review. The Contractor’s failure or omission to grant or approve the Subcontractor’s application for a change order, supplemental agreement or other type or form of relief within fifteen (15) days of Subcontractor’s submission of same to Contractor shall be deemed the Contractor’s denial of such application. . . .
“Failure to strictly comply with the Dispute Resolu[198]*198tion Procedure herein set forth, and strictly within the time periods herein set forth, shall constitute an absolute and unconditional waiver of Subcontractor’s right to recover extra or additional compensation, contractual payments, or such other relief as is sought in any particular circumstances, and shall preclude any action or proceeding by Subcontractor against Contractor to the extent such action or proceeding seeks the extra or additional compensation, contractual payments, or other relief that have been waived as herein provided. In any action or proceeding by Subcontractor against Contractor arising out of or in relation to, or in any manner or to any extent involving or referring to this Subcontract, the Prime Contract, or the work at the Project, as a further express and absolute condition precedent to the commencement of such action or proceeding, Subcontractor shall specifically plead full compliance with the Dispute Resolution Procedure herein in its Complaint or other pleading, the failure of which pleading shall constitute a bar to the action or proceeding and a ground for dismissal thereof. . . .
“Contractor or any other person designated by Contractor in Contractor’s sole and unreviewable discretion, shall be the sole arbiter of all claims, disputes, and questions of any nature whatsoever arising out of, or in connection with, or any way related to, or on account of the Contract, and in its capacity as sole arbiter shall determine, among other things, Subcontractor’s entitlement to compensation or other relief and/or the extent to which Subcontractor is entitled to compensation or other relief and all matters pertaining to payments, or relief, if any, as well as the relative responsibility of Contractor or Owner regarding any claim, dispute, difference, question or controversy presented for resolution hereunder by Subcontractor. The said determinations by the sole arbiter shall be final, conclusive and binding upon Subcontractor and Contractor; provided, however, that Subcontractor may seek judicial review of any such determination limited solely to the question whether the determination by the sole arbiter was made in bad faith or fraudulently, and Subcontractor knowingly and voluntarily waives all other rights, claims, causes of ac[199]*199tion, and remedies, including breach of contract, against Contractor.”

In addition, article XIII of the subcontract contained a “no damages for delay” clause, which, in pertinent part, provided as follows:

“DELAY: . . . Contractor owes no damage, duty, obligation, or liability to Subcontractor as a result of any delay, interference, suspension, or other event, except for seeking an extension of time from Principal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Architectural, Inc. v. Marino
109 A.D.3d 773 (Appellate Division of the Supreme Court of New York, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
34 Misc. 3d 194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-architectural-inc-v-marino-nysupct-2011.