Chittenden Lumber Co. v. Silberblatt & Lasker, Inc.

43 N.E.2d 459, 288 N.Y. 396, 1942 N.Y. LEXIS 1003
CourtNew York Court of Appeals
DecidedJuly 29, 1942
StatusPublished
Cited by38 cases

This text of 43 N.E.2d 459 (Chittenden Lumber Co. v. Silberblatt & Lasker, Inc.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chittenden Lumber Co. v. Silberblatt & Lasker, Inc., 43 N.E.2d 459, 288 N.Y. 396, 1942 N.Y. LEXIS 1003 (N.Y. 1942).

Opinion

Lewis, J.

In the construction of a public improvement at Kings Park State Hospital the defendant-respondent, Silberblatt & Lasker, Inc., was the general contractor. Dixon Concrete Construction Co. Inc., held a subcontract for certain concrete work *400 required under the general contract. When Dixon defaulted on its subcontract the work was completed by the general contractor at a cost exceeding any balance due the sub-contractor. The plaintiff-appellant and each of the defendants-appellants had supplied the sub-contractor with building materials or the use of construction equipment employed in carrying out the contract with the State. Each of the appellants, as an unpaid creditor of the sub-contractor, filed a notice of lien and each has sued to foreclose its lien. As no money was due from the general contractor to the subcontractor following the completion of the defaulted subcontract the efforts by the creditor-lienors to recover under the Lien Law were futile. (Lien Law, § 5; Cons. Laws, ch. 33; Devitt v. Schottin, 274 N. Y. 188, 194; Schuessler v. Metropolitan Casualty Ins. Co., 240 App. Div. 449; affd., 265 N. Y. 48; Herrmann & Grace v. Hillman, 203 N. Y. 435, 440, 441.)

In the state of the law prior to 1938, the courts, and apparently the Legislature, recognized the fact that “if [as in the case at bar] the contractor, owes no money to the subcontractor, then laborers employed by the subcontractor, like persons furnishing materials to the subcontractor, may go unpaid.” (Devitt v. Schottin, supra, p. 194; and see Report of the Joint Legislative Committee on State Fiscal Policies [Leg. Doc. No. 41, 161st Session] at p. 158.) In an apparent effort to afford greater protection to laborers and materialmen on public improvement contracts with the State, the Legislature by chapter 707 of the Laws of 1938, added to the State Finance Law (Cons. Laws, ch. 56) a new section (38a) which was later renumbered section 137 (L. 1940, ch. 593) and provides as follows:

“ 137. Bond to secure laborers and materialmen. In addition to other bond or bonds, if any, required by law for the completion of a work specified in a contract for the prosecution of a public improvement for the state of New York, or in the absence of any such requirement, the comptroller may nevertheless require prior to the approval of any such contract a bond guaranteeing prompt payment of moneys due to all persons supplying the contractor or a sub-contractor with labor and materials employed and used in carrying out the contract, which bond shall inure to the benefit of the persons supplying such labor and materials. In order to secure any rights and benefits conferred herein, laborers having claims for *401 unpaid wages shall file and enforce a wage claim as provided by the labor law or shall file and enforce a mechanic’s lien pursuant to the provisions of the lien law, and a materialman, in order to secure any such rights and benefits, shall file and enforce a mechanic’s lien pursuant to the provisions of the lien law.” (Emphasis supplied.)

In the present case the Comptroller exercised the right given him by section 137 and accordingly, prior to his approval of the public improvement contract involved herein, he required of, and was furnished by the general contractor a“ bond to secure laborers and materialmen,” as provided by the statute. Upon that bond the respondent Silberblatt & Lasker Inc., the general contractor, is principal and the respondent insurance company is surety. The bond provides: “ Whereas, the Comptroller of the State of New York, under the terms of Chapter 707 of the Laws of 1938, has required this bond guaranteeing prompt payment of moneys due to all persons supplying the contractor or a sub-contractor with labor and materials employed and used in carrying out the contract, which bond shall inure to. the benefit of the persons supplying such labor and materials. Now, therefore, the condition of the foregoing obligation is such, that if the said Principal shall promptly pay all moneys due to all persons supplying the contractor or a sub-contractor with labor and materials employed and used in carrying out the contract, then this obligation shall be null and void, otherwise, to remain in full force and virtue.” (Emphasis supplied.)

In the complaint now before us the first cause of action is for the foreclosure of a mechanic’s lien filed by the plaintiff-appellant as a materialman. The other appellants served answers containing counterclaims for the foreclosure of mechanics’ liens duly filed by each of them. There being no fund to which the appellants’ liens could attach it follows that, although the appellants as lienors have pursued their remedies under the Lien Law, judgment in their favor on the first cause of action must be denied. (Lien Law, § 5; Dewitt v. Schottin, supra, p. 194.)

As to the second cause of action, which is brought as a class action in behalf of the plaintiff and all others similarly situated (see Bleimeyer v. Public Service M. C. Ins. Corp., 250 N. Y. 264, 269) the plaintiff-appellant, and the defendants-appellants by counterclaims in their answers, demand payment of sums due to *402 them respectively from the sub-contractor, which demands are based upon obligations incurred by the principal and surety when the labor and material-bond, quoted in part above, was executed.

Following the service of answers by the present respondents and the appellant lienors, Special Term denied the plaintiff’s application, under rule 113 of the Rules of Civil Practice, for an order striking out the answer of the general contractor and its surety and for judgment in favor of the plaintiff and the defendant lienors. By the same order Special Term granted a cross-motion by the general contractor and its surety under rule 113 (id) for an order dismissing the complaint of the plaintiff and the counterclaims of the defendant lienors. The judgment entered upon the order of Special Term was thereafter affirmed by the Appellate Division, one justice dissenting. The case comes before us on appeal by the plaintiff and defendant lienors as of right.

The interpretation of section 137 of the State Finance Law for which the general contractor and its surety contend, would deny recovery herein to the appellant lienors because there is no fund due the sub-contractor to which their liens may attach. The respondents’ argument runs as follows: It is conceded that following default by the sub-contractor the cost of completion of the subcontract by the general contractor exceeded any balance due thereupon and left no fund to which liens filed by the appellant lienors could attach. That fact, it is said, serves to defeat the appellant lienors’ right to recover on the labor and material bond, executed by the general contractor and its surety, because section 137 of the State" Finance Law provides that in order to secure the rights and benefits afforded by that statute,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Architectural, Inc. v. Marino
34 Misc. 3d 194 (New York Supreme Court, 2011)
Morin v. Empiyah & Co., LLC
389 F. Supp. 2d 506 (S.D. New York, 2005)
Harsco Corp., Patent Construction Systems Division v. Gripon Construction Corp.
301 A.D.2d 90 (Appellate Division of the Supreme Court of New York, 2002)
Windsor Metal Fabrications, Ltd. v. General Accident Insurance Co. of America
250 A.D.2d 148 (Appellate Division of the Supreme Court of New York, 1998)
Murnane Associates, Inc. v. Harrison Garage Parking Corp.
239 A.D.2d 882 (Appellate Division of the Supreme Court of New York, 1997)
Scaccia Concrete Corp. v. Hartford Fire Insurance
212 A.D.2d 225 (Appellate Division of the Supreme Court of New York, 1995)
Davidson Pipe Supply Co. v. Wyoming County Industrial Development Agency
648 N.E.2d 468 (New York Court of Appeals, 1995)
Hempstead Concrete Corp. v. Elite Associates., Inc.
203 A.D.2d 521 (Appellate Division of the Supreme Court of New York, 1994)
Davidson Pipe Supply Co. v. Wyoming County Industrial Development Agency
196 A.D.2d 240 (Appellate Division of the Supreme Court of New York, 1994)
Dutchess Quarry & Supply Co. v. Firemen's Insurance Co. of Newark
190 A.D.2d 36 (Appellate Division of the Supreme Court of New York, 1993)
Pennex Aluminum Co. v. International Fidelity Insurance
818 F. Supp. 772 (M.D. Pennsylvania, 1993)
Conesco Industries, Ltd. v. St. Paul Fire & Marine Insurance
184 A.D.2d 956 (Appellate Division of the Supreme Court of New York, 1992)
Syracuse Supply Co. v. Seaboard Surety Co.
167 A.D.2d 830 (Appellate Division of the Supreme Court of New York, 1990)
La Vallee v. Peer
104 Misc. 2d 943 (New York Supreme Court, 1980)
Finger Lakes Racing Ass'n v. Western Regional Off-Track Betting Corp.
83 Misc. 2d 761 (New York Supreme Court, 1975)
Callanan Industries, Inc. v. Fretto
42 A.D.2d 664 (Appellate Division of the Supreme Court of New York, 1973)
Gerosa Crane Service, Inc. v. International Products, Ltd.
70 Misc. 2d 176 (Civil Court of the City of New York, 1972)
Kipp Bros. v. Hartford Accident & Indemnity Co.
63 Misc. 2d 788 (New York Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
43 N.E.2d 459, 288 N.Y. 396, 1942 N.Y. LEXIS 1003, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chittenden-lumber-co-v-silberblatt-lasker-inc-ny-1942.