Kalisch-Jarcho, Inc. v. City of New York

448 N.E.2d 413, 58 N.Y.2d 377, 461 N.Y.S.2d 746, 1983 N.Y. LEXIS 2931
CourtNew York Court of Appeals
DecidedMarch 29, 1983
StatusPublished
Cited by222 cases

This text of 448 N.E.2d 413 (Kalisch-Jarcho, Inc. v. City of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kalisch-Jarcho, Inc. v. City of New York, 448 N.E.2d 413, 58 N.Y.2d 377, 461 N.Y.S.2d 746, 1983 N.Y. LEXIS 2931 (N.Y. 1983).

Opinions

OPINION OF THE COURT

Fuchsberg, J.

The pivotal point on this appeal is whether, under the facts and circumstances of this action for breach of a construction contract, it was reversible error, in the face of a “no-damage-for-delay” exculpatory clause, for the trial court to refuse to charge that the contractor could not recover for delays allegedly caused by the contractee, the City of New York, unless these were actuated by bad faith and deliberate intent. The exculpatory clause, article 13 of the contract, reads as follows: “The Contractor agrees to make no claim for damages for delay in the performance of this contract occasioned by any act or omission to act of the City or any of its representatives, and agrees that any such claim shall be fully compensated for by an extension of time to complete performance of the work as provided herein”.

[381]*381In a strenuously contested trial, the plaintiff, Kalisch-Jarcho, Inc., the successful bidder, at $8,033,000, for the heating, ventilating and air-conditioning component in the construction of the new New. York City police headquarters, offered proof calculated, essentially, to convince the jury that the progress of its work was subjected to drastic and costly delays which stretched out the time for the job’s completion, originally fixed at 1,000 consecutive calendar days, for an additional 28 months.1 Attributing this solely to the city’s “endless” revisions of scores of plans and drawings, to its failure to co-ordinate the activities of its prime contractors, of which plaintiff was one of four, and to other acts of omission or commission interfering with the sequence and timing of the work, Kalisch sought $3,311,960 in damages.2

On trial, it was at Kalisch’s specific request that the jury was instructed that, notwithstanding the exculpatory clause, to bring in a verdict for the plaintiff it would have to find no more than that “the delay was caused by conduct constituting active interference”. Relevant also is Kalisch’s position that the right" to challenge the correctness of this charge was not preserved for our review.

The city, in defense, also raised issues of fact and of law. Contending that the delays were well within the contemplation of the parties, it presented evidence on which, among other things, it was possible to hold that, at the time of the bidding, the plaintiff knew that many of the drawings still were incomplete and so entered into the contract with eyes open. Moreover, the city attempted to show that the delay in any event was either greatly exaggerated or not of its making. From Kalisch’s own partial payment requisitions, it argued, for instance, that 97.4% of this contractor’s work was complete fully nine months before the formal completion, only routine punch list items remaining open thereafter. The city also relied on the fact that for a considerable period an industry-wide strike [382]*382immobilized the project. But, above all, by way of affirmative defense, it relied on the exculpatory clause, the thrust of which, in its view, was to insulate it from any finding of delay based on less than “bad faith and deliberate intent”.

In this context, the jury rendered a general verdict for the plaintiff in the sum of $806,382 to cover “delay damages [including claims of] subcontractors”, whose separate damage assertions had been incorporated into the Kalisch complaint. The verdict took the form of a response to the last of a series of interrogatories drafted by the Trial Judge and, after some hesitancy by the city’s counsel, submitted to the jury by consent of the parties. Important too is the jury’s affirmative answer to the interrogatory which asked whether “the delay, interference or obstruction” was within the contemplation of the parties at the time the contract was made. In addition, other replies placed responsibility for the delay on both parties and then placed 63% of the blame on the city and 37% on Kalisch. And, by its answer to an interrogatory cast in language conforming to the Judge’s charge, the jury further affirmed that the delay or obstruction caused by the conduct of the city constituted “active interference”.

Judgment on the verdict, inclusive of interest, having been entered in the sum of $949,645.35, the city took an appeal to the Appellate Division, which affirmed without opinion. Because, on our examination of the record, we find that the correctness of the trial court’s “active interference” charge was saved for our consideration, and, in our view, a stricter standard is required, the order of affirmance cannot stand. Our reasons follow.

Preliminarily, as to preservation, Kalisch’s presentation is two-pronged. First, it argues that the city failed to note its exception to the charge and, second, that, assuming it had, the city in effect waived any error by acquiescing in the form of the interrogatories, which, as afore-mentioned, contained a question parroting the “active interference” charge. We find neither ground persuasive.

In essence, CPLR 4110-b provides for the filing of written requests to charge, for the court’s informing counsel of its rulings and, when adverse, for counsel to have an opportunity for meaningful objection before the jury re[383]*383tires. On the specific matter before us now, the city in writing duly requested a charge that unless it be proved that the city “[had] acted in bad faith and with deliberate intent [to delay] the plaintiff in the performance of its obligation, plaintiff [could] not recover”. In so doing, it merely kept to the legal tack it had taken, unswervingly, from the beginning of the trial. For his part, the Trial Judge, when pressed on the same request at a charge conference, if less than explicit, left no doubt of his intention to tell the jury no such thing. For, not only did he state, “I’m not going to use the word ‘intent’ ”, explaining in the process that “An intent is an important ingredient in a crime”, but went on to add, “In fact, the City of New York may have done certain things with all the good intention in the world and committed a wrong.”3 Moreover, after the court acted on this communication by charging the “active interference” formulation, when counsel began to intone each of his earlier objections, the court interrupted to assure him that all written requests had been studied and, in the interest of time, could be deemed adequately protected by blanket exception. In light of the court’s elaboration of its ruling, the denial of the city’s request had the earmarks of an “irrevocable” decision (Meagher v Long Is. R. R. Co., 27 NY2d 39, 46). In this perspective, counsel’s desistance from continuing his ad seriatim recitation must be taken fairly as acceptance of the court’s suggestion.

Nor was the city’s ultimate acquiescence in the query as to whether there had been “active interference” a waiver of its underlying contention. The Trial Judge already had ruled that he would submit the case on the contractor’s rather than the city’s legal theory. The interrogatory in question was but a mechanism by which the jury was to say whether there was enough credible proof to support that theory. At this purely procedural juncture, to require a rote refrain of an objection so “clearly made and overruled” would have been superfluous (Kulak v Nationwide Mut. Ins. Co., 40 NY2d 140, 145).

[384]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tutor Perini Corp. v. State Univ. Constr. Fund
2025 NY Slip Op 52062(U) (New York Supreme Court, Albany County, 2025)
Henick-Lane, LLC v. Stellar Mgt. Group, Inc.
2025 NY Slip Op 05190 (Appellate Division of the Supreme Court of New York, 2025)
One River Run Acquisition, LLC v. Milde
2025 NY Slip Op 03653 (Appellate Division of the Supreme Court of New York, 2025)
Iberdrola Energy Projects v. Oaktree Capital Mgt. L.P.
2024 NY Slip Op 03798 (Appellate Division of the Supreme Court of New York, 2024)
Audthan v. Nick & Duke
New York Court of Appeals, 2024
New Enterprise Associates 14, L.P. v. Rich
Court of Chancery of Delaware, 2023
MLB Constr. Servs., LLC v. Dormitory Auth. of the State of N.Y.
2021 NY Slip Op 02852 (Appellate Division of the Supreme Court of New York, 2021)
CWCapital Cobalt VR Ltd. v. CWCapital Invs. LLC
2021 NY Slip Op 02487 (Appellate Division of the Supreme Court of New York, 2021)
Matter of Part 60 Put-Back Litig.
2019 NY Slip Op 368 (Appellate Division of the Supreme Court of New York, 2019)
Klapper v. Graziano
129 A.D.3d 674 (Appellate Division of the Supreme Court of New York, 2015)
People v. Cruz
129 A.D.3d 119 (Appellate Division of the Supreme Court of New York, 2015)
TIAA Global Investments, LLC v. One Astoria Square LLC
127 A.D.3d 75 (Appellate Division of the Supreme Court of New York, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
448 N.E.2d 413, 58 N.Y.2d 377, 461 N.Y.S.2d 746, 1983 N.Y. LEXIS 2931, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kalisch-jarcho-inc-v-city-of-new-york-ny-1983.