Johnson v. City of New York

191 A.D. 205, 181 N.Y.S. 137, 1920 N.Y. App. Div. LEXIS 4686
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 26, 1920
StatusPublished
Cited by19 cases

This text of 191 A.D. 205 (Johnson v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. City of New York, 191 A.D. 205, 181 N.Y.S. 137, 1920 N.Y. App. Div. LEXIS 4686 (N.Y. Ct. App. 1920).

Opinion

Blackmar, J.:

The plaintiffs, contractors, have recovered a judgment for $5,345.22 against the city of New York for damages caused by the suspension of their work in constructing a sewer. The city, appealing, claims that by the express terms of the contract such damages are at the charge of the contractors. The contract, which was made on September 19, 1912, was for the construction of a section of a sewer in Staten Island. Work was begun soon thereafter and continued until March 6, 1913, when the engineer in charge notified plaintiffs to cease work on account of the failure of the board of estimate and apportionment to appropriate sufficient funds to pay for the engineering and inspection necessary to complete the sewer. Work was accordingly suspended until May 17, 1913, when, the requisite appropriation of funds having been made, it was, on the direction of the defendant, resumed and completed. It is for the damages caused by the suspension of the work that the judgment under consideration was rendered.

The contract contains the following clause: “ The President [of the borough] may suspend the whole or any part of the work herein contracted to be done if he shall deem it for the interest of' The City so to do, without compensation to the Contractor for such suspension other than extending the time for completing the work as much as it may be, in the opinion of the President, delayed by such suspension.” As I understand it, the claim of the appellant that it is not liable rests primarily upon this clause in the contract.

[207]*207If the clause is applicable to the suspension of the work under the circumstances of this case, the contractors must suffer the heavy loss caused thereby. In the absence of fraud or mistake, the contract made by the parties, however burdensome it may prove in execution, must govern. It is no excuse that a party to a contract did not foresee a hardship which its operation might entail. It is the function of the courts to enforce contracts according to their true intent and meaning, and neither to mitigate nor relieve against their operation. (Norcross v. Wills, 198 N. Y. 336; Mechanics’ Bank v. City of New York, 164 App. Div. 128.) This contract gives the president of the borough the right to suspend the work whenever he deems it for the interests of the city so to do. This is not an arbitrary power, to be exercised at his will. It must be used in the just interests of the city. The limitation of the power is prescribed in the phraseology of the clause which grants it. The intent of the parties, which is the touchstone of interpretation, must, however, be gathered from the whole contract, read in the light of the existing facts with reference to which it was framed. The contract imposed certain obligations on each of the parties. The city was under the obligation, necessarily implied, to furnish the funds required to discharge the expense of the supervision under which the plaintiffs were to do the work. This is as plainly the duty of the city as if it had been written into the contract in so many words. Without this, the work could not proceed. The work must be supervised, measured and approved by engineers in the employ of the city. It was by virtue of such supervision that the city was to secure the proper performance of the contract, and the plaintiffs agreed to submit their work to the city’s engineer and accept his arbitrament as to its character, measure and value. As the work could not proceed without engineering and inspection, the obligation of the city to furnish engineers and inspectors was concurrent with the work. An obligation necessarily implied from the whole purpose and scope of the contract is as much a part thereof as if expressed in its wording. (Mansfield v. N. Y. C. & H. R. R. R. Co., 102 N. Y. 205; City of New York v. Delli Papli, 202 id. 18; Wigand v. Bachmann-Bechtel Brewing Co., 222 id. 278.) It is obvious that the president of the [208]*208borough assumed to suspend the work because the city had failed in its obligation under the contract to furnish inspectors and engineers. The letter of the engineer in charge, expressing the president’s direction to suspend work, puts it squarely upon that ground, and the undisputed evidence of the case is that when the work was suspended the unincumbered balance in the fund applicable to the expense of supervision was only $6.97, whereas the February payroll for engineers and inspectors, then unpaid, was $349.60, and the estimated engineers’ and inspectors’ salaries for the time necessary to complete the work was $988.

Was it the intent of the parties that this power to suspend work, entailing as it did great expense on the contractors, could be exercised because the city had failed in the performance of its obligation? I think not. It cannot be assumed that a clause in the contract was intended to authorize one of the parties to impose the result of its own default upon the other. A court should not so interpret a contract unless required so to do by the most explicit terms. There is room enough for the proper operation of the clause without giving it an interpretation so unreasonable. The city was bound to furnish inspectors and engineers. Without them the work could not proceed. The city suspended work on the contract because it had no appropriation for such engineering and inspection. Therefore, the city suspended the work because it had failed in its obligation. The quoted clause cannot be construed to authorize such an unreasonable and unjust result. It cannot in its true meaning be said to authorize the suspension of the work in the interest of the city, when used to relieve the city from the result of a violation of its duty under the contract. It is the interest of the city in performance and not in breach which justifies a suspension of the work.

As no other point was made by the brief of the appellant, it is unnecessary to consider other points discussed by the respondents.

The judgment and order should be affirmed, with costs.

Present—Jenks, P. J., Mills, Putnam, Blackmar and Kelly, JJ.

Judgment and order unanimously affirmed, with costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Earthbank Co. v. City of New York
145 Misc. 2d 937 (New York Supreme Court, 1989)
Forward Industries, Inc. v. Rolm of New York Corp.
123 A.D.2d 374 (Appellate Division of the Supreme Court of New York, 1986)
Corinno Civetta Construction Corp. v. City of New York
493 N.E.2d 905 (New York Court of Appeals, 1986)
Bradley Environmental Constructors v. Village of Sylvan Beach
98 A.D.2d 973 (Appellate Division of the Supreme Court of New York, 1983)
Kalisch-Jarcho, Inc. v. City of New York
448 N.E.2d 413 (New York Court of Appeals, 1983)
New Again Construction Co. v. City of New York
76 Misc. 2d 943 (New York Supreme Court, 1974)
Peckham Road Co. v. State
32 A.D.2d 139 (Appellate Division of the Supreme Court of New York, 1969)
Reiss & Weinsier, Inc. v. United States
116 F. Supp. 562 (Court of Claims, 1953)
In re the Arbitration between Herbert G. Martin, Inc. & Municipal Housing Authority
277 A.D.2d 904 (Appellate Division of the Supreme Court of New York, 1950)
Endres Plumbing Corp. v. State
198 Misc. 546 (New York State Court of Claims, 1950)
Shore Bridge Corp. v. State
186 Misc. 1005 (New York State Court of Claims, 1946)
De Riso Bros. v. State
161 Misc. 934 (New York State Court of Claims, 1937)
American Bridge Co. v. State
245 A.D. 535 (Appellate Division of the Supreme Court of New York, 1935)
Moran Bros. Contracting Co. v. City of New York
154 Misc. 802 (City of New York Municipal Court, 1935)
Wilson & English Construction Co. v. New York Central Railroad
240 A.D. 479 (Appellate Division of the Supreme Court of New York, 1934)
Wright & Kremers, Inc. v. State
238 A.D. 260 (Appellate Division of the Supreme Court of New York, 1933)
John T. Brady & Co. v. Board of Education of School District
222 A.D. 504 (Appellate Division of the Supreme Court of New York, 1928)
People Ex Rel. Wells Newton Co. v. . Craig
133 N.E. 419 (New York Court of Appeals, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
191 A.D. 205, 181 N.Y.S. 137, 1920 N.Y. App. Div. LEXIS 4686, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-city-of-new-york-nyappdiv-1920.