Mansfield v. . N.Y.C. H.R.R.R. Co.

6 N.E. 186, 102 N.Y. 205, 1886 N.Y. LEXIS 824
CourtNew York Court of Appeals
DecidedApril 13, 1886
StatusPublished
Cited by45 cases

This text of 6 N.E. 186 (Mansfield v. . N.Y.C. H.R.R.R. Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mansfield v. . N.Y.C. H.R.R.R. Co., 6 N.E. 186, 102 N.Y. 205, 1886 N.Y. LEXIS 824 (N.Y. 1886).

Opinion

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 207 This action was brought to recover the damages arising from a breach by the defendant of a contract made by it on April 5, 1876, with Gill Mansfield for the construction of an elevator. The complaint alleges as a breach that the defendants failed to have the foundations ready for the erection of the elevator, at the time notice was served upon them and they were required to commence work for its construction, and claim damages therefor by reason of increased expense in doing the work and supplying materials, and loss of gain or profits, arising from the delay occasioned by the want of readiness on the part of the owners. Upon the trial all proof on the part of the plaintiff tending to show the cause of action set out in the complaint, with the damages arising therefrom, was objected to by the defendant and excluded by the court under the plaintiff's exception.

The decision of the court seems to have been based upon the assumption that there was no covenant on the part of the defendant to have the foundations ready at the time of giving notice thereof, and such seems to have been the opinion of the General Term in affirming the judgment.

An examination of the terms of the contract is necessary to determine the correctness of the views taken by the court below. That instrument provided, among other things, that Gill Mansfield should furnish the materials and perform the work in erecting the superstructure of an elevator, over the water, upon piers in the Hudson river between Sixtieth and Sixty-first streets in New York, and should finish the same within five months from the time of the commencement of the work, and should receive as their compensation therefor the sum of $331,500, and the further sum of $500 per day for each day less than that time occupied in its construction. It was further provided that they should pay the defendant as *Page 210 liquidated damages the sum of $500 per day for each day in excess of that time, during which the completion of the work should be prolonged.

With respect to the time of the commencement of the work it was provided: "The said parties of the first part hereby further agree to commence the erection of the elevator within five days after notice from the engineer that the foundations are ready and to complete the same ready for the use of all the lofting elevators within five months thereafter." "Whenever the word `engineer' is used in the specifications reference is had to the engineer-in-chief in charge of the work for the party of the second part, to this contract."

It seems to us that the courts below have mistaken the plain reading and import of this contract. It is true that there is no express provision in it requiring the foundations, or any part of them to be ready at any particular time. So neither is there any such provision requiring any foundations at all to be built by the owners; but the clearest implication arises from the language of the agreement, and its avowed object and intent, that the property of the owners upon which the building was to be erected, should be prepared for the superstructure by such owners, and that the contractors should have notice whenever that time arrived. It was the indispensable condition to the performance of any of the obligations incurred by the contractors that the foundations should be prepared, and unless they were to be so prepared, it rendered the whole contract motiveless and nugatory.

It is not denied by the respondent but that the duty of preparing the foundations was assumed by it, but it is urged that there is no provision in the contract requiring it to have all of the foundations, or any particular portion of them, ready at the time of giving the notice of readiness stipulated for in the agreement. In this we think it is mistaken.

It was made the duty of the owner not only to prepare the foundations for the reception of the work of the contractors, but also to notify them, through their agent, of the fact of such readiness. The terms of the contract plainly imply that the *Page 211 notice was to be of an actually existing condition, and not the expression of an opinion on the part of the engineer that the foundations were sufficiently advanced to enable the contractors to prosecute their work advantageously. The contractors have not submitted any such question to the decision either of the owners or their engineer, and in view of the heavy obligations assumed by them it would have been unwise and hazardous to have done so. There is no rule of construction or principle of law which will justify a party who is required by contract to give notice to another of the existence of a fact upon which important obligations depend, to do so untruly, or in such a manner as to prejudice the contractual rights and privileges of the party entitled to notice. It was held by this court in the case ofPeck v. Collins (70 N.Y. 376), that notice of readiness to perform implies readiness on the part of the party giving such notice, and if he was not in fact ready, neglect to perform on the part of the other party constitutes no default. It is a well-settled principle of law in the construction of contracts that when the obligation of performance by one party presupposes the doing of some act on the part of the other prior thereto, that the neglect or refusal to perform such act not only dispenses with the obligation of performance by the other, but also entitles him to rescind, or when rescission will not afford him an adequate remedy, to continue the work and recover such damages as the delinquency has occasioned, against the defaulting party. (Cross v. Beard, 26 N.Y. 85, 88.)

The meaning of a contract is to be gathered from a consideration of all of its provisions, and the inferences naturally derivable therefrom, as to the intent and object of the parties in making it, and the result which they intended to accomplish by its performance. It was said by ALLEN, J., inBooth v. Cleveland Mill Co. (74 N.Y. 15, 21): "There is no particular formula of words or technical phraseology necessary to the creation of an express obligation to do or forbear to do a particular thing or perform a specified act. If from the text of an agreement and the language of the parties, either in the body of the instrument or in the recital or references, there is *Page 212 manifested a clear intention that the parties shall do certain acts, courts will infer a covenant in the case of a sealed instrument, or a promise if the instrument is unsealed, for non-performance, of which an action of covenant or assumpsit will lie." It was said by Judge DANFORTH in New England IronCo. v. Gilbert Elevated R.R. Co. (91 N.Y. 153, 165), that "although the defendant does not in express terms undertake to do the act, or give the notice which shall set the plaintiff in motion, a promise to do so" "is clearly to be implied from the covenants and stipulations which were inserted." "There is manifested a clear intention on the part of the defendant to construct the railway, and for that purpose to do certain things, among others, raise the money, provide the masonry and give instructions to the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Highway Commission v. Garton & Garton, Inc.
418 P.2d 15 (Wyoming Supreme Court, 1966)
Studer v. Rasmussen
344 P.2d 990 (Wyoming Supreme Court, 1959)
Mainieri v. Magnuson
272 P.2d 557 (California Court of Appeal, 1954)
Dorsey v. Oregon Motor Stages
194 P.2d 967 (Oregon Supreme Court, 1947)
Shore Bridge Corp. v. State
186 Misc. 1005 (New York State Court of Claims, 1946)
R. H. Baker Co. v. State
267 A.D. 712 (Appellate Division of the Supreme Court of New York, 1944)
Haley v. Brady
137 P.2d 505 (Washington Supreme Court, 1943)
Becker v. Hercules Foundries, Inc.
263 A.D. 991 (Appellate Division of the Supreme Court of New York, 1942)
Madison County Construction Co. v. State
177 Misc. 777 (New York State Court of Claims, 1941)
Manhattan Fireproofing Co. v. John Thatcher & Son
38 F. Supp. 749 (E.D. New York, 1941)
Taylor-Fichter Steel Construction Co. v. Niagara Frontier Bridge Commission
261 A.D. 288 (Appellate Division of the Supreme Court of New York, 1941)
American Bridge Co. v. State
245 A.D. 535 (Appellate Division of the Supreme Court of New York, 1935)
Wilson & English Construction Co. v. New York Central Railroad
240 A.D. 479 (Appellate Division of the Supreme Court of New York, 1934)
O'Rourke Engineering Construction Co. & Duit, Inc. v. City of New York
229 A.D. 261 (Appellate Division of the Supreme Court of New York, 1930)
Mack v. State
122 Misc. 86 (New York State Court of Claims, 1923)
Beskin v. State
119 Misc. 209 (New York State Court of Claims, 1922)
Degnon Contracting Co. v. City of New York
202 A.D. 390 (Appellate Division of the Supreme Court of New York, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
6 N.E. 186, 102 N.Y. 205, 1886 N.Y. LEXIS 824, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mansfield-v-nyc-hrrr-co-ny-1886.