Haley v. Brady

137 P.2d 505, 17 Wash. 2d 775
CourtWashington Supreme Court
DecidedMay 8, 1943
DocketNo. 28919.
StatusPublished
Cited by18 cases

This text of 137 P.2d 505 (Haley v. Brady) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haley v. Brady, 137 P.2d 505, 17 Wash. 2d 775 (Wash. 1943).

Opinion

Mallery, J.

This action was brought by plaintiffs, as subcontractors, to recover compensation for their services in doing all the lathing and plastering on two ward buildings of the western state custodial school at Buckley. Defendants are the principal contractors and their surety. The bonds were furnished in accordance with Rem. Rev. Stat., §§ 1159-1161 [P. C. §§ 9724-9727], inclusive. The jury’s verdict was for plaintiffs, in the amount of $4,366.22. There was a second cause of action upon which the verdict was for the defendants. This appeal by the defendants deals only with the first cause of action, upon a short written contract and five oral contracts for additional work. The reasonable value of the additional work, as itemized in the complaint, was as follows:

“(1) Suspended ceilings, material and labor...........................$ 190.00
(2) Lathers’ time preparing groundwork .................... 95.06
(3) Padding out and building up crooked walls, etc. (material).... 351.50
(4) Labor on last item........ 439.30
(5) Extra labor cost in preparing ground work for plaster, and. standby time......................... 2,234.78
(6) Increased cost because of change in plant location.............. 992.00
(7) Labor cost, cleaning up........... 100.00
Total.......................$4,402.64”

These items were not numbered in the complaint, but have been given the numbers (1) to (7) as above for the purposes of this opinion.

*777 The evidence was conflicting with regard to the alleged oral contracts and the conditions surrounding the work performed by respondents. The facts which the jury was entitled to find were as follows: The respondents, who composed the partnership of Haley & Smyth, were asked by the appellants in October, 1939, to submit a bid for the lathing and plastering, according to plans and specifications, of the two buildings. The plans furnished them called for a simple plastering and lathing operation. They first submitted a bid of fourteen thousand dollars. Later on, upon the assurance that they were to have a certain fixed and definite place to set up their equipment from which they could carry on their operations, they were asked by the appellants to refigure the bid. They reduced the bid by nine hundred dollars and signed the agreement as follows:

“Brady Construction Company
General Contractors
1166 Mercer Street
Seattle, Washington
Oct. 23, 1939
“Haley & Smith
304 Bell St.,
Seattle, Washington
Re: Ward Building
Western State Custodial School
Buckley, Washington
“Gentlemen:
“This is your order to proceed with the furnishing of all labor and material to do plastering complete on Two Ward Buildings, Western State Custodial School, Buckley, Washington, Graham & Painter, Architects, all according to Plans and Specifications, including Stools, Metal Screeds and grounds and Cement Base. Also includes screeds for stairs if required, but does not include stair base or treads for the sum of— Thirteen Thousand One Hundred and no/100 Dollars ($13,100.00).
*778 The State Sales Tax and all other State and Federal Taxes are to be paid by the Subcontractor
Yours truly,
Brady Construction Co.
By C. D. Brady”
“Accepted:
Haley & Smith
By R. C. Smyth”

Upon reporting for work, respondents discovered that the promised place for their plant location was otherwise occupied by tile setters and brick masons, whose operations had to precede those of respondents. Respondents refused to proceed until the place for their plant location was rendered available, or they were compensated for their increased costs that would be occasioned from operating from some other location.

This was the situation on May 6, 1940, when a definite oral agreement was made and entered into by R. C. Smyth of the respondents, and C. T. Brady of the appellants, in reference to the payment of their increased costs occasioned because of the change in the plant location (item 6 above). The exact amount which respondents were to receive was not stated in so many words, but how it could be arrived at was a matter of fairly simple mathematical computation.

When respondents started their actual lathing operations in the basement portion of the boys’ ward building, it was discovered by them that, in that particular area at least (that being the only section in either building that was then ready for lathing and plastering operations), they were being asked, to carry on an operation that was not in accordance with the plans and specifications. Accordingly on that date, May 13th, Mr. Smyth of respondents entered into an oral agreement with C. T. Brady of the contractors, in reference to their reimbursement for their increased costs upon *779 that particular section of the work and for the remedy of certain defects that would have to be corrected in the window stools in and about the building. This was item 2 as set forth above.

Two days later, on May 15, 1940, an oral agreement was entered into between these same individuals with reference to general cleaning up, which respondents were to do on the two buildings upon the completion of their operation. The amount agreed upon was one hundred dollars (item 7 above).

From May 6, 1940, until and including May 22, 1940, R. C. Smyth repeatedly told C. T. Brady that the contractors’ operations were not then at such an advanced stage that the lathing and plastering operation could be carried on in an orderly and economical manner. He urged that the lathing and plastering operation be deferred until the contractors’ other operations had gotten out of the way. He was assured, however, that the contractors were putting on a larger crew of men and that their operations would, within a few days, be entirely out of respondents’ way. Accordingly, respondents brought their plastering crew to the job on Monday, May 20, 1940. In two days time, all of the plastering had been done by the crew in the area then available in the basement. By that time it became apparent to Mr. Smyth that respondents’ lathing and plastering operations could not proceed under the conditions existing, except at a prohibitive cost to them, and that respondents were then being called upon to do a lathing and plastering job not “all according to plan and specifications” because of the poor, faulty, or incomplete work of the appellants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Of Washington, V. Kareem Babbs
Court of Appeals of Washington, 2022
Consolidated Electrical Distributors, Inc. v. Gier
602 P.2d 1206 (Court of Appeals of Washington, 1979)
City of Seattle v. Dyad Construction, Inc.
565 P.2d 423 (Court of Appeals of Washington, 1977)
Norris Industries v. Halverson-Mason Constructors
529 P.2d 1113 (Court of Appeals of Washington, 1974)
Lacey v. People
442 P.2d 402 (Supreme Court of Colorado, 1968)
Bignold v. King County
399 P.2d 611 (Washington Supreme Court, 1965)
Kaltoft v. Nielsen
106 N.W.2d 597 (Supreme Court of Iowa, 1960)
Studer v. Rasmussen
344 P.2d 990 (Wyoming Supreme Court, 1959)
Fleming v. City of Seattle
275 P.2d 904 (Washington Supreme Court, 1954)
Kilpatrick v. Commissioner
22 T.C. 446 (U.S. Tax Court, 1954)
Atkins v. Churchill
194 P.2d 364 (Washington Supreme Court, 1948)
Dorsey v. Oregon Motor Stages
194 P.2d 967 (Oregon Supreme Court, 1947)
Pfotzer v. Aqua System, Inc.
162 F.2d 779 (Second Circuit, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
137 P.2d 505, 17 Wash. 2d 775, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haley-v-brady-wash-1943.