Gearty v. . Mayor, Etc., of New York

63 N.E. 804, 171 N.Y. 61, 9 Bedell 61, 1902 N.Y. LEXIS 833
CourtNew York Court of Appeals
DecidedMay 13, 1902
StatusPublished
Cited by51 cases

This text of 63 N.E. 804 (Gearty v. . Mayor, Etc., of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gearty v. . Mayor, Etc., of New York, 63 N.E. 804, 171 N.Y. 61, 9 Bedell 61, 1902 N.Y. LEXIS 833 (N.Y. 1902).

Opinion

Bartlett, J.

The plaintiff, on the eighteenth day of May, 1895, entered into a contract with the mayor, aldermen and commonalty of the city of New York, to regulate, set curb' *65 stones and pave with granite block pavement with concrete foundation the roadway or Transverse road Nq. 4, crossing Central Park at Ninety-seventh street from Fifth avenue to Central Park West (Eighth avenue). This is one of the underpass roads crossing Central Park from east to west.

The complaint contains two causes of action: (1) To recover the sum of $440.00 alleged to have been unlawfully deducted for overtime. (2) To recover the sum of $10,000 as damages suffered by reason of certain work being unlawfully, and in breach of the contract, required to be done a second time.

It may be stated, generally, that the answer of the city insists that the deduction for overtime was' properly made and that the work required to be done a second time was exacted, under the express terms of the contract entered into by the plaintiff with the city.

In setting forth his first cause of action, the plaintiff alleged, in substance, that he demanded of the department of public parks of the city of New York, a certificate in writing, containing the number of days delay caused by any act or omission on the part of the plaintiff, as required under the contract, but that the same was unreasonably and in bad faith refused. This allegation is denied by the city.

It is conceded that on the twenty-fifth day of June, 1896, the defendant paid to the plaintiff the sum of $12,396.23 as the total amount admitted by the city as due him under the contract as completed, excepting the amount retained as security for repairs. This left in the hands of the city the sum of $440.00, sued for in the first cause of action, for excess of inspection, twenty-two days at twenty dollars a day, and amount retained as security for repairs. It also left, unadjusted, as plaintiff claims, the value of the work referred to in the second cause of action.

On receiving this amount the plaintiff' gave to the city a receipt reading as follows: Beceived at the office of the Comptroller of the City of New York, this 25 th day of June, 1896, from Ashbel P. Fitch, Comptroller, a warrant on the Chamberlain for $12,396.23 in payment of the above account, *66 which is in full for all claims and demands on this contract, excepting the amount retained as security for repairs.” ■

The plaintiff at the same time executed under seal a general release, which is exacted by the city from all contractors when receiving the last payment on a completed contract in accordance with the final certificate of the engineer of the department of public works.

This instrument releases the city from all claims that the plaintiff has against it by reason of the contract in question on account of “ any matter, cause or thing whatsoever reserved or arising therefrom, from the beginning of the world to the day of the date of these presents, excepting $1,723.33 retained as repairing security; also excepting any legal claim which I may have under and in pursuance of the terms and conditions of the contract herein.”

It is the contention of the plaintiff that he was obliged to execute the receipt and release, under the rules of the comptroller’s office; in order to collect what was admitted to be due him finder the contract; and that the release does not bar this action, as it expressly excepts any legal claim which he has under and in pursuance of the terms and conditions of the contract.

The city gave no evidence at the trial, the motion to dismiss the complaint being granted at the close of the plaintiff’s case.

The plaintiff began work under this contract on notice from the city May 23rd, 1895, and continued without interruption until July, 1895, when a seventy per cent certificate for work done was given him by the engineer of construction, which showed that a certain amount of work had been performed.

The certificate further stated: “ I certify that I have duly examined the above account and compared it with the contract and that it is correct; that the work and materials mentioned above have been performed and delivered as required by the contract and in a satisfactory manner, and that the sum of $7,751.00 is justly due.”

*67 There was also given to the plaintiff at this time the certificate of the commissioners of the department of public parks, which reads as follows: “We hereby certify that we have examined the above account and believe it to be correct ; the prices charged are in accordance with the terms of the contract for regulating, setting curbstones and paving with granite block pavement, with concrete foundation (describing roadway in detail); and that such services as herein specified have been properly performed and according to the certificates of the officers of this department duly appointed to supervise the same.”

Thereafter, and on the twenty-fourth day of July, 1895, the plaintiff received the following notice from the engineer of construction: “ On Monday last I made an examination of the work done by you under your contract for regulating and paving the roadway (describing it) and found it improperly done and not in accordance with the specifications, and I instructed the agent in charge to stop all work being done under the contract, excepting the grading and curbsetting, until the work improperly done was remedied. You are hereby directed to immediately take up and remove the concrete and pavement improperly done — beginning at the westerly end and working toward Fifth avenue until all the -work which has not been done in accordance with the specifications has been removed.”

The plaintiff made vigorous objection to tearing up the completed work, and insisted that it was properly done under the contract, as the previous certificates received from the engineer and commissioners of the department of public parks showed.

Nevertheless, in view of the city’s notice to stop work under the contract, except grading and curbsetting, until the work alleged to have been improperly done was remedied, the plaintiff proceeded to remove the completed work and laid it over again as required.

While the complaint contains two causes of action, it is obvious that the main and controlling question in this case is *68 whether, under the terms of the contract between the plaintiff and the city, the course pursued by the engineer of construction is justifiable.

There is also the additional question whether any of the conceded acts of. the plaintiff amount to an estoppel or waiver as to the causes of action now sought to be enforced.

The agreements which contractors are required to execute before entering upon city work are exceedingly stringent in their provisions against contractors and in favor of the municipality, and the former must determine in the first instance whether it is advisable to assume obligations that may prove very onerous.

It remains only for the courts to decide what is a reasonable and fair construction of the contractas written, and determine the rights of the parties accordingly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pulver v. Dougherty
58 A.D.3d 978 (Appellate Division of the Supreme Court of New York, 2009)
Edgewater Construction Co. v. 81 & 3 of Watertown, Inc.
252 A.D.2d 951 (Appellate Division of the Supreme Court of New York, 1998)
Condon-Cunningham, Inc. v. Day
258 N.E.2d 264 (Cuyahoga County Common Pleas Court, 1969)
Lathrop Co. v. City of Toledo
214 N.E.2d 408 (Ohio Supreme Court, 1966)
Buffalo Electric Co. v. State
27 Misc. 2d 527 (New York State Court of Claims, 1961)
Merchants Mutual Casualty Co. v. Wildman
12 A.D.2d 664 (Appellate Division of the Supreme Court of New York, 1960)
D. W. Winkelman Co. v. State
17 Misc. 2d 418 (New York State Court of Claims, 1959)
Byson v. City of Los Angeles
308 P.2d 765 (California Court of Appeal, 1957)
Nicholas Di Menna & Sons, Inc. v. City of New York
92 N.E.2d 918 (New York Court of Appeals, 1950)
Novak & Rehner, Inc. v. State
192 Misc. 66 (New York State Court of Claims, 1948)
Shore Bridge Corp. v. State
186 Misc. 1005 (New York State Court of Claims, 1946)
A. W. Banko, Inc. v. State
186 Misc. 491 (New York State Court of Claims, 1946)
Haley v. Brady
137 P.2d 505 (Washington Supreme Court, 1943)
Nugent v. State
265 A.D. 549 (Appellate Division of the Supreme Court of New York, 1943)
Bay City v. Frazier
77 F.2d 570 (Sixth Circuit, 1935)
Cantu v. Fenner, Beane Ungerleider
160 So. 399 (Supreme Court of Louisiana, 1935)
City of Wheeling v. John F. Casey Co.
74 F.2d 794 (Fourth Circuit, 1935)
Ajax Drainage Contracting Corp. v. City of New York
125 Misc. 794 (New York Supreme Court, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
63 N.E. 804, 171 N.Y. 61, 9 Bedell 61, 1902 N.Y. LEXIS 833, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gearty-v-mayor-etc-of-new-york-ny-1902.