City of Wheeling v. John F. Casey Co.

74 F.2d 794, 1935 U.S. App. LEXIS 3541
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 8, 1935
DocketNo. 3695
StatusPublished
Cited by9 cases

This text of 74 F.2d 794 (City of Wheeling v. John F. Casey Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Wheeling v. John F. Casey Co., 74 F.2d 794, 1935 U.S. App. LEXIS 3541 (4th Cir. 1935).

Opinion

NORTHCOTT, Circuit Judge.

An action of trespass on the case in assumpsit, for damages in the sum of $160,-000, was instituted in the District Court of the United States for the Northern District of West Virginia by John F. Casey Company, a Pennsylvania corporation, appellee herein, and hereinafter referred to as Casey Company, against the city of Wheeling, ,a municipal corporation of West Virginia, appellant herein, and hereinafter referred to as the city.

The action was based on a contract entered into between Casey Company and the city on April 16, 1923, for the construction of a purification and filtration plant in the city of Wheeling. Prior to the execution of the contract, which is the subject of this action, the said city had entered into a contract with the J. N. Chester Engineers, hereinafter referred to as engineers, a copartnership, an engineering firm of Pittsburgh, Pa., for the designing of the work, for the production of plans and specifications for the same, and for the complete engineering work thereon, including the location of the plant and the supervision of the construction of said project; said engineers to have entire charge of it.

One Stow, an employee, agent, and the designated resident engineer of the engineers, in laying out the base of the main line of the whole project, mistakenly located said line 21.9 feet to the west of where the same should have been located if laid out in exact accordance with the plans and specifications; the result of this mistake was to shift the entire project as a unit 21.9 feet to the west, every item or unit of said project, however, running in the same relative position to each other unit or item of said project as though constructed exactly on the location called for by said plans and specifications. The mistake of Stow was not discovered by him until some two months after it had been made, at which 'time the work had been started. The Casey Company did not discover the mistake until some thirteen months afterwards, when the work of the entire project was 98 per cent, completed. The engineers never advised the Casey Company that the mistake had been made, though there was evidence to the effect that it was highly probable that the city manager of the city was notified of the mistake by one of the partners of the engineers in the latter part of the year 1923 or the first part of 1924. The city did not notify the Casey Company of the mistake.

After the intake line, which is a pipe laid along the bed of the river, had been laid, the engineers directed that it be subjected to a certain test called the suction or emptying test. The Casey Company protested against employing such a test, but, upon demand of the engineers, made it and, as a result, the pipe line floated and came to the surface. For the cost of repairing this intake line and for the additional cost incurred by Casey Company in constructing the project on the mistaken location instead of on the location as shown on the original plans and specifications, the Casey Company claimed damages in the amount of $160,000, and on April 3, 1929, filed, in this action, its declaration, containing three counts.

The city demurred to the declaration, which demurrer was overruled. The city also objected to the sufficiency of the bill of particulars filed with the declaration, which obj ection was sustained. An amended bill of particulars was filed, the sufficiency of which was again objected to by the city, and which objection the court overruled. Two special pleas were also filed by the city, which were objected to by Casey Company, and the objections were sustained.

After a long trial the jury returned a verdict in favor of the plaintiff in the sum of $75,000, upon which verdict judgment was entered. From this action of the court below this appeal was brought.

The first question to be considered is whether the relationship between the engineers and the city was that of employer and employee, or whether the engineers were independent contractors for whose mistake or wrong the city had no responsibility. A study of the contracts between the engineers and the city and the Casey Company and the city and the surrounding circumstances established by the evidence leads us to the conclusion that the relationship of the engineers was not that of an independent contractor, but that the engineers [796]*796were the agents of the city, placed by the action of the city in a position of authority over the entire project and all of the details connected with its construction, including location, with the option on the part of the engineers to make any changes they might think necessary. This - being true, it follows that the city is primarily liable for the acts of its agents, the engineers.

The contract between the engineers and the city supports the idea of agency rather than that of independent contracting. Under this contract the preliminary work done by the engineers was subject to approval by the city. Paragraph 10 of the specifications made a part of the contract between the plaintiff and the city is as follows:

“Definition of Engineer.
“(10) Where the word ‘Engineer’ occurs in these specifications or contract, it shall be understood to indicate the Engineers of the City of Wheeling, W. Va., or to said Engineers’ duly appointed assistants, and all explanations or directions necessary for the proper execution -and construction of the work shall be given by the Engineers, who shall have final decision on all matters of dispute involving the character or amount of work, and the compensation to be made therefor, or any question arising under these specifications. They shall have the option of making changes in location, grades, alignment, forms, plans, position, dimensions or materials of the work contemplated to be done under these specifications either before or after construction is begun. Such changes will be adjusted on a basis of the additional or decreased cost of the work affected.”

Granting that the city was not at fault either as to the mistake or its concealment after the mistake was discovered, it is a well-recognized principle that where one of two innocent persons must suffer from the conduct of a third the loss must fall upon the one who has enabled such third, person to occasion it. Atlantic Life Insurance Co. v. Rowland (C. C. A.) 22 F.(2d) 126, and cases there cited.

Here the city selected and placed in charge of the project the engineers who made the mistake and afterwards concealed it and made it possible for the loss to occur.

The engineers, after the approval of the plans and specifications drawn by them, directed the setting of the stakes, and it was then that the mistake that 'gave' rise to this litigation occurred. That the mistake was not intentional seems clear, and it is contended on behalf of the city that the plaintiff, having contracted to construct the project according to the plans and specifications, should have discovered the mistake before beginning the work. On this point we agree with the judge below that the question as to whether the plaintiff in the exercise of reasonable care should have known of the mistake was one for the jury, which question the jury resolved in favor of the plaintiff. We think the jury reached the correct solution. The engineers had drawn the plans, the contracts gave them the right to locate the plant, and the work of location was primarily the duty of an engineer placed in complete authority over the entire project and over the contractor rather than the duty of the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Groves v. Compton
280 S.E.2d 708 (West Virginia Supreme Court, 1981)
Clark v. City of Humansville, Missouri
348 S.W.2d 369 (Missouri Court of Appeals, 1961)
Furton v. City of Menasha
71 F. Supp. 568 (E.D. Wisconsin, 1947)
City of Wheeling v. Chester
134 F.2d 759 (Third Circuit, 1943)
James v. Nelson
90 F.2d 910 (Ninth Circuit, 1937)
City of Wheeling v. John F. Casey Co.
85 F.2d 922 (Fourth Circuit, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
74 F.2d 794, 1935 U.S. App. LEXIS 3541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-wheeling-v-john-f-casey-co-ca4-1935.