Parkersburg & Marietta Sand Co. v. Smith

85 S.E. 516, 76 W. Va. 246, 1915 W. Va. LEXIS 110
CourtWest Virginia Supreme Court
DecidedMay 18, 1915
StatusPublished
Cited by17 cases

This text of 85 S.E. 516 (Parkersburg & Marietta Sand Co. v. Smith) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parkersburg & Marietta Sand Co. v. Smith, 85 S.E. 516, 76 W. Va. 246, 1915 W. Va. LEXIS 110 (W. Va. 1915).

Opinion

Miller, Judge:

On two special counts and the common counts in assumpsit, and on issues joined on the general and sundry special pleas, with special replications to some of said special pleas, plaintiff obtained the verdict and judgment for $8,280.49, complained of.

On writ of error defendant opposes to this judgment numerous assignments of error charged to have been committed on the trial below.

The first of these is that the trial court erroneously overruled his demurrer to the declaration and each count thereof. No point is made against the common counts. The first count pleads a first and a second or supplementary contract between plaintiff and defendant in haee verba, and performance thereof by plaintiff, and alleges that plaintiff was entitled to recover thereon from defendant the sum of $13,197.53, ?s shown by an itemized statement filed therewith, and designated “Amount due under written contracts.” This count then pleads performance of certain other work, namely, the making of certain excavations, fillings, and embankments around and in a certain coffer-dam, and sinking certain piling, and raising and repairing a certain boat, in connection with the work done and performed by the plaintiff under said written contracts; and that at the special instance and request of defendant and for the consideration then and [249]*249there agreed to be paid by defendant to plaintiff, plaintiff also performed certain labor for defendant and furnished certain material, including piling and equipment, amounting to $791.69, according to an itemized account thereof also filed with the declaration and designated “Account for work done not under writings.”

“By reason whereof”, it is alleged, defendant “became indebted and liable to the said plaintiff in the said sum of Fifteen Thousand Dollars * * * with interest from the first day of August, 1910, until paid, and being so liable, the said defendant * * * in consideration thereof, afterwards, to-wit, on the--day of-, 1912, undertook and promised to pay * '* * plaintiff, the sum of $15,000.00, with interest as aforesaid, whenever the said defendant should be thereunto afterwards requested.” And the allegation follows that not regarding his said promises and undertakings defendant, though often requested, had not as yet paid plaintiff said sum with interest as aforesaid, or any part thereof, but had wholly neglected to do so to the damage of plaintiff, $15,000.00.

The second count pleads that on the-day of August, 1912, after defendant had executed and delivered the contracts in writing aforesaid, and after plaintiff had done and performed all the labor and furnished all the material mentioned and set forth in the first count, at the special instance and request of defendant, defendant accounted with plaintiff^ “of and concerning divers sums of money for said labor performed, and said material and equipment furnished, before that time and owing to plaintiff, and then in arrear and unpaid”, and that upon such accounting “defendant * * * * w-as found in arrear, and indebted to * * * * plaintiff in the further sum of * # * * * $15,000.00”, and that being so indebted, and in consideration thereof, defendant “undertook and then faithfully promised” to pay plaintiff the said sum of money, when he should be thereunto after-wards requested, and as represented in the account thereof filed therewith, and that being so liable defendant in consideration thereof, on the-day of-, 1912, undertook, etc., in the same manner as alleged in the first count.

• The first point made against the first count is that it con[250]*250tains no allegation of a promise to pay “the sum of-dollars” alleged in a previous paragraph thereof to have been due and owing plaintiff under the first' or original contract. We think there is no merit in this point. Immediately following this averment it is alleged that owing to disputes- and controversies between the parties as to plaintiff’s rights under said first contract, the second or supplementary contract pleaded was entered into, and then follows the allegation above recited in relation to the liability and promises of defendant under both contracts, and as to the amount accrued to plaintiff thereunder and the promises of defendant alleged, etc. We think these averments sufficient to satisfy all requirements of good pleading.

The point is also made against those averments that there are no distinct allegations of a promise to pay the sum of $13,197.53, accrued under the contracts in writing, and the sum of $791.69, accrued under the contracts not in writing, but only of the sum of $15,000.00, and which said two sums do not aggregate the sum of $15,000.00, alleged to have accrued and been demanded. We see no substantive merit in this point.

It is unnecessary to aver a promise to pay each individual sum demanded. The averment of the promise to pay the aggregate, of all the sums demanded is certainly sufficient, and though in this case there is no promise to pay the exact aggregate of the 'two sums demanded, it is plainly to be seen that the intention was to cover the aggregate of these sums by the promise to pay the sum of $15,000.00. We know of no authority, -and none is cited, for the proposition that the averment of the amount promised must exactly equal the aggregate of the different items demanded. No such strict rule is known to us when applied to an action of assumpsit.

Another point is that the averment of the promise to pay interest from the first day of August, 1910, a date anterior to the making of the second or supplementary agreement, and a date anterior to the date of the work done under the' contract and covered by the bill of particulars filed, is an impossible date, rendering the first two counts bad. We see no merit in this proposition. The averment of time from which interest is to run is an immaterial averment, and i [251]*251Minor, Inst., Part II, 1175, cited, is inapplicable. Unless there is an express contract to pay interest it does not form the basis of the action, but becomes an .incident only to the recovery of the principal debt. Bennett v. Federal Coal & Coke Co., 70 W. Va. 456. Here there was no express contract to pay interest, and interest therefore was a mere incident to the recovery of the principal sum sued for, and the damage laid in the declaration constituted a sufficient cloak to cover that interest.

Some other points of demurrer are noted, but they are practically conceded to be without merit, as duplicity, etc., and will not be further regarded on this hearing. The same points are covered by other points of error, and they will have consideration in disposing' of them.

The second point of error is the rejection of defendant’s special plea number one. This plea is based upon the theory of the entirety of the contract pleaded, and proposes to recoup in damages certain losses of interest, and damages sustained by defendant by being obliged to’pay plaintiff over and over again for doing the same work contracted to be done by it, and damages sustained by defendant from delay by plaintiff in the execution of its contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strahin v. Cleavenger
603 S.E.2d 197 (West Virginia Supreme Court, 2004)
Horton v. Horton
264 S.E.2d 160 (West Virginia Supreme Court, 1980)
Wetherall v. State Road Commission
8 Ct. Cl. 1 (West Virginia Court of Claims, 1969)
Nesbitt v. Flaccus
138 S.E.2d 859 (West Virginia Supreme Court, 1964)
Swope v. Pageton Pocahontas Coal Co.
41 S.E.2d 691 (West Virginia Supreme Court, 1947)
Inter-Ocean Casualty Co. v. Leccony Smokeless Fuel Co.
17 S.E.2d 51 (West Virginia Supreme Court, 1941)
Keatley v. Hanna Chevrolet Co.
6 S.E.2d 1 (West Virginia Supreme Court, 1939)
City of Wheeling v. John F. Casey Co.
74 F.2d 794 (Fourth Circuit, 1935)
Summit Coal Co. v. Raleigh Smokeless Fuel Co.
128 S.E. 298 (West Virginia Supreme Court, 1925)
Freeman v. Monongahela Valley Traction Co.
128 S.E. 129 (West Virginia Supreme Court, 1924)
First National Bank v. Bailey
125 S.E. 357 (West Virginia Supreme Court, 1924)
Hamrick v. Nutter
116 S.E. 75 (West Virginia Supreme Court, 1923)
Sues v. Smith
114 S.E. 375 (West Virginia Supreme Court, 1922)
Ewing v. Chapman
114 S.E. 158 (West Virginia Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
85 S.E. 516, 76 W. Va. 246, 1915 W. Va. LEXIS 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parkersburg-marietta-sand-co-v-smith-wva-1915.