Sues v. Smith

114 S.E. 375, 92 W. Va. 12, 1922 W. Va. LEXIS 3
CourtWest Virginia Supreme Court
DecidedOctober 17, 1922
StatusPublished
Cited by3 cases

This text of 114 S.E. 375 (Sues v. Smith) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sues v. Smith, 114 S.E. 375, 92 W. Va. 12, 1922 W. Va. LEXIS 3 (W. Va. 1922).

Opinion

Lively, Judge:

Prom a judgment in favor of plaintiff for $4,133.04, entered December 8, 1921, both plaintiff and defendants prosecute error.

The litigation arises over a road building contract between the county court and defendant, Harry P. Smith, dated September 26, 1916, bond for the faithful performance of which was given by Smith with American Surety Company, as surety, on October 26, 1916, in the penalty of $20,000.00. The declaration, demurrer to which was properly overruled, is on the bond, alleging breaches of the contract. It is averred that after Smith had undertaken the work and constructed a portion of the road in Piedmont district of Mineral County, known as the Ashfield Street and Keyser Road, being from Station 25 to Station 95 at the New Creek District line, he failed and refused to complete the same, and plaintiff was compelled to take over the contract and [14]*14complete the road, by laying 1,100 feet of concrete paving and other work at an additional cost and expenditure of $6,997.83 over what it would have cost if the contractor had completed the work under the terms of the contract. The work which should have been done by, Smith, at the prices under the contract, would have cost $7,265.55, whereas, the same work done by the county court actually cost $17,188.17, leaving an excess of $9,922.62, on which a credit of $2,924.79 was allowed, being the gross amount retained by the county court under the contract on the work performed by Smith, $4,004.79, less machinery and equipment furnished him amounting to $1,140.00. The prices of material and labor advanced after Smith began the work; and being unable to complete the contract at the prices stipulated therein, he abandoned the job and breached his contract, according to the theory of the county court.

The defendants plead the general issue; and tendered, and filed over plaintiff’s objection, three special pleas, to the effect that before liability had accrued on the bond the plaintiff, by its engineer, ordered and enforced a suspension of further work east of Station 85, as shown on a blue print of the road, for more than 150 working days, and therefore, under paragraph 30 of the contract, they were each relieved and released from further performance, and liability. The surety company also-plead that Smith and the county . court had made a new agreement, without its consent, by which the work was to be done and was done by the county court at greatly increased cost not contemplated by the original contract, and hence it was not.bound thereby. It was the theory of defendants that Smith had performed a part of the work, that west of station 85, in accordance with the contract which had been accepted, and had been relieved of further performance by suspension of the remainder of the work, (east of station 85) for more than 150 working days under the provisions of paragraph 30 of the contract. These pleas should have been rejected.

Paragraph 30 of the contract, under which defendants claim right-to file these please is as follows: “(30) Eight to [15]*15Suspend Work. Tbe right is also reserved by tbe Engineer and County Court to suspend work on any section or sections of tbe road covered by this contract for weather conditions or other valid reason. Such suspension shall not in any way invalidate the contract or relieve the Contractor from the fulfillment of any of its conditions and requirements, provided that the sum total of the time lost by such suspension of work shall not exceed one hundred and fifty (150) working days. The order for such suspension of work shall be given only by the Engineer, in writing, and the total number of working days during which the work is thus suspended shall be added to the specified time within which the Contractor shall complete his work.” We do not interpret this to mean the same thing as the defendants do. We do not think that a suspension of any part of the work, where there is but one section of road covered by the contract, unless such suspension covered the entire work so as to cause the contractor to lose 150 working days thereon, would invalidate the contract or relieve the contractor from its fulfillment. There is but one section of road covered by this contract, and the suspension claimed under the pleas relates to only a portion of that section. It follows that the evidence introduced in support of these pleas, over the objections of plaintiff, and instructions Nos. 1, 2 and 3 for the defendants should have been rejected.

Smith filed a statement of set-off over the objection of plaintiff, and this, as well as introduction of evidence to prove the items, is claimed as error on the theory that the items therein set out for extra labor and material, amount of money retained by the court being 10% of cost of work done by defendant, and time devoted by defendant’s employees in helping plaintiff’s engineer in making estimates, and not paid for nor included in the estimates of work done, in all totaling $7,056.90, could not be made the subject of litigation against the county court until they had been presented to that body for settlement as required by sections 40 and 41 of chapter 39, Code, citing Chapman v. County Court, 27 W. Va. 496; Yates v. County Court, 47 W. Va. 376; Beury C. & C. Co. [16]*16v. County Court, 76 W. Va. 610; Barbour v. County Court, 85 W. Va. 359; and Williams v. County Court, 90 W. Va. 67.

The procedure required by the statute is a condition precedent to the claimant’s right to sue the county court for money founded on a contract, except an order for payment out of the county treasury, and must be followed or his suit will abate. The reason for such procedure is plainly apparent. It was designed to protect the county court against useless costs and litigation. The fiscal affairs of the county coming under the jurisdiction of the county court are numerous, and its obligations in the conduct of the public business are necessarily complex and varied, and to permit the owners of claims founded on contract to sue as and when their whims or spite might dictate before presentation for audit and"payment in an orderly way, would subject the court to vexatious suits and unnecessary ■ costs.

■ Our cases above cited construing the statute, simply affirming what the statute plainly says, are cases where claimants have sued without following the prescribed procedure. In the Chapman case, the court decided that the allegations of the declaration were sufficient to show that there had been a substantial compliance with the .statute, and the plaintiff was allowed to recover. In the Williams ease the plaintiff had sued the county court upon his claim for work and material furnished by contract, which he had presented toN the defendant, the county court, and which had been disallowed; but he also sued for certain damages caused by a breach of the contract in not furnishing to him grade lines, stakes .and locations, and failure of the engineer to promptly make up estimates for work done. He had never presented his claim for damages for these alleged breaches, and the court was in ignorance of this claim until suit was instituted. He was not permitted to recover on this item of damage because of the statute. In the case under consideration we' have a different situation. The county court has begun the litigation; the items of set-off all arise out of the subject of the litigation — the contract; they are in the nature of re-coupment to, or credits against, the claim of the plaintiff. [17]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
114 S.E. 375, 92 W. Va. 12, 1922 W. Va. LEXIS 3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sues-v-smith-wva-1922.