Opinion

Lively, Judge:

From a judgment against him of nil capiat rendered by the circuit court of Lincoln County on the 14th day of December, 1920, plaintiff prosecutes error.

The summons was in assumpsit, and the declaration avers that defendant entered into a written contract with plaintiffs by which the latter were to build and construct the grade for a certain county road between East Hamlin and West Hamlin for which defendant promised to pay certain stipulated prices for various items of the work, and for certain material used by plaintiffs therein such as concrete culverts, pipes, drain tile, and the like; and that defendant agreed to furnish grade line stakes and guides by which to carry on the work, and cause estimates of the work to be made each month by an engineer, on which payments were to be made on or before the 20th day of each month; but that defendant failed to carry ont its contract in that it failed to furnish grade lines, stakes and locations, refused to make up said estimates and refused to make payments as agreed, by reason of which failures plaintiffs were damaged $10,000.00; and that plaintiff had performed work under contract amounting to $34,-856.10 but that defendant had failed to pay for same except such credits as were shown by an account filed with the [69]*69declaration, to the damage of plaintiff $10,000.00. There was no demurrer interposed. The general issue of non-assumpsit was made up, and defendant filed notice of re-coupment. Williams, one of the plaintiffs, testified to the correctness of his account filed as a bill of particulars and which amounted to $34,412.76, including an item of $500.25 for dynamite and powder used and paid for by him which last item he claimed should have been furnished by defendant at its own expense under the terms of the contract. To this sum of $34,412.76 he added the further sum of $1,392.00 which he claimed as damages for delays occasioned by failure of defendant to furnish line stakes as required and by changing the grade. The credits he admitted amounted to $29,-530.76, leaving due him the sum of $6,274.00. Defendant proved by S. E. Bradley, J. E. Doyle, both engineers, and others that the work done by plaintiffs, including force account, amounted to $30,183.79 and that defendant had paid thereon $30,157.88; and that it had furnished plaintiffs supplies consisting of dynamite, powder, caps, fuse and the like, amounting to $1,632.18, and that plaintiffs had been over paid by defendant the sum of $1,606.27. An effort was made to show under the notice of recoupment that it had or would cost defendant something like $20,000.00 to complete the contract after plaintiff has given it up, more than it would have cost if plaintiff had completed it under its terms. This evidence was given by Engineer Bradley. It is not clear from the record whether or not this evidence was excluded. A motion to exclude all of this witness’ evidence as to custom of interpretation of -the word “material” as used in road contracts, “and so forth” made at the conclusion of his evidence was sustained. Whether the “and so forth” included his evidence on the recoupment is uncertain; but the county court is'not complaining. No evidence was offered by plaintiff to contradict the evidence of Bradley on the matter of recoupment.

An instruction was offered by defendant to the effect that if the jury believed that plaintiffs failed to complete the work provided for in the contract, and that defendant on account thereof was compelled to readvertise and relet the [70]*70same; and that it cost more money by reason of plaintiffs’ failure to comply with the contract, then defendant had the right of offset to the amount of the difference between the contract price, and what it actually cost under the reletting, unless the jury further believed that plaintiffs’ failure was caused by the action of the county court. This instruction was refused, whether because it was inaptly drawn, or because of the evidence on which it was predicated, does not appear.

One of the grounds assigned as error is that the court “allowed the recoupment to go to the jury without evidence to support it.” We do not perceive the relevancy of the objection. If the evidence was excluded, plaintiff was benefited and cannot complain. Certainly defendant had the right to file notice of recoupment and attempt to introduce evidence to sustain it. There was evidence tending to show that up to September 5, 1918, there was no serious friction in the performance of the contract. About that time a difficulty arose between Bartrug, the engineer who was connected with the road making and employed by defendant to oversee this work, and plaintiff Williams, possibly a serious altercation arose between them, degenerating into a fight, and then plaintiffs announced that they would not continue in the work under Bartrug, and wanted a final settlement and release from the contract. Then it was that Bradley and Doyle, both competent engineers, were called in to make the final measurements, both parties agreeing to abide by their measurements. Possibly the court refused the instruction on the recoupment evidence for this reason. The evidence tended to show that plaintiffs desired to cease the work, with consent of defendant.

Plaintiffs’ evidence relative to their damages was excluded because this claim had not been presented to the county court, or filed with the clerk prior to the institution of the suit as provided in chap. 39, secs. 40 and 41, Code, 1918. Under this statute every person having a claim' or demand against a county ‘ ‘ shall file with the clerk of the county court thereof an account or statement of the same, fully setting forth the items”; and “no suits shall be brought against a county [71]*71court for any demand for a specified sum of money founded on contract * * * * until sucli demand has been presented to such court and disallowed by them in whole or in part” etc. There is no pretence that this claim for damages had been presented to the county court before suit was instituted. It will he observed from inspection of the declaration that there are two distinct claims sued on; (1) the amount of money claimed for work and material furnished under contract, and (2) damages caused by a breach of the contract in not furnishing grade lines, stakes and locations, and failure to make up estimates of work done and pay money promptly under the estimates. We think the court properly refused to permit evidence as to the damages claimed, under the statute above partially quoted and under Chapman v. County Court, 27 W. Va. 496; Yates v. County Court, 47 W. Va. 376; and Barbour v. County Court, 85 W. Va. 359.

Two instructions for plaintiffs were refused and error is predicated thereon. The first instruction is to the effect that if defendant “broke its contract in the first instance,” that then plaintiff had the right to treat the contract as broken and be discharged from further performing it, and if they find he did so treat it he had the right to sue for all work done under the contract which then became due by law” and the jury should find for the plaintiff in such sum as they may find defendant owes him, if any, for labor and material, less what had been paid on account thereof. This instruction is misleading. It tells the jury that plaintiff could take advantage of any non-performance of the contract, consider and treat it as broken, be discharged therefrom if he so desired to quit, and then sue for all the work and material which then became due.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Collins
180 S.E.2d 54 (West Virginia Supreme Court, 1971)
Hollen v. Linger
151 S.E.2d 330 (West Virginia Supreme Court, 1966)
State v. Vance
124 S.E.2d 252 (West Virginia Supreme Court, 1962)
Blain v. Woods
115 S.E.2d 88 (West Virginia Supreme Court, 1960)
State Ex Rel. Shatzer v. Freeport Coal Co.
107 S.E.2d 503 (West Virginia Supreme Court, 1959)
State v. Morris
95 S.E.2d 401 (West Virginia Supreme Court, 1956)
State v. Michael
87 S.E.2d 595 (West Virginia Supreme Court, 1955)
Wilson v. Edwards
77 S.E.2d 164 (West Virginia Supreme Court, 1953)
Thrasher v. Amere Gas Utilities Co.
75 S.E.2d 376 (West Virginia Supreme Court, 1953)
Chesapeake & Ohio Railway Co. v. Johnson
69 S.E.2d 393 (West Virginia Supreme Court, 1952)
Davis v. Pugh
57 S.E.2d 9 (West Virginia Supreme Court, 1949)
Sues v. Smith
114 S.E. 375 (West Virginia Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
110 S.E. 486, 90 W. Va. 67, 1922 W. Va. LEXIS 194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-v-county-court-of-lincoln-county-wva-1922.