Hamilton v. Republic Casualty Co.

135 S.E. 259, 102 W. Va. 32, 1926 W. Va. LEXIS 5
CourtWest Virginia Supreme Court
DecidedJune 1, 1926
Docket5447
StatusPublished
Cited by12 cases

This text of 135 S.E. 259 (Hamilton v. Republic Casualty Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hamilton v. Republic Casualty Co., 135 S.E. 259, 102 W. Va. 32, 1926 W. Va. LEXIS 5 (W. Va. 1926).

Opinion

Hatcher, Judge:

This is an action of debt, instituted in the Circuit Court of Fayette County by E. S. Hamilton, against the Shawver Construction Company, principal, and the Republic Casualty Company, surety, to recover for alleged breaches of a building contract. The plaintiff secured a judgment for $3234.38 against the Casualty Company, which prosecutes error here.

On June 11,1923, the Construction Company, as first party, and the plaintiff, as second party, entered into a building contract, wherein the Construction Company agreed to furnish all materials and labor, construct and complete at Oak Hill in said county, within 135 days (Sundays excluded) from June 15, a' dwelling house, in accordance with certain plans and specifications made by Gr. C. Seibt, architect; and the plaintiff agreed to pay to the Construction Company the sum of $10,464.70 as follows: $2000.00 when an approved bond in the penalty of $10,000.00 conditioned upon complete compliance with the contract, was given by the Construction Company, and the residue of $8,464.70 to be “paid on monthly estimates to be prepared by the architect, based on work and labor performed and material on the ground, 90% of each estimate to be paid at the time of the making thereof, *34 and the retained percentage of 10%'to be withheld byithe party of the second part, pending final adjustment andithe completion by the party of the first part of the acts qnd things required of it to be done by these presents.” • i

On June 22 the bond referred to in the contract was executed by the Construction Company as principal and the Casualty Company as surety. • ;

The Construction Company began work under this contract immediately after giving the bond, but did not complete the building until 185 days after June 15. The delay was caused by several circumstances, the main one of which was the inability of the Construction Company to meet its labor and material bills. The Casualty finally advanced funds in order to secure the completion of the contract. i

In his action the plaintiff seeks to recover for the delay iff the completion of the building, for alleged faulty material used therein, and for certain mechanics’ liens filed against the property.

There are numerous details in the contract and evidence, and many errors charged against the trial court, which we consider unnecessary to narrate. Under our view of the case, there was one act by the plaintiff which terminated his rights against the Casualty Company. Consequently we will not attempt to develop the ease fully except as to that act.

Prior to the contract of June 11 the Construction Company, had built two dwelling houses for plaintiff. It owed large amounts to the Dickinson Lumber Company on material for these structures. The Lumber Company was threatening to file mechanics’ liens against the two houses, when the plaintiff entered into an arrangement with the Construction Company to loan it $3936.31 to pay the Lumber Company’s claims. This loan was made on August 11, 1923, on which date the Construction Company executed to the plaintiff its note for the above amount due in forty days. The note was endorsed by several responsible parties, and secured by a deed of trust on a lot in Fayetteville and certain construction equipment. When the note became due on September 20, the plaintiff had the architect make an estimate of the amount then due the Construction Company under the contract of *35 June 11, which, the architect reported to be $3736.31. The plaintiff then paid the Construction Company $800.00 in cash to enable it to pay its laborers, and credited the entire balance of the estimate, to-wit, $2936.31, on the note of the Construction Company, thereby ignoring the requirement in the contract that he retain 10 per cent of the estimate. The Casualty Company knew nothing about this transaction. The Construction Company was without funds to meet its bills at that time. This fact was known to the plaintiff. The injurious effect of diverting $2936.31 from the working capital of the Construction Company at that time is too obvious to require comment. "Within a month after Sept. 20 its plight is graphically described by plaintiff as follows: “The Construction Company became bankrupt, or insolvent; they could not hire labor; they could not buy material; they could not finish the job; nobody would work for them. The laborers all refused to do anything. The men themselves that were working, members of the construction company, became demoralized and threw up their hands, and virtually quit the job. Then is when I asked the bonding company to see the contract through. ’ ’

■The plaintiff would justify withholding the $2936.31 from the estimate, on the theory that payment of a debt does not necessarily have to be made in money, citing Smith v. Smith 92 W. Va. 12. In that case the County Court had charged against money due a contractor some road machinery with which it had supplied him. This court upheld that charge, but it was, as stated in the opinion, because the machinery enabled the contractor to perform his contract “and to that extent was a benefit to the surety.”

Monroe v. Surety Co. 47 Wash 488, and Museum of Fine Arts v. Am. Bonding Co. 211 Mass. 124, are also realized on by plaintiff. In the first case it was explicitly stated “the payments! could not have operated to the prejudice of the bonding company”. In the second case, a loan was made by the owner to the contractor, to enable him to carry on the work, the contractor agreeing that future installments to become due on the work should be security for the note. The owner did not withhold any money which afterwards *36 became due the contractor, and in fact the note had not been paid at the time the owner sued the surety. The court held that the' loan to the contractor under those circumstances “was an independent transaction and not a payment under the contract in violation of its terms and therefore that it did not relieve the sureties from-liability pro ianio.” In the second case there was no diversion of the money due the contractor, consequently that ease can have no bearing on the present one.

But, say counsel, the loan made by plaintiff to the Construction Company was really a benefit to both the principal and the surety, in that it permitted the Construction Company “to proceed with the contract without reference to hindrance of the pressing demands of its creditors.” The record does not show that demands were being pressed against the Construction Company at the date of the loan. On Aug. 11, the only threat from a creditor, disclosed by the evidence, was directed against the property of the plaintiff. We must necessarily, conclude that the purpose of the loan was to prevent the Dickinson Lumber Company from filing mechanics’ liens against the two houses of plaintiff. Prior to October 1923, it was seemingly the plaintiff, and not the other creditors of the contractor, who pressed claims against it. Counsel also say that it was to the benefit of both principal and surety that the plaintiff withheld from the estimate the $2936.61 as a credit on the note, instead of selling the contractors equipment as he had the right to. do under the deed of trust. The sale of the equipment was not plaintiff’s only means for collecting the note.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Educ. of County of Wood v. Airhart
569 S.E.2d 422 (West Virginia Supreme Court, 2002)
Potesta v. United States Fidelity & Guaranty Co.
504 S.E.2d 135 (West Virginia Supreme Court, 1998)
Hoffman v. Wheeling Savings & Loan Ass'n
57 S.E.2d 725 (West Virginia Supreme Court, 1950)
Koblegard Co. v. Maxwell
34 S.E.2d 116 (West Virginia Supreme Court, 1945)
Crane Co. v. James McHugh Sons, Inc.
108 F.2d 55 (Tenth Circuit, 1939)
Potts v. Mathieson Alkali Works
181 S.E. 521 (Supreme Court of Virginia, 1935)
Appalachian Marble Co. v. Boone
171 S.E. 751 (West Virginia Supreme Court, 1933)
State Ex Rel. Persinger Supply Co. v. Webb
166 S.E. 281 (West Virginia Supreme Court, 1932)
Capon Valley Bank v. State Road Commission
163 S.E. 44 (West Virginia Supreme Court, 1932)
Crouse v. . Stanley
154 S.E. 40 (Supreme Court of North Carolina, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
135 S.E. 259, 102 W. Va. 32, 1926 W. Va. LEXIS 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hamilton-v-republic-casualty-co-wva-1926.