Appalachian Marble Co. v. Boone

171 S.E. 751, 114 W. Va. 307, 1933 W. Va. LEXIS 71
West Virginia Supreme Court·Decided November 14, 1933·No. 7626·Published

Opinion

Hatcher, Judge :

This is a suit by a furnisher of material to recover on a contractor’s bond for the default of a subcontractor. The plaintiff appealed from a judgment in its favor on the ground that the recovery was not adequate.

Defendants Boone, Eason & Wood (hereinafter called the contractors) constructed the Mercer County courthouse in 1930-1. Defendant Fidelity & Deposit Company was surety on their bond. They sublet the marble, tile and terrazzo work and the slate window stools to R. N. Vanderberry for $15,000, without any bond from him to secure them, and with the following provision in the contract as to payments: "The monthly payments on contracts in course of execution shall be made within fifteen days after the submission of estimates for payment and shall be based on 90% of the value of the work set in place up to the date of the submission of the same, plus 85% of the set value of all material delivered at the *308 building, whether installed or not. Final payment in full shall be made within thirty days from the completion and acceptance of the * * * work. ’ ’

Yanderberry purchased from the plaintiff the marble required at a total cost of $5,624.64. None of this amount was paid and the subcontractor has been adjudicated a bankrupt. There were two main shipments of marble, one on April 23, 1931, amounting to $2,500.00 and the other on May 7, 1931, amounting to $2,870.00. Small shipments for replacements were made in June and July of 1931, amounting to $254.64. There is no dispute as to any of these items.

On May 1, 1931, the contractors were allowed an estimate of $13,000.00 exclusively on the work of Yanderberry and were paid 85% of that estimate by the county. On that day they paid Yanderberry $3,000.00. On May 7th they mailed the plaintiff a letter which is in part as follows: “We will be pleased to have you advise us the amount of your account and how you wish us to handle this in order that we may know that you are paid for this material.” On that same day the plaintiff wired the architect in charge of the construction,. ‘ ‘ Satisfactory with us to pay 'Yanderberry on estimates when due.” The architect forthwith delivered the telegram to the contractors. Following which they made further payments-to Yanderberry of $2,000.00 on May 8th, $2,500,000 on May 11th, and $1,000.00 on May 22nd. On May 24th they received from plaintiff a letter written on May 22nd, which charged its delay in answering the contractors’ letter of May 7th to-the dalliance of Yanderberry, notified the contractors of the-shipments of April 23rd and May 7th, and requested them to protect its interest. The contractors also received from the architect on May 24th a copy of a letter to him from plaintiff directing him to disregard the telegram of May 7th. No further’ payments were made to Yanderberry after May 24th. On June 1st the architect made the contractors a further estimate-of $4,000.00 on Yanderberry’s work. He abandoned his contract the early part of June, and it was then completed by the contractors.

The contractors did not answer plaintiff until June 18th,. when they wrote that Yanderberry’s balance with them as-of that date was approximately $5,500.00, subject to be re *309 duced by “the payroll” and by some cement they had furnished him, and that they would hold the balance, etc. Some other letters were exchanged during the summer months of 1931, in which the plaintiff kept demanding that the balance due the subcontractor be paid to it, and the contractors kept postponing such payment, at first because plaintiff had not secured an order from Yanderberry for the balance, and later because the building was not yet completed. On September 15, 1931, the contractors notified plaintiff that the balance due Yanderberry then was $2,314.41, which they offered to pay to plaintiff, if it would guarantee them against any action of any of his creditors against them, and would also assign to them its claim against them and their surety arising out of the subcontractor ’s default. The tender was not accepted and plaintiff sued for its entire claim of $5,624.64. The circuit court found in its favor for the above balance of $2,314.41.

Free access — add to your briefcase to read the full text and ask questions with AI

Appalachian Marble Co. v. Boone, 171 S.E. 751, 114 W. Va. 307, 1933 W. Va. LEXIS 71 (W. Va. 1933).

171 S.E. 751 (Appalachian Marble Co. v. Boone) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hibner v. Ebersbach
157 S.E. 178 (West Virginia Supreme Court, 1931)
Hamilton v. Republic Casualty Co.
135 S.E. 259 (West Virginia Supreme Court, 1926)
Rhodes v. Riley
169 S.E. 525 (West Virginia Supreme Court, 1933)