Appalachian Marble Co. v. Boone

171 S.E. 751, 114 W. Va. 307, 1933 W. Va. LEXIS 71
CourtWest Virginia Supreme Court
DecidedNovember 14, 1933
Docket7626
StatusPublished

This text of 171 S.E. 751 (Appalachian Marble Co. v. Boone) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appalachian Marble Co. v. Boone, 171 S.E. 751, 114 W. Va. 307, 1933 W. Va. LEXIS 71 (W. Va. 1933).

Opinion

Hatcher, Judge :

This is a suit by a furnisher of material to recover on a contractor’s bond for the default of a subcontractor. The plaintiff appealed from a judgment in its favor on the ground that the recovery was not adequate.

Defendants Boone, Eason & Wood (hereinafter called the contractors) constructed the Mercer County courthouse in 1930-1. Defendant Fidelity & Deposit Company was surety on their bond. They sublet the marble, tile and terrazzo work and the slate window stools to R. N. Vanderberry for $15,000, without any bond from him to secure them, and with the following provision in the contract as to payments: "The monthly payments on contracts in course of execution shall be made within fifteen days after the submission of estimates for payment and shall be based on 90% of the value of the work set in place up to the date of the submission of the same, plus 85% of the set value of all material delivered at the *308 building, whether installed or not. Final payment in full shall be made within thirty days from the completion and acceptance of the * * * work. ’ ’

Yanderberry purchased from the plaintiff the marble required at a total cost of $5,624.64. None of this amount was paid and the subcontractor has been adjudicated a bankrupt. There were two main shipments of marble, one on April 23, 1931, amounting to $2,500.00 and the other on May 7, 1931, amounting to $2,870.00. Small shipments for replacements were made in June and July of 1931, amounting to $254.64. There is no dispute as to any of these items.

On May 1, 1931, the contractors were allowed an estimate of $13,000.00 exclusively on the work of Yanderberry and were paid 85% of that estimate by the county. On that day they paid Yanderberry $3,000.00. On May 7th they mailed the plaintiff a letter which is in part as follows: “We will be pleased to have you advise us the amount of your account and how you wish us to handle this in order that we may know that you are paid for this material.” On that same day the plaintiff wired the architect in charge of the construction,. ‘ ‘ Satisfactory with us to pay 'Yanderberry on estimates when due.” The architect forthwith delivered the telegram to the contractors. Following which they made further payments-to Yanderberry of $2,000.00 on May 8th, $2,500,000 on May 11th, and $1,000.00 on May 22nd. On May 24th they received from plaintiff a letter written on May 22nd, which charged its delay in answering the contractors’ letter of May 7th to-the dalliance of Yanderberry, notified the contractors of the-shipments of April 23rd and May 7th, and requested them to protect its interest. The contractors also received from the architect on May 24th a copy of a letter to him from plaintiff directing him to disregard the telegram of May 7th. No further’ payments were made to Yanderberry after May 24th. On June 1st the architect made the contractors a further estimate-of $4,000.00 on Yanderberry’s work. He abandoned his contract the early part of June, and it was then completed by the contractors.

The contractors did not answer plaintiff until June 18th,. when they wrote that Yanderberry’s balance with them as-of that date was approximately $5,500.00, subject to be re *309 duced by “the payroll” and by some cement they had furnished him, and that they would hold the balance, etc. Some other letters were exchanged during the summer months of 1931, in which the plaintiff kept demanding that the balance due the subcontractor be paid to it, and the contractors kept postponing such payment, at first because plaintiff had not secured an order from Yanderberry for the balance, and later because the building was not yet completed. On September 15, 1931, the contractors notified plaintiff that the balance due Yanderberry then was $2,314.41, which they offered to pay to plaintiff, if it would guarantee them against any action of any of his creditors against them, and would also assign to them its claim against them and their surety arising out of the subcontractor ’s default. The tender was not accepted and plaintiff sued for its entire claim of $5,624.64. The circuit court found in its favor for the above balance of $2,314.41.

The law applicable to this ease is well settled and it is mainly a problem in mathematics. There is no evidence on the correctness of the estimates of the architect or of the entire cost of the Yanderberry work. One would infer that the estimates were too liberal or that the work cost more than $15,000.00, the contract price. Be that as it may, the bond herein obligates the contractors and the surety (under Code .1923. ch. 75, sec. 12) to pay in full for all materials used in the construction of the courthouse, irrespective of loss to them through the default of a subcontractor. It makes no difference whether the materials are furnished to the principal contractors or to a subcontractor. Hibner v. Ebersbach, 110 W. Va. 177, 157 S. E. 178. However, a materialman may waive the security of the bond. Jones on Liens (3d Ed.), sec. 1500. The plaintiff did waive that security by its telegram of May 7th (“Satisfactory with us to pay Yanderberry on estimates when due”). But as the waiver was voluntary, it could be withdrawn if not to the legal prejudice of the contractors. The waiver was withdrawn on May 24th. Had the contractors paid over to Yanderberry before May 24th all the money due him under the estimate of May 1st, they would have been protected as to the marble included in that estimate. But they did not do that. Their account with Yander-berry, which they file, shows that up to May 24th they had *310 paid either to him or on his account only $8,739.32. Under their contract with him, at least 85% of the $13,000.00 awarded them on May 1st, or $11,050.00, was payable to him on May 15th. (The brief of the contractors concedes that this sum was then payable to Yanderberry.) Deduct from the sum payable the amount of the advances made to or for Yanderberry and the difference is $2,310.68. The contractors had no arbitrary right to retain this difference. But they did so and charged against it by June 1st, freight and express bills amounting to $79.30, leaving a difference on the original estimate of $2,231.38 then payable to Yanderberry. Of the $4,000.00 awarded in the estimate of June 1st, $2,000.00 (the balance due Vanderberry after subtracting $13,000.00, the allowance of May 1st, from $15,000.00, the entire contract price) should have been credited to Yanderberry and 85% of that sum, or $1,700.00, was payable to him on June 15th. Therefore, on that date, $2,231.38 undisposed of from the first estimate and $1,700.00 from the second estimate, or $3,931.38 in all, was payable to Yanderberry. The contract with him gave the contractors no right to retain this sum merely to insure the completion of the work. On the contrary, the contract required them to pay Yanderberry all of the monthly estimate except 15% “within fifteen days after submission of estimates”. Of course, this requirement did not preclude the contractors from retaining enough in addition to the 15% to protect themselves against the claims of Yander-berry ’s workmen and materialmen. But no such claims are alleged or proved to have existed prior to June 15th, except the claim of the plaintiff, with this qualification: the contractors’ account against Yanderberry shows charges on June 13th of $30.00 paid to one W. G-. Anderson and of $746.59 expended on a payroll.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hibner v. Ebersbach
157 S.E. 178 (West Virginia Supreme Court, 1931)
Hamilton v. Republic Casualty Co.
135 S.E. 259 (West Virginia Supreme Court, 1926)
Rhodes v. Riley
169 S.E. 525 (West Virginia Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
171 S.E. 751, 114 W. Va. 307, 1933 W. Va. LEXIS 71, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appalachian-marble-co-v-boone-wva-1933.