Crane Co. v. James McHugh Sons, Inc.

108 F.2d 55, 1939 U.S. App. LEXIS 2502
CourtCourt of Appeals for the Tenth Circuit
DecidedNovember 6, 1939
DocketNo. 1819
StatusPublished
Cited by13 cases

This text of 108 F.2d 55 (Crane Co. v. James McHugh Sons, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crane Co. v. James McHugh Sons, Inc., 108 F.2d 55, 1939 U.S. App. LEXIS 2502 (10th Cir. 1939).

Opinions

PHILLIPS, Circuit Judge.

James McHugh Sons, Inc.,1 entered into a contract with the United States for the construction of eighteen apartments at Fort Sill, Oklahoma, for $612,000.

On January 8, 1934, McHugh, as principal, and the New Amsterdam Casualty Company, Hartford Accident and Indemnity Company, The Fidelity and Casualty Company of New York, and the United States Fidelity and Guaranty Company,2 as sureties, executed a bond to the United States conditioned for the faithful performance of the contract and the prompt payment to all persons supplying labor and material in the prosecution of the work provided for in the contract.

H. W. Thompson, doing business as H. W. Thompson Heating & Engineering Company,3 submitted a bid to McHugh for furnishing all materials and performing all labor in the installation of the plumbing, gas, and heating equipment in the apartments for the sum of $94,000.4 McHugh advised Thompson that the bid would be accepted if he could furnish a proper surety bond.

Crane Company5 had its principal office at Chicago, Illinois, and maintained a branch office at Oklahoma City, Oklahoma. It had a copy of the plans and had suggested to Thompson that he submit a bid, had quoted him prices, and assisted him in preparing and submitting his bid. Thompson experienced difficulty in securing the bond and took the matter up with Legg, manager of the branch office of Crane at Oklahoma City. Thompson advised Legg that he could secure the bond if Crane would furnish the materials and look to Thompson alone for payment therefor. Legg suggested to Thompson that they go to Chicago and take the matter up with Crane’s head office in that city. Whereupon, Legg and Thompson went to Chicago. They conferred with various surety companies and Legg conferred with the officers of Crane. Thereafter, the Guaranty Company agreed to write the bond on condition that Crane waive any claim under the bond for materials furnished to Thompson. On December 7, 1933, Legg, purporting to act as the agent of Crane, executed the waiver to the Guaranty Company. Thereafter, the Guaranty Company executed Thompson’s bond in the principal sum of $97,700, the bid in the meantime having been increased to that amount by a supplemental bid.

The subcontract was entered into between McHugh and Thompson. Under it McHugh was to pay Thompson on or about the fifteenth of each month, 90 per cent of the value of the work completed during the preceding month as estimated and approved by the constructing quartermaster, and the remaining 10 per cent upon final completion and acceptance of the work by the constructing quartermaster, such payments to be made only upon presentation of formal waivers of liens, together with an affidavit that all payments had been made for all labor and materials. The subcontract expressly provided that McHugh had the right to retain at any time out of moneys due Thompson a sum sufficient to pay all persons wbo had performed labor or furnished materials for work included in the contract and that such sums might be retained until satisfactory evidence was furnished to McHugh that all such claims had been fully satisfied.

Thompson entered into the performance of the subcontract. On February 24, 1934, McHugh wrote a letter to Thompson reading in part as follows:

“We are enclosing our check No. 7293 in the amount of $10,630.00 as a payment on your January estimate. * * * We were compelled to withhold your payment until we received your waiver from the Oklahoma Office of Crane Company.
“The release of Crane Company dated February IS does not meet with our approval, as the form used is a waiver of lien used on private enterprises, * * * It is our request, therefore, that you again [58]*58contact the Crane Company office and have them prepare a reléase as follows:
“We, the Crane Company of 705 West Main Street, Oklahoma City, Oklahoma, will hold the H. W. Thompson Heating & Engineering Company of Stillwater, Oklahoma, duly responsible for the payment of all plumbing and heating material furnished on the 18 Four Family Apartments now being erected at Fort Sill Oklahoma. Further, in the event the H. W. Thompson Heating & Engineering Company default in the payment of their account to us, we will not hold James McHugh Sons, Inc., General Contractors, of 6449 South Park Avenue, Chicago, 111., responsible for the payment of our account. This release embodies all the materials to be furnished by us in connection with this contract.
“The above form of release must be signed by a duly authorized representative of the Crane Company * * * Would request you to send us this release at the earliest possible date, obliging * * * ”

On March 1, 1934, Legg prepared a release in the exact language of that requested by McHugh in its letter of February 24, 1934, signed it “Crane Co., by C. L. Legg, Manager,” and forwarded it to McHugh at its Chicago office.

McHugh mailed a copy of its letter of February 24, 1934, to Crane at its Chicago office and on re'ceipt of the release of March 1, 1934, executed by Legg, forwarded a letter to Crane at its Chicago office enclosing a copy of such release. Crane did not advise McHugh that Legg was unauthorized to execute the release, or otherwise object thereto until it filed its petition of intervention in the instant case.

Thompson completed the performance of the sub-contract. McHugh paid him the amount due on the monthly estimates and the final estimate in reliance upon the release of March 1, 1934, and out of such funds Thompson made monthly payments to Crane for materials furnished, during the months of February and September, 1934, inclusive, aggregating $45,130.47.

The United States on relation of J. B. Klein Iron & Foundry Company brought this suit against McHugh and its sureties on the bond of January 8, 1934. Crane filed an intervening petition therein, asserted a balance due from Thompson of $28,697.06, and sought recovery thereof from McHugh, Thompson, and the sureties on the bond of January 8, 1934. McHugh and the sureties pleaded the release of March 1, 1934. Thompson denied any indebtedness to Crane and asserted that he and Crane were coadventurers in the carrying 'out of the sub-contract.

The trial court held that the letter of March 1, 1934, released McHugh from any liability to Crane for materials furnished and discharged McHugh’s sureties and entered judgment on the intervening petition in favor of McHugh and its sureties. Crane has appealed.

Crane asserts that Legg was without authority to execute the waiver to the Guaranty Company. Crane here seeks recovery upon the bond given by McHugh and its sureties and not upon the bond given by Thompson and the Guaranty Company. Whether Legg had authority to sign the waiver to ,the Guaranty Company is not here material. However, Legg had been connected with Crane for 35 years and for 18 years had been employed at its Oklahoma City branch. After the Guaranty Company demanded the waiver as a condition to writing the bond, Legg went to the office of C. R. Crane, vice president of Crane, for the purpose of taking up the matter of executing the waiver. When he came out of Mr. Crane’s office Legg said to Thompson, “We got everything all fixed.” Thereupon, he went to the office of the Guaranty Company and executed the waiver. Under all the circumstances, it is a fair "inference that he was authorized so to do.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stone v. First Wyoming Bank
625 F.2d 332 (First Circuit, 1980)
Stone v. First Wyoming Bank N. A.
625 F.2d 332 (Tenth Circuit, 1980)
American States Insurance v. Floyd I. Staub, Inc.
370 N.E.2d 989 (Indiana Court of Appeals, 1977)
Crane Co. v. PARK CONSTRUCTION CO. INC.
247 N.E.2d 591 (Massachusetts Supreme Judicial Court, 1969)
Moyer v. United States, for Use of Trane Co.
206 F.2d 57 (Fourth Circuit, 1953)
Knox v. First Security Bank of Utah
196 F.2d 112 (First Circuit, 1952)
Wittlin v. Giacalone
171 F.2d 147 (D.C. Circuit, 1948)
Pittsburgh Steel Co. v. Standard Accident Ins.
55 F. Supp. 36 (E.D. South Carolina, 1944)
Farmers Co-Op. Oil Co. v. Socony-Vacuum Oil Co.
133 F.2d 101 (Eighth Circuit, 1942)
Alexander v. Phillips Petroleum Co.
130 F.2d 593 (Tenth Circuit, 1942)
Hanover Fire Ins. v. Isabel
129 F.2d 111 (Tenth Circuit, 1942)
New York Casualty Co. v. Sinclair Refining Co.
108 F.2d 65 (Tenth Circuit, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
108 F.2d 55, 1939 U.S. App. LEXIS 2502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crane-co-v-james-mchugh-sons-inc-ca10-1939.