Moyer v. United States, for Use of Trane Co.

206 F.2d 57, 39 A.L.R. 2d 1098, 1953 U.S. App. LEXIS 3848
CourtCourt of Appeals for the Fourth Circuit
DecidedJuly 16, 1953
Docket6602_1
StatusPublished
Cited by34 cases

This text of 206 F.2d 57 (Moyer v. United States, for Use of Trane Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moyer v. United States, for Use of Trane Co., 206 F.2d 57, 39 A.L.R. 2d 1098, 1953 U.S. App. LEXIS 3848 (4th Cir. 1953).

Opinion

SOPER, Circuit Judge.

These suits were brought under the Miller Act, 49 Stat. 793, 40 U.S.C.A. §§ 270a and 270b, by The Trane Company, The Crane Company and MinneapolisHonejuvell Regulator Company, to recover the balance due for materials furnished by them to a subcontractor in the construction of a government armory. The defendants are the prime contractors, A. C. Moyer and J. E. Moyer, partners, doing business as Moyer Brothers, and Continental Casualty Company, their statutory surety on a payment bond. The cases were consolidated for trial, and the District Court, sitting without a jury, entered judgment for the claimant in each case, i. e., $4,-949.11 for Trane, $1,614.60 for Crane, and $1,495.00 for Minneapolis-Iioneywell, or a total of $8,058.71; whereupon this appeal was taken.

The controversies arise out of a contract of June 16, 1950 whereby Moyer Brothers contracted with the United States to build an armory at South Charleston, West Virginia, at a price of $241,071.50. Pursuant to the statute, Moyer Brothers *59 posted a payment bond in the amount of $120,535.75, with Continental Casualty Company as surety, for the protection of persons supplying labor and materials for the armory project. On June 30, 1950 Moyer Brothers entered into a subcontract with John R. Kegley for the installation of plumbing, drainage, gas fittings and a heating plant for the armory for the sum of $16,356.55. In the performance of this contract Kegley obtained materials from the claimants and other suppliers not involved here. In accordance with the subcontract he submitted each month to Moyer Brothers an estimate of the amount he had paid for labor during the preceding month, and the amount of materials which had been either incorporated in the building or placed on the job site ready for iustallation. Materials listed by Kegley on these estimates had not been paid for by him, except for items taken out of bis stock, Moyer Brothers, as provided by tile contract, paid Kegley 90 per cent: of his monthly estimates up to and including the estimate submitted Marcn 1, 1951, retaming 0 per cent.

During the next two or three months occurred the circumstances upon which rests the main defense of Moyer Brothers to the plaintiffs’ claims. Moyer Brothers became apprehensive that Kegley had been paid a larger stun under the subcontract than his performance justified. The testimony on the point is conflicting but it is beyond dispute that Kegley had included in his estimates materials which he had installed hut had not paid for. Moyer Brothers took two steps to protect themselves. ™ . . , . . , , They refused to make funlier payments to . , , 1 . . . , Kegley and demanded that he furnish re- . . ceipts showing that the materials, which „ ’ ... , , . , . , had been delivered to him by the material- .... . . men and included m previous estimates, had ’ ecu pan oi.

Kegley became financially embarrassed about this time and was without the necessary funds to complete the work he had agreed to do. Accordingly he requested Moyer Brothers to furnish the money to meet his weekly payrolls, and they complied, beginning with the payroll of April 13, 1951, but thereafter, except for the payrolls and for the purchase of certain materials necessary for the completion of the job, they paid out no money on account of the work covered by the subcontract. The work was completed by Kegley’s employees under the direction of his superintendent, and Kegley himself was on the job from time to time. Moyer Brothers claim to have supervised the performance of the work beginning in April, 1951 until it was finished, but whether their activities in this repect were in excess of those ordinarily performed by a prime contractor is not clearly shown and there is no testimony as to additional expense incurred therefor by Moyer Brothers. The balance due Kegley upon the completion of the contract was S7/I63.80. 1 Kegley went into bankruptcy in July or August, 1952.

In ^ meantime in the m(Mlth of May, 1931> Kegley, having becn tok} by Moyer Brothers that they would make no further payments to him until he furnished receipts showing that he had paid for the materials which had becn installed by him in the building, obtained from Trane a release of claim for materials furnished to Kegley, an(l from each of the other claimants a receipt showing payment in full for the a2 tides supplied by them to Kegley. Ine matei'ials, however had not been paid for anc^ ^le sMtemeius t0 ti10 contrary in tne rcceiPts wcre ^orrect. The claimants, UP0U cx^uiting t e papers, received only checks to be held by them for future pay- . , , merit winch Kegley hoped to make good , ,, T) 5 , . . . when Moyer Brothers honored Ins esti- , ™ , . , mates. 1 he checks, however, were never . . T-r , . , paid. Kegley presented the release and . , , ^ receipts to Moyer Brotners as evidence that he had paid the claimants for the goods, and failed to inform Moyer Brothers that the statements therein contained were false. Moyer Brothers, nevertheless, made no *60 further payments, except for payrolls and materials needed in the work.

Moyer Brothers contend that the amounts claimed by the plaintiffs and allowed by the court are not due because Moyer Brothers had paid Kegley on his estimates for nearly all of the materials covered by the instant suits; and also because they were deceived by the false certificate and receipts, and led to take actions to their detriment which they would not have performed if they had known the truth. There is, however, nothing in the first position for it is the essence and purpose of the statute and of - the payment bond on a government construction project to protect the materialmen and to place the burden on the contractor to make sure that they are paid for the goods which they furnish. Smith v. Mosier, C.C.N.Y., 169 F. 430, 435; Seaboard Surety Co. v. Standard Acc. Ins. Co., 277 N.Y. 429, 433, 14 N.E.2d 778, 117 A.L.R. 658.

The main defense is that the matt.yialmen are estopped to sue the contractor and the bonding company because of the false statements in the papers which they signed. On this point the law is also dear since the improper practice in which the claimants engaged in this case finds a parallel in prior cases where false receipts were given by materialmen to a subcontractor to aid him in securing payments from the prime contractor for work done under a subcontract. The prime contractor, in order to protect himself, not infrequently requires a subcontractor to furnish receipted bills to show that the materials installed in the work and included in his estimates, have actually been paid for, and sometimes the materialmen, relying on the promises of the subcontractor, give false receipts to assist him in getting payments from the prime contractor. The rule to be deduced from the cases is that which is embodied in the legal principle of estoppel, which precludes one from denying the truth of statements upon which other persons have relied to their detriment. Territory of Arizona ex rel. Tax Collector of Cochise County v. Copper Queen Consol. Mining Co., 233 U.S. 87, 95, 34 S.Ct. 546, 58 L.Ed. 863.

In the application of this rule in suits under the Miller Act and its predecessor, the Heard Act, Act Aug.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. GE Supply v. G & C Enterprises, Inc.
29 F. Supp. 2d 49 (D. Puerto Rico, 1998)
Westinghouse Electric Supply Co. v. B. L. Allen, Inc.
413 A.2d 122 (Supreme Court of Vermont, 1980)
United States v. Aetna Casualty & Surety Co.
480 F.2d 1095 (Eighth Circuit, 1973)
L. M. White Contracting Co. v. St. Joseph Structural Steel Co.
488 P.2d 196 (Court of Appeals of Arizona, 1971)
Crane Co. v. PARK CONSTRUCTION CO. INC.
247 N.E.2d 591 (Massachusetts Supreme Judicial Court, 1969)
United States v. Glassman Construction Co.
397 F.2d 8 (Fourth Circuit, 1968)
United States v. Glassman Construction Company
397 F.2d 8 (Fourth Circuit, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
206 F.2d 57, 39 A.L.R. 2d 1098, 1953 U.S. App. LEXIS 3848, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moyer-v-united-states-for-use-of-trane-co-ca4-1953.