United States ex rel. Farwell, Ozmun, Kirk & Co. v. Shea-Adamson Co.

21 F. Supp. 831, 1937 U.S. Dist. LEXIS 1284
CourtDistrict Court, D. Minnesota
DecidedDecember 18, 1937
DocketNo. 3712
StatusPublished
Cited by12 cases

This text of 21 F. Supp. 831 (United States ex rel. Farwell, Ozmun, Kirk & Co. v. Shea-Adamson Co.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Farwell, Ozmun, Kirk & Co. v. Shea-Adamson Co., 21 F. Supp. 831, 1937 U.S. Dist. LEXIS 1284 (mnd 1937).

Opinion

SULLIVAN, District Judge.

This is an action by the United States of America, for the Use and Benefit of Farwell, Ozmun, Kirk & Co., a corporation, against Shea-Adamson Company, a corporation, Nils P. Severin and Alfred N. Severin, copartners doing business under the name and style of N. P. Severin Company, and .Royal Indemnity Company, a corporation, under the provisions of the Heard Act, 40 U.S.C.A. § 270.

This suit is brought by the plaintiff materialman to recover the unpaid balance on certain materials furnished to the SheaAdamson Company, the subcontractor, in the performance of its contract in constructing and installing a ventilating system in the post office building in Minneapolis, Minn.

N. P. Severin Company is the general contractor. The defendant Royal Indemnity Company is the surety on its bond given in connection with said job contract, and Shea-Adamson Company is one of the subcontractors on said job for the ventilating system.

The Heard Act, 40 U.S.C.A. § 270, authorizes a cause of action in the form in which this one is brought, in favor of subcontractors, laborers, and materialmen, and the time within which they must bring the suit is limited to one year after the completion of the work and “final settlement” of the contract, but it may not be brought within the first six months of such period, which is reserved to the United States to sue on its own account.

This suit was started on the 30th day of December, 1936, arid the final settlement of the general contract for the construction of said post office building was made May 14, 1936. When one action has been brought, all the other creditors must intervene therein within one year from the date of the final settlement. 40 U.S.C.A. § 270; United States, for Use of Joseph Tino & Co., Inc., v. Rangely Const. Co., Inc., et al., D.C., 288 F. 76.

Two complaints in intervention within the time allowed by law were filed:

(a) The claim of Emil A. March. During the progress of the trial, a stipulation of settlement and dismissal of said claim was filed.

(b) The claim of Conditionedaire, Inc.

The claim of the plaintiff was duly settled and dismissed during the progress of the trial.

The complaint in intervention of Conditionedaire, Inc., is divided into four claims, all of which said claims were duly sold and assigned by the original claimants, materialmen, and laborers, to1 the intervener, Conditionedaire, Inc., before the bringing of this action.

The different claims of Conditionedaire, Inc., will be taken up in order, viz.:

Minneapolis Roofing Company.

William H. Gausewitz and Louis C. Provencial, copartners doing business as the Minneapolis Roofing Company, on February 28, 1934, sold and delivered directly to the N. P. Severin Company certain building materials, which were incorporated in the Minneapolis post office building, and on which a balance of $133 is due, payment thereof being demanded on or before March 10, 1934. This claim has been established, and no evidence in opposition thereto was offered or received at the trial.

Minnesota Steel Supply Company.

This company sold and delivered, between February 12, 1934, and June 7, 1934, to the Shea-Adamson Company certain materials which _ were incorporated in the ventilating job in said Minneapolis post office building, upon which there is a balance due of $346.87, payment of the balance having been duly demanded on or before November 10, 1934. The amount of the account is undisputed, and it is conceded that said materials went into the Minneapolis post office ventilating job. It is further conceded that demand for the payment of the said balance was made on the Shea-Adamson Company on March 10, 1934.

It is, however, contended on the part of the defendants N. P. Severin Company and Royal Indemnity Company that they are not liable on said claim by reason of the [834]*834fact that a waiver or release of the claim was executed by the Minnesota Steel Supply' Company and delivered by it to the Shea-Adamson Company, which in turn delivered it to the N. P. Severin Company.

(a) The question arises as to whether or not the release of the Minnesota Steel Supply Company bars it from a recovery against the general contractor and its surety. The release is dated December 30, 1933, and was on the same date delivered to the Shea-Adamson Company. The release, among other things, reads as follows, * * * do hereby waive and release any and all liens, claims, or right of liens on said above described building and premises, and do further release N. P. Sever in Company and their sureties and the owners of the above described building on all claims and demands whatsoever, on account of labor or materials, or both, furnished or which may be furnished by the undersigned for said building or premises,” and the release in other parts refers to the United States post office at Minneapolis, Minn.

It appears from the record that there was no actual intention to waive any known right. In fact, ,at the time of the execution of said release, there was in existence no right in favor of claimant as against Shea-Adamson Company, the general contractor, or its surety. At the .time the so-called release or waiver was signed, the material which was involved in this action had not been furnished or ordered. The items in the claim of the Minnesota Steel Supply Company evidence sale and delivery of materials on February 12, 1934, May 16, 1934, and June 7, 1934.

To waive or release a lien right, it must appear to be supported by a consideration. Abbott v. Nash, 35 Minn. 451, 452, 29 N.W. 65.

There was no consideration in the instant case for the release,' nor does the record disclose any grounds of estoppel barring the intervener from asserting this claim. No receipt was' ever given by the Minnesota Steel Supply Company for the payment of the account. All that was given ¡was a writing in the form of- a release of lien on the lands and buildings, of course such release of lien being'with reference to the building, the Minneapolis post office, was without any force or effect, .since claimant would -under .no circumstances have a right to file -a- lien against a government building, and a release of right of claim as against the general contractor and its surety, but was in no manner a release of any claim against the Shea-Adam-son Company, or was it in satisfaction of any claim against the Shea-Adamson Company. The release is not a bar to a recovery on this claim. See Kubu v. Kabes, 142 Minn. 433, 172 N.W. 496; Ohio Confection Co. v. Eimon Mercantile Co., 154 Minn. 420, 191 N.W. 910, 31 A.L.R. 952; Duncansori v. Chicago Title & Trust Co., 188 Ill.App. 551; Empire State Surety Co. v. Hanson, 8 Cir., 184 F. 58; Antrim Lumber Co. v. Neal et al., 172 Okl. 292, 44 P.2d 939; Johnson v. Spencer, 49 Ind.App. 166, 96 N.E. 1041; Cellized Floors, Inc., v. Glens Falls Indemnity Co. of New York, 156 A. 845, 9 N.J.Misc. 1111.

The record shows that the general contractor had supervisors and foreman on the job, and that it either had knowledge of the truth of the fact that at the time of the delivery of the waiver or release that said materials referred to in said itemized statement had not been delivered on the job or furnished to the Shea-Adamson Company, or in any event, the general contractor had the means by which, with the use of reasonable diligence, it could acquire this knowledge.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
21 F. Supp. 831, 1937 U.S. Dist. LEXIS 1284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-farwell-ozmun-kirk-co-v-shea-adamson-co-mnd-1937.