Fillbach v. Inland Construction Cor

CourtMontana Supreme Court
DecidedSeptember 29, 1978
Docket13907
StatusPublished

This text of Fillbach v. Inland Construction Cor (Fillbach v. Inland Construction Cor) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fillbach v. Inland Construction Cor, (Mo. 1978).

Opinion

No. 13907

IN THE SUPREME COURT OF THE STATE OF MONTANA 1978

EDWIN R. FILLBACH, DALE FILLBACH, d/b/a FILLBACH & SONS, Plaintiff and Respondent,

INLAND CONSTRUCTION CORPORATION, INLAND DEVELOPMENT CORPORATION OF MONTANA; BIG SKY OF MONTANA, INC., et al., Defendants and Appellants.

Appeal from: District Court of the Eighteenth Judicial District, Honorable Frank E. Blair, Judge presiding. Counsel of Record: For Appellants: Brown, Pepper and Komrners, Bozeman, Montana William L. Pepper argued, Bozeman, Montana

For Respondent : Bolinger and Wellcome, Bozeman, Montana G. Page Wellcome argued, Bozeman, Montana

Submitted: April 27, 1978 Decided: b-F 7 1978 Filed: 2 . ;gT@ Mr. Justice Daniel J. Shea delivered the Opinion of the Court.

Defendant Big Sky of Montana, Inc., appeals from a

judgment of the District Court, Gallatin County, foreclosing

a mechanic's lien in favor of plaintiffs, Edwin R . Fillbach, individually, and d/b/a Fillbach and Sons.

Big Sky of Montana, Inc., (hereinafter Rig Sky) is the

developer of a condominium project on land it owns near

Bozeman, Montana. Inland Construction Corp. was the general contractor for the project. In early 1974, plaintiff Fillbach

submitted a bid for painting and drywall work on the project's Glacier condominiums. Plaintiff's bid was accepted by the general contractor.

Plaintiff and his crew began working on the project, but due to various construction problems not attributable to

plaintiff, the project was delayed and expected completion date

was extended. In September 1974, the general contractor determined the project would have to be expedited and added

several men to plaintiff's crew for that purpose. Thereafter, plaintiff had difficulty meeting his expenses, due in part to the expanded crew which had been assigned to him. The general contractor promised other subcontractors

increases in their contract prices because of the construction

delays, but the parties dispute whether plaintiff was promised

such an increase. Plaintiff contends his contract was reneg- otiated to a cost-plus basis, but Big Sky contends plaintiff

was not promised the increase given the other subcontractors because he was not meeting his contract obligations. plaintiff

did receive regular contract payments, but he did not receive

any increase over the contract price specified in his bid. I n J a n u a r y 1975 t h e g e n e r a l c o n t r a c t o r began con-

t r o l l i n g t h e money p a i d t o p l a i n t i f f f o r d i s b u r s e m e n t t o

h i s employees, s u b c o n t r a c t o r s and s u p p l i e r s . P l a i n t i f f was

t e r m i n a t e d from t h e p r o j e c t on February 1 2 , 1975, a f t e r

t e l l i n g t h e g e n e r a l c o n t r a c t o r he would need a d d i t i o n a l money

t o complete h i s work. P l a i n t i f f r e c e i v e d a check i n t h e amount

of $457.64 on t h e day of h i s t e r m i n a t i o n . Accompanying t h a t

check was a l i e n w a i v e r p r i n t e d on a form p r o v i d e d by t h e

general contractor. Such l i e n w a i v e r s were p r o c u r e d a t t h e

i n s i s t e n c e of Big Sky from a l l s u b c o n t r a c t o r s a s t h e y w e r e

p a i d f o r work performed o r l a b o r f u r n i s h e d on t h e p r o j e c t .

P l a i n t i f f e x e c u t e d 37 s u c h w a i v e r s upon r e c e i p t of a p p r o x i m a t e l y

3 1 c h e c k s d u r i n g t h e p e r i o d from J a n u a r y 1 6 , 1974 t o F e b r u a r y

1 4 , 1975.

A f t e r h i s t e r m i n a t i o n , p l a i n t i f f demanded payment he

a l l e g e d was due under t h e c o n t r a c t a s r e n e g o t i a t e d t o t h e

cost-plus standard. He d u l y p e r f e c t e d a m e c h a n i c ' s l i e n a g a i n s t

Big Sky f o r t h e b a l a n c e due under t h a t c o n t r a c t and b r o u g h t

the present action. Named a s d e f e n d a n t s were t h e g e n e r a l

c o n t r a c t o r , Big Sky, and s e v e r a l p a r t i e s c l a i m i n g an i n t e r e s t

i n Big S k y ' s p r o p e r t y . I n l a n d Development C o r p o r a t i o n of

Montana, t h e a s s i g n e e of I n l a n d C o n s t r u c t i o n ' s i n t e r e s t , was

l a t e r joined a s a p a r t y defendant.

The c a u s e was t r i e d b e f o r e t h e D i s t r i c t Court s i t t i n g

without a jury. Big Sky was t h e o n l y d e f e n d a n t i n v o l v e d i n

t h i s appeal t o appear. I n l a n d C o n s t r u c t i o n C o r p o r a t i o n and

I n l a n d Development C o r p o r a t i o n d e f a u l t e d and t h e o t h e r p a r t i e s '

i n t e r e s t s were d e t e r m i n e d . O A p r i l 8 , 1977, t h e D i s t r i c t n

Court e n t e r e d f i n d i n g s of f a c t and c o n c l u s i o n s of law and

judgment i n p l a i n t i f f ' s f a v o r . The D i s t r i c t Court found

p l a i n t i f f ' s l i e n a g a i n s t Big Sky t o be i n t h e amount of $43,693.94. Plaintiff was awarded that amount, plus costs and attorney's fees in the amount of $21,000. Following denial of its motions to amend and make additional findings of fact and conclusions of law and for a new trial, Big Sky appealed. Two issues are presented for review: (1) whether the District Court erred in limiting the scope of the lien waivers to the money received as each such waiver was executed, and (2) whether the District Court abused its discretion in awarding a $21,000 attorney's fee. The first issue concerns the interpretation of the lien waivers signed by plaintiff. Each such waiver was prepared on the following form: "RECEIPT AND WAIVER OF MECHANICS' LIEN RIGHTS N.B. It is important that the following directions be closely followed as otherwise the receipt WILL NOT BE ACCEPTED. 1. This is a LEGAL INSTRUMENT and must be executed accordingly by officers of corporations and by partners of co-partnerships. 2. It is important that ALL the blanks be completed and that the AMOUNT PAID BE SHOWN. 3. If payment is not in full to date, so state, SHOW UNPAID BALANCE, and strike out last three lines. 4. A receipt similar to this or legal waiver of lien rights will be required for all plumbing, heating and plastering material, etc. 5. NO ERASURES OR ALTERATIONS MUST BE MADE.

(date) The undersigned acknowledges having received payment of from in full payment of all by the undersigned delivered or furnished to (or performed at) and for value received hereby waives all riqhts which may have been acquired by the undersigned to file mechanics' liens against said premises for labor, skill, or material furnished to said premises prior to the date hereof. The District Court's Finding of Fact VII states: "That on each occasion when the plaintiff would receive payment for work performed and materials furnished, he would sign a lien waiver which lien waiver was solely limited to the amount of money received at that particular time and such lien waiver did not in any way prevent the plaintiff from filing and foreclosing a mechanic's lien for all amounts not covered by the specific lien waivers which were required by the Inland Corporations for each payment which they made to the plaintiff; that this manner of proceeding was requested by the defendant Big Sky of Montana, Inc., and the Inland Corporations were paid an overhead margin and a profit margin on all amounts which they paid to their subcontractors." The thrust of Big Sky's argument is that the above finding is contrary to the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Safeco Insurance Company v. Munroe
527 P.2d 64 (Montana Supreme Court, 1974)
Merritt v. Merritt
526 P.2d 1375 (Montana Supreme Court, 1974)
Crncevich v. Georgetown Recreation Corporation
541 P.2d 56 (Montana Supreme Court, 1975)
Tribble v. Reely
557 P.2d 813 (Montana Supreme Court, 1976)
State, by and Through State Hwy. Com'n v. Marsh
575 P.2d 38 (Montana Supreme Court, 1978)
Mittelstadt v. Buckingham
480 P.2d 831 (Montana Supreme Court, 1971)
Kielmann v. Mogan
478 P.2d 275 (Montana Supreme Court, 1970)
Valier-Montana Land & Water Co. v. Ries
97 P.2d 584 (Montana Supreme Court, 1940)
Hale v. Belgrade Co., Ltd.
242 P. 425 (Montana Supreme Court, 1925)
Sherburne Mercantile Co. v. Bonds
145 P.2d 827 (Montana Supreme Court, 1944)
Ikovich v. Silver Bow Motor Car Co.
157 P.2d 785 (Montana Supreme Court, 1945)
St. Louis Flexicore, Inc. v. Lintzenich
414 S.W.2d 787 (Missouri Court of Appeals, 1967)
Lehrkind v. McDonnell
153 P. 1012 (Montana Supreme Court, 1915)
Lewis v. Lambros
194 P. 152 (Montana Supreme Court, 1920)
McCaull-Dinsmore Co. v. Stevens
0 P. 000 (Montana Supreme Court, 1921)
Thisted v. Country Club Tower Corp.
405 P.2d 432 (Montana Supreme Court, 1965)
McNussen v. Graybeal
405 P.2d 447 (Montana Supreme Court, 1965)
Larson v. Burnett
492 P.2d 921 (Montana Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
Fillbach v. Inland Construction Cor, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fillbach-v-inland-construction-cor-mont-1978.