United States ex rel. Krupp Steel Products, Inc. v. Aetna Insurance

923 F.2d 1521
CourtCourt of Appeals for the Eleventh Circuit
DecidedFebruary 21, 1991
DocketNos. 89-3389, 90-3063 and 90-3325
StatusPublished
Cited by4 cases

This text of 923 F.2d 1521 (United States ex rel. Krupp Steel Products, Inc. v. Aetna Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Krupp Steel Products, Inc. v. Aetna Insurance, 923 F.2d 1521 (11th Cir. 1991).

Opinion

FAY, Circuit Judge:

This appeal involves a suit brought under the Miller Act by plaintiff-appellee Krupp Steel Products, Inc. d/b/a Diversified Steel Services (“Diversified”), a supplier of steel. Diversified sued defendant-appellant Aetna Insurance Company (“Aetna”) as surety on a public works construction project in Tampa, Florida. At trial, Aetna attempted to raise the affirmative defense of estoppel. The trial court, however, interpreted the jury’s responses to interrogatories contained in the Special Verdict form in such a way as to conclude that Aetna had failed to establish the elements of estoppel. The court therefore entered a final judgment for the full amount of Diversified’s claim. Because of the extreme confusion surrounding the meaning of the jury’s verdict, generated in large part by the district court’s attempts on remand to accommodate an earlier discussion of estoppel by a panel of our Circuit, we reluctantly must REVERSE and REMAND this case once again for a new trial on the issue of estop-pel.

FACTUAL BACKGROUND AND PROCEDURAL HISTORY

As mentioned, Diversified is a supplier of steel. Allied Steel Fabrications (“Allied”), a steel fabricator, was a subcontractor for a portion of the construction of the Forest Hills Post Office, a federal public work in Tampa, Florida (the “Forest Hills job”). The general contractor for the Forest Hills job was John D. Grubbs, Inc. (“Grubbs”). As required by the Miller Act, Grubbs, the principal, and Aetna, as surety for the project, executed and delivered a public works payment bond to the Post Office for the protection of all persons supplying labor or materials to the Forest Hills job.

Allied ordered raw steel for the Forest Hills job from Diversified, and Diversified shipped steel to Allied’s yard from June to December, 1984.1 Allied made only one payment of $10,058.39 for Diversified’s steel deliveries.

Although it had received only one payment, Diversified’s credit manager gave Allied two separate partial releases of lien (or “partial lien waivers”) in connection with the payment.2 The first partial lien waiver was signed on October 26,1984, and recited nominal consideration of $10.00. The second partial lien waiver, signed November 15, 1984, recited as consideration the amount actually received from Allied— $10,058.39. Both partial lien waivers had “effective dates” of August 31, 1984.

[1523]*1523Diversified sued Aetna as surety for the project under the Miller Act, 40 U.S.C. § 270a, to recover the balance of outstanding payments owed by Allied for steel shipped between September 6, 1984, and December 20, 1984. Diversified demanded judgment in the amount of $36,667.82, plus interest, costs, and a reasonable attorney’s fee. In answering Diversified’s complaint, Aetna raised several affirmative defenses. Diversified then moved for summary judgment with supporting affidavits. Aetna subsequently moved for leave to file an amended answer for the purpose of adding a sixth affirmative defense.3 The district court granted Diversified’s motion for summary judgment, in the process denying as moot Aetna’s motion to file an amended answer. The court awarded Diversified the full sum of $39,667.82, as well as $5,524.00 in attorney’s fees.

Appealing the district court’s summary judgment in favor of Diversified, Aetna raised three issues. Aetna argued (1) that fact issues existed regarding Diversified’s good faith belief that the materials included in its Miller Act claim were actually intended for use in the Forest Hills job; (2) that fact issues existed regarding Aetna’s claim of estoppel (the claim embodied in the language of the sixth affirmative defense that Aetna sought to add to its original pleading); and (3) that Diversified was not entitled to an award of attorney’s fees.

In Krupp /, 831 F.2d at 984, a panel of our Circuit, although affirming the district court’s resolution. of the good faith issue, reversed the district court’s summary judgment in favor of Diversified, and remanded the case. The panel ruled that Aetna had made a showing of “genuine and material unresolved issues of fact” relating to Aet-na’s estoppel defense, Id. at 980, and that Aetna should be granted leave to amend its answer to include the added affirmative defense prior to trial. Id. at 983. The panel also instructed the district court that attorney’s fees were not recoverable in this action, since such an award would create an inappropriate exception to the American Rule that each party bear its own litigation costs. Id. at 984.

On remand, the case was ultimately tried to a jury. At the beginning of the charge conference, the district court stated its intention to submit the issues framed in the Pretrial Stipulation as tried to the jury for its resolution pursuant to appropriate instructions and a special interrogatory form of verdict. With regard to Aetna’s estop-pel defense, the court originally proposed the following basic elements of proof: (1) that the plaintiff was negligent in issuing the partial releases of lien to Allied (the subcontractor); (2) that Grubbs, as the general contractor, relied upon the partial releases of lien; and (3) that Grubbs was damaged as a result of its reliance (or would be damaged if it or its surety should now be required to pay the plaintiffs claim), Subsequently, however,.the court decided to modify the second element of the estoppel instruction so that the jury would have to find that Grubbs “was misled by and reasonably relied upon (that is, was not itself negligent in relying upon) the partial releases of lien.” (R3-97) (emphasis supplied)..

The addition of the highlighted language was an apparent attempt by the district court to accommodate language in Krupp I which seemed to suggest that some balancing of the relative negligence' of the parties was necessary to the jury’s estoppel determination.4 In interpreting Krupp I, the district court opined that the panel’s [1524]*1524discussion of estoppel did not intend “to borrow the tort concept of comparative negligence and apply it in a commercial transaction context” (although the court also acknowledged that it was “something less than clear”): “Rather, it seems to me, they were simply speaking in terms of the concept or defense of estoppel as it might relate to the facts of this case. At least that’s the way I interpret it and the way that I intend; to try and submit the case to the jury.” (R7-12-13). Nevertheless, the court sought to build the negligence terminology of Krupp I into its jury estoppel instruction and Special Verdict form so that “if I am wrong in my interpretation of the opinion and the submission of these issues to the jury it might be possible for the Court of Appeals to render, without necessity of a retrial.” (R7-14).5

The reason all of that, frankly, doesn’t make a lot of sense to me is because in the law of estoppel itself it seems to me that issue would be subsumed in the determination as to whether Grubbs reasonably relied — that is to say, whether Grubbs was negligent, and, if it was to any extent, then there's no estoppel.

After deliberations, the jury returned an initial verdict. There was confusion, however, regarding the jury’s responses to the questions set forth in the Special Verdict form.6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
923 F.2d 1521, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-krupp-steel-products-inc-v-aetna-insurance-ca11-1991.