Seaboard Surety Co. v. Standard Accident Insurance

14 N.E.2d 778, 277 N.Y. 429, 117 A.L.R. 658, 1938 N.Y. LEXIS 1000
CourtNew York Court of Appeals
DecidedApril 12, 1938
StatusPublished
Cited by17 cases

This text of 14 N.E.2d 778 (Seaboard Surety Co. v. Standard Accident Insurance) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seaboard Surety Co. v. Standard Accident Insurance, 14 N.E.2d 778, 277 N.Y. 429, 117 A.L.R. 658, 1938 N.Y. LEXIS 1000 (N.Y. 1938).

Opinion

Finch, J.

Whether the surety of a subcontractor is liable on its bond to the general contractor for an unpaid bill for materials incorporated in the work under the subcontract made with a general contractor doing building work for the United States government where the subcontractor has failed to complete the work or pay for the material furnished, is the question of law presented.

A motion by defendant for judgment on the pleadings was granted, and the Appellate Division has affirmed.

The relevant allegations of the complaint are as follows: One Lundberg entered into a contract with the United States of America to remodel a postoffice and courthouse in *432 Butte, Montana. Simultaneously with entering into this contract, Lundberg executed a bond conditioned upon his performance of the contract in accordance with its terms and providing that he would pay promptly all persons supplying labor and materials. This bond, obtained from the plaintiff, was required by the provisions of the Hurd Act (U. S. Code, tit. 40, § 270). Thereafter Lundberg entered into a subcontract for a portion of the work and materials with the Interstate Heating and Plumbing Company. This subcontract provided, among other things, that Interstate shall and will provide all the materials and perform all the work for the plumbing, sanitary and roof drainage, heating apparatus, and ventilating in the present postoffice in Butte, Montana, and the addition thereto.” The defendant herein, by its written bond, guaranteed to indemnify Lundberg in a sum not exceeding $14,000 against loss or damage directly caused by the failure of the principal [Interstate Heating and Plumbing Company] to faithfully perform ” this subcontract.

Lundberg was unable to carry the work to completion and the plaintiff undertook and did complete the work in accordance with the contract. After the plaintiff undertook performance, the Interstate agreed to continue the performance of its subcontract under the direction of the plaintiff as general contractor, and the defendant, as surety for the Interstate, acknowledged the right of subrogation of the plaintiff in the bond, and acknowledged it as successor obligee thereunder. Interstate failed to complete the work under its subcontract. At the time there were unpaid material bills which had been incurred by Interstate amounting to approximately $6,700, and the plaintiff had in its hands moneys owing to Interstate under the subcontract totaling approximately $7,700. The cost of completion of the subcontract after the default by Interstate was approximately $5,500. Thus the net loss to the plaintiff was approximately $4,500.

*433 The Hurd Act requires any person contracting to do public work for the United States to execute a bond not only for completion but also conditioned on prompt payment of all persons supplying labor and materials in the prosecution of the work. It has been held that a materialman may recover on the bond of the general contractor, even though he supplied material to the subcontractor and even though the subcontractor has already been paid in full. (Hill v. American Surety Co., 200 U. S. 197; Mankin v. Ludowici-Celadon Co., 215 U. S. 533. See Illinois Surety Co. v. Davis Co., 244 U. S. 376, 380.) Where the general contractor fails to furnish such a bond the laborers and materialmen who supply the subcontractors may sue the general contractor and recover from him. (Strong v. American Fence Constr. Co., 245 N. Y. 48.)

The plaintiff was bound to pay all unpaid claims for labor and material supplied to its contractor, the Interstate Company. Not only had it undertaken by its bond to pay all such claims, but it had stepped into the shoes of the general contractor; and, as noted above, a general contractor is bound to pay such claims. Therefore, when the Interstate defaulted on its contract, and the unpaid bills for materials were paid by the plaintiff, these bills were paid not as a voluntary act but by compulsion of law. The defendant, by the express terms of its bond, undertook to indemnify the plaintiff against loss or damage directly caused by the failure of the principal to faithfully perform said contract * * When the principal, the Interstate Company, defaulted on the contract, the breach caused loss to the plaintiff arising out of the necessity for completing the work and the necessity for paying for the materials already incorporated in the work, for which the Interstate had failed to make payment.

The failure to pay for material incorporated in the work after the subcontractor had undertaken to provide all the materials constituted a breach of the contract with the *434 general contractor. A contract as in the case at bar which requires the contractor to provide material, under any reasonable construction means that he will pay for the material, and a bond which undertakes to guarantee the faithful performance of such a contract includes within its scope losses suffered because of the failure of the contractor or subcontractor to pay for materials furnished. (Pacific States Elec. Co. v. United States Fidelity & Guaranty Co., 109 Cal. App. 691; Empire State Surety Co. v.Lindenmeier, 54 Col. 497; Closson v. Billman, 161 Ind. 610; Mayes v. Lane, 116 Ky. 566; Stoddard v. Hibbler, 156 Mich. 335; Cockrill v. Davie, 14 Mont. 131; Kiewit v. Carter, 25 Neb. 460; Boone v. Maloney, 171 Okla. 454; Friend v. Ralston, 35 Wash. 422.)

A different situation exists where the person in whose favor the bond runs is under no obligation to pay the materialmen and they cannot obtain a lien on his property. That was the case in Schwartz & Co. v. Aimwell Co. (227 N. Y. 184, 187) where this court said: “ It has not paid any of them and is not personally liable for their payment. As, indicated, no mechanics’ liens have been filed, nor are any threatened. Under such circumstances, the plaintiff could not voluntarily pay such claims and then recover the amount paid from the principal or surety on the bond.” To enable it to do that, as stated in Village of Argyle v. Plunkett (226 N. Y. 306), there must “be involved somewhere, as an essential element of its right to recover, damages which have been or may be suffered by it by reason of the failure to pay these debts, and such an element is in our opinion utterly lacking ” (p. 312). In the case at bar that element is present. The plaintiff was under legal obligation to pay these materialmen.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S. A. Lindstrom Co. v. Pennsylvania National Mutual Casualty Insurance Co.
1 Pa. D. & C.4th 73 (Dauphin County Court of Common Pleas, 1989)
Hoiness-LaBar Insurance v. Julien Construction Co.
743 P.2d 1262 (Wyoming Supreme Court, 1987)
Continental Casualty Co. v. Hartford Accident & Indemnity Co.
243 Cal. App. 2d 565 (California Court of Appeal, 1966)
Ulpiano Casal, Inc. v. Totty Manufacturing Corp.
90 P.R. 719 (Supreme Court of Puerto Rico, 1964)
Harry F. Ortlip Co. of Pennsylvania v. Alvey Ferguson Co.
223 F. Supp. 893 (E.D. Pennsylvania, 1963)
L. G. Defelice & Son v. Globe Indemnity Co.
189 F. Supp. 455 (S.D. New York, 1960)
Weiss v. Johnson & Johnson Construction Co.
107 S.E.2d 708 (Court of Appeals of Georgia, 1959)
Moyer v. United States, for Use of Trane Co.
206 F.2d 57 (Fourth Circuit, 1953)
H. Herfurth, Jr., Inc. v. Acker
177 F.2d 38 (D.C. Circuit, 1949)
Citizens National Bank at Brownwood v. Ross Construction Co.
206 S.W.2d 593 (Texas Supreme Court, 1947)
Ross Const. Co. v. Citizens Nat. Bank at Brownwood
201 S.W.2d 244 (Court of Appeals of Texas, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
14 N.E.2d 778, 277 N.Y. 429, 117 A.L.R. 658, 1938 N.Y. LEXIS 1000, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seaboard-surety-co-v-standard-accident-insurance-ny-1938.