American Casualty Company of Reading, Pennsylvania v. Brezina Construction Company, Inc.

295 F.2d 603, 1961 U.S. App. LEXIS 3311, 43 Lab. Cas. (CCH) 31,183
CourtCourt of Appeals for the Eighth Circuit
DecidedNovember 1, 1961
Docket16770_1
StatusPublished
Cited by15 cases

This text of 295 F.2d 603 (American Casualty Company of Reading, Pennsylvania v. Brezina Construction Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Casualty Company of Reading, Pennsylvania v. Brezina Construction Company, Inc., 295 F.2d 603, 1961 U.S. App. LEXIS 3311, 43 Lab. Cas. (CCH) 31,183 (8th Cir. 1961).

Opinion

*604 MATTHES, Circuit Judge.

This appeal is from the judgment on a cross-claim in a proceeding instituted under and pursuant to the provisions of Title 40 U.S.C.A. § 270a et seq., commonly known and referred to as the Miller Act.

The case is before us on an agreed statement submitted pursuant to our Rule 10(f), 28 U.S.C.A. From this stipulation it appears that Brezina Construction Company, Inc. (Brezina) and the United States entered into a contract under which Brezina agreed to construct certain housing facilities in North Dakota and Montana. As required by the Miller Act, § 270a(l) and (2) of Title 40 U.S.C.A., Brezina furnished the Government a performance bond and a payment bond with General Insurance Company of America as surety thereon. Subsequently Brezina entered into a contract with A & A Contractors, Inc. (A & A) whereby the latter, as subcontractor, agreed to furnish and install the plumbing and heating in the housing facilities. Pertinent to the instant controversy are these provisions of the contract between Brezina and A & A:

“Section 1. The Subcontractor [A & A] agrees to furnish all material and perform all work as described in Section 2 hereof * * * in accordance with the General Conditions of the Contract between the Owner [United States] and the Contractor and in accordance with Supplementary General Conditions, the drawings and the Specifications prepared by * * *, all of which General Conditions, * * *, form a part of a Contract between the Contractor and the Owner dated, 4 August 1958, and hereby become a part of this Contract.
“Section 2. The Subcontractor and the Contractor agree that the materials to be furnished and work to be done by the Subcontractor are
* * * * * *
“Section 5. * * *
“The Subcontractor agrees—
“(a) To be bound to the Contractor by the terms, of the Agreement, General Conditions of the Contract, the Supplementary General Conditions, * * *, and to assume toward him all the obligations and responsibilities that he, by those documents, assumes toward the Owner.
•x- * * * * *
“Section 6.
“The Subcontractor is to furnish a Bond in the full amount of the Contract. * *

A & A, as principal, and American Casualty Company (American), as surety, furnished the bond which is the subject of this controversy, whereby they became obligated and bound unto Brezina, as obligee, in the amount of $84,924. 1 The bond furnished by A & A and American, so far as here relevant, provides:

“Whereas the said Principal [A & A] has entered into a written contract with said Obligee * * * for Plumbing and Heating, A C & W Station Family Housing for United States * * *, a copy of which is or may be attached hereto, is by reference made a part hereof, and is hereafter referred to as the Contract.
“Now, Therefore, the Condition of This Obligation Is Such that if the said principal shall conform and comply with the terms and conditions of the contract hereinbefore described, on the part of said Principal to be performed and complied with, then this obligation shall be void, otherwise to be and remain in full force and effect.”

A & A failed to pay for materials supplied by Lennox Industries and this action was instituted against A & A, Brezina, American and General Insurance Company of America. Brezina thereafter filed a cross-claim against A & A and American praying that it be awarded *605 judgment against them in such sum as the court found Lennox was entitled to recover from Brezina. Judgment was entered in favor of Lennox against A & A, Brezina, and its surety, and in favor of Brezina and against A & A, and its surety, American, on Brezina’s cross-claim for $28,328.21 and this appeal was timely perfected and prosecuted by American.

The sole and- narrow issue for determination is whether the bond of appellant American Casualty Company indemnified Brezina for any amount which it as prime contractor was required to pay because of A & A’s defalcation, that is, its failure to pay for materials furnished to it by third persons. In resolving this issue, the trial court in a memorandum opinion (not officially published) stated: “ * * * I conclude that the surety required and contemplated by the subcontract (which is by reference made a part of the bond required under Section 6 thereof), executed pursuant to the provisions of the Miller Act is, in the sense it has been referred to herein, a ‘pay bond’ in that payment for materials used in the completion of the contract is one of the things which must be ‘performed,’ as that term has been used.”

Succinctly stated, appellant’s position is that we are dealing with a “performance” bond which imposed no obligation upon appellant as surety thereon unless A & A failed to “perform and comply” with the terms and conditions of the subcontract; that inasmuch as the subcontract does not in express and explicit language require A & A to pay for materials furnished it and used in the project, the contractual obligation to perform cannot be extended by implication to mean an obligation to pay, and that this is so even though the subcontract did require the subcontractor to “furnish” the materials. It is urged that such a holding is compelled by U. S. for Use of W. B. Young Supply Co. v. Stewart, et al., 8 Cir., 1923, 288 F. 187, certiorari denied 263 U.S. 699, 44 S.Ct. 5, 68 L.Ed. 513, and Crow & Crow, Inc. v. Saint Paul-Mercury Indemnity Co., 247 Minn. 426, 77 N.W.2d 429.

We recognize that in the foregoing cases the court used language which standing alone supports the argument that a contractual obligation to “furnish” materials does not in law constitute an obligation to pay for the same. But when such statements are considered, as they must be, in light of the facts and circumstances presented, it becomes apparent that the cases are distinguishable as to material matters, and thus do not constitute controlling authority for resolution of the issue here presented.

U. S. v. Stewart et ah, supra, was an action on a contractor’s bond brought against the contractor and his personal sureties for the benefit of a materialman and to recover for materials furnished the contractor. 2 The bond was conditioned on the contractor fully observing and performing all the conditions of the contract executed by Stewart, the contractor. 3 The Court followed our earlier opinion in Babcock & Wilcox et al. v. American Surety Co., 8 Cir., 236 F. 340, decided September 4, 1916, and reannounced the rule that “(a)n obligation to furnish is not an obligation to pay for material that will be furnished.” 288 F. at p. 189.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A & P Sheet Metal Co., Inc. v. Edward Hansen, Inc.
357 A.2d 37 (New Jersey Superior Court App Division, 1976)
United States ex rel. Warren v. Kimrey
358 F. Supp. 1404 (E.D. Arkansas, 1973)
Watkins Products Incorporated v. Anhorn
193 N.W.2d 228 (North Dakota Supreme Court, 1971)
Triangle Electric Supply Co. v. Mojave Electric Co.
234 F. Supp. 293 (W.D. Missouri, 1964)
United States v. Kalady Construction Co.
227 F. Supp. 1017 (N.D. Illinois, 1964)
Home Indemnity Company v. Donovan Painting Co.
325 F.2d 870 (Eighth Circuit, 1963)
Home Indemnity Co. v. F. H. Donovan Painting Co.
325 F.2d 870 (Eighth Circuit, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
295 F.2d 603, 1961 U.S. App. LEXIS 3311, 43 Lab. Cas. (CCH) 31,183, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-casualty-company-of-reading-pennsylvania-v-brezina-construction-ca8-1961.