Triangle Electric Supply Co. v. Mojave Electric Co.

234 F. Supp. 293, 1964 U.S. Dist. LEXIS 7989
CourtDistrict Court, W.D. Missouri
DecidedOctober 5, 1964
DocketNos. 12904, 13232
StatusPublished
Cited by9 cases

This text of 234 F. Supp. 293 (Triangle Electric Supply Co. v. Mojave Electric Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triangle Electric Supply Co. v. Mojave Electric Co., 234 F. Supp. 293, 1964 U.S. Dist. LEXIS 7989 (W.D. Mo. 1964).

Opinion

JOHN W. OLIVER, District Judge.

The cross-claim of defendant D & L Construction Company and Associates, the prime contractor on the Fort Leonard Wood Capehart job, against National Union Fire Insurance Company, the surety on the payment and performance bonds of the defaulted subcontractor, Mojave Electric Company, has been submitted for final decision pursuant to an amended final pre-trial order, the testimony adduced at the hearing, and the parties’ stipulation designating the record. That stipulation designates and identifies the various exhibits, pleadings, discovery items, earlier pre-trial orders, depositions, and the transcript of evidence adduced at the hearing held in our Southern Division at Springfield.1

Earlier in this case, D & L filed a motion for summary judgment on its cross-claim. Although a great mass of documentary evidence was not questioned by National Union, we refused to rule this case on that motion because of National Union’s representation that many of the facts were in dispute.

Subsequent proceedings, however, including the hearing at which two witnesses testified, revealed that the areas of factual dispute are indeed narrow and that the controversies between the parties revolve around questions of law and the inferences that should or should not be drawn from what are, for the most part, the undisputed facts.

FINDINGS OF FACT

In order to place the legal questions in perspective, we make the following findings of fact: 2

1. The original plaintiff, Triangle Electric Supply Company, Inc., is a Texas corporation having its principal place of business in such state. Defendant National Union Fire Insurance Company of Pittsburgh, Penn, (herein sometimes referred to as “National Union”), is a Pennsylvania corporation with its principal place of business in that state. The defendant-crossclaimant D & L Construction Co. and Associates (herein sometimes referred to as simply D & L) is a joint venture composed of D & L Construction Company, a California corporation, and several individuals also residents of California. There is thus complete diversity in the citizenship of the parties. The matter in controversy exceeds $10,000 exclusive of interest and costs.

2. On August 18, 1959, D & L entered into a contract (the “Prime Contract”) whereby it undertook, under authority of the legislation commonly referred to as the “Capehart Act” (42 U.S.C. § 1594 if.), the construction of 700 residential housing units at Fort Leonard Wood, Missouri, for a lump sum price of approximately eleven million dollars.

3. The electrical work required by the prime contract was thereafter subcontracted to Mojave Electric Company by separate written subcontracts, one requiring the performance of all the exterior electrical work for a lump sum price of $200,000.00; a second, the interior electrical work, for a price of $330,000.00.

[296]*2964. As required by such subcontracts, Mojave, as principal, and National Union, as surety, executed and delivered to D & L the following four bonds:

(a) A “payment bond” relating to the exterior electrical work in a face amount of $200,000.00;
(b) A “payment bond” relating to the interior electrical work in the face amount of $330,000.00;
(c) A “performance bond” relating to the exterior electrical work in the face amount of $200,000.00;
(d) A “performance bond” relating to the interior electrical work in the amount of $330,000.00.

5. The two payment bonds were each conditioned solely upon the prompt payment by Mojave of all labor and material used in the prosecution of the work of the respective subcontracts.

6. Such condition of each of these bonds was at least prior to April 1, 1960, breached by the failure of Mojave to promptly pay for material furnished and labor supplied or performed in the prosecution of the work of the respective subcontracts.

7. The two performance bonds were each conditioned solely upon the faithful performance by Mojave of all of the terms and conditions of the respective subcontracts.

8. By March 28, 1960, Mojave had done nothing toward the performance of either of the subcontracts, other than order, receive and store materials on the job site.

9. On March 28, 1960, D & L notified Mojave and National Union that Mojave was “not maintaining satisfactory progress” as required by the provisions of paragraph four of the subcontracts and that unless satisfactory progress was resumed by March 31, D & L would proceed to avail itself of the remedies provided by said paragraph; i. e., that it would relet the work of the subcontracts and charge the costs of completion to Mojave and National Union. On April 4, 1960, D & L requested National to proceed with the defaulted work in accordance with Paragraph 4(a); but National elected not so to do.

D & L’s proposed findings in paragraphs 10 to 22, respectively, relate to the extent of damages. D & L requests that we find that D & L was damaged $78,219.71, as a result of the breach of the exterior payment bond, and $28,479.-41, as a result of the breach of the interior payment bond. In regard to the exterior performance bond, D & L requested a finding that more than the $200,000.00 face amount was spent to complete Mojave’s defaulted subcontract, and a finding for reasonable attorney’s fees in the amount of $10,000.00, together with interest.

In regard to the interior performance bond, D & L requested a finding that $318,402.00 was spent to complete the defaulted Mojave subcontract, and that interest and a reasonable attorney’s fee of $15,000.00 should also be allowed.

The various pre-trial stipulations and pre-trial orders have dealt with the actual dollars involved in particular categories of damage. The proposed findings of the parties in regard to particular amounts show a large area of agreement as to particular amounts but they also show some disagreement in regard to other particular amounts.

National Union has noted of record that its requested finding of fact F-39 was limited “to the amounts potentially involved in various items of damages sought by D & L in the event the Court should hold in its favor” and that “no findings were requested as to the total amount of final judgment. * * * because of the great number of unresolved legal issues bearing on the recovery and amount of various categories of damages.”

National Union also suggested in that letter, and we think it a good suggestion, that we should “allow the parties to consult with each other as to the amount of the judgment, if any, after the Court has made its decision on the various issues raised by the requested Findings, of Fact and Conclusions of Law.”

[297]*297In our order at the end of this Memorandum Opinion we shall direct further proceedings consistent with that thought. We shall not, therefore, either accept or reject any of the specific requests of the parties that include particular dollar amounts as included, for example, in paragraphs 10 through 22, inclusive, of D & L’s requested findings.

In regard to the affirmative defenses asserted by National Union we make the following findings of facts:3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
234 F. Supp. 293, 1964 U.S. Dist. LEXIS 7989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/triangle-electric-supply-co-v-mojave-electric-co-mowd-1964.