Triangle Electric Supply Co. v. Mojave Electric Co.

238 F. Supp. 815, 1965 U.S. Dist. LEXIS 6823
CourtDistrict Court, W.D. Missouri
DecidedFebruary 26, 1965
DocketNos. 12904, 13232
StatusPublished
Cited by5 cases

This text of 238 F. Supp. 815 (Triangle Electric Supply Co. v. Mojave Electric Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triangle Electric Supply Co. v. Mojave Electric Co., 238 F. Supp. 815, 1965 U.S. Dist. LEXIS 6823 (W.D. Mo. 1965).

Opinion

JOHN W. OLIVER, District Judge.

In our memorandum opinion of October 5, 1964, now reported as Triangle Electric Supply Company v. Mojave Electric Company, W.D.Mo., 1964, 234 F. Supp. 293, we noted that at the time of the original submission of this branch of the case National Union suggested that various questions relating to the amount of damages be reserved in order to “ 'allow the parties to consult with each other as to the amount of judgment, if any, after the Court has made its decision on the various issues raised by the requested Findings of Fact and Conclusions of Law’ ” as initially presented by the parties, (page 296 of 234 F.Supp). In accordance with that suggestion we did not rule specifically on the items of damage concerning attorneys’ fees, pre-judgment interest, and other particular items of damages (page 316 of 234 F.Supp.).

Our order of October 5, 1964, therefore directed counsel for D & L to prepare a final order and to submit the same to counsel for National Union for approval. The parties, however, were unable to agree. We then directed the submission of additional suggested findings and conclusions, together with supporting briefs. We have studied those briefs and shall make additional findings and state additional conclusions in order that final judgment may be entered.

The latest briefs of the parties reveal that particular questions formerly in contest are no longer contested. We therefore note at the outset that “National Union concurs with D & L in its statement (Br. p. 2) that the legal principle applicable to the issues now remaining for decision will be the same no matter whether Missouri, California, or federal law is held to be controlling” (page 1 of National Union’s Supplemental Suggestions). National Union also agrees that, on the facts, the bond limitations of both the exterior and interior bonds are exceeded by items of damage as to which no [817]*817dispute remains (page 2 of National Union’s Supplemental Suggestions).

The area of conflict between the parties’ present positions relates to the questions of whether attorneys’ fees and pre-judgment interest may be included in the judgment in excess of the amount of the bonds involved. National Union contends generally that neither item of damage may be allowed because to do so jvould exceed the $200,000 provided in the exterior bond, and the $330,000 provided in the interior bond. National Union also argues that pre-judgment interest may not be recovered in any event because the damages were not “liquidated;” because no demand was made on the surety; and because, as already stated, the sums provided in the bonds have already been exhausted by the allowance of other items of damage.

National Union’s factual assertion that no demand was ever made by D & L can not be sustained in light of paragraph 29(1) of the amended pre-trial order which stipulated that “due notice of said defaults by Mojave was given National by D & L and due demand was made that National assume the duties of Mojave under said subcontracts.” That paragraph of the amended pre-trial order adds that “National refused to comply with said demand, however, claiming that it had been released from its obligations under said performance and payment bonds by virtue of the actions of D & L and Mojave above described.”

There is no question but that the demand referred to in that agreed statement was made on April 4, 1960. Hence the basic question for decision reduces itself to the question of whether attorneys’ fees and pre-judgment interest may be allowed as elements of damage over and above the amounts specified in the bonds.

We deal first with the question of attorneys’ fees. In our memorandum of October 4, 1964, we noted that the situation presented by this branch of the case in regard to attorneys’ fees and pre-judgment interest was a bit different than the narrow question we ruled on summary judgment on the first branch of this case on June 30, 1963, now reported as Triangle Electric Supply Co. v. Mojave Electric Co., W.D.Mo.1963, 217 F.Supp. 913.

Our memorandum opinion of June 20, 1963 did not reach or rule the question of whether attorneys’ fees and pre-judgment interest might be recovered in a case where no agreement existed between the parties in regard to those particular items (page 914 of 217 F.Supp.). We did, however, hold that Illinois Surety Co. v. John Davis Co., 244 U.S. 376, 37 S.Ct. 614, 61 L.Ed. 1206 (1917), was a case that we would follow, in addition to United States for the Benefit and on Behalf of Sherman v. Carter, 353 U.S. 210, 77 S.Ct. 793, 1 L.Ed.2d 776 (1957).

The Court of Appeals, in affirming our order of June 20, 1963, agreed that Carter controlled the factual situation where the contract made express provision for the allowance of attorneys’ fees and interest. While the Court of Appeals limited its holding to that particular factual situation, as we had, it nevertheless helpfully stated that “where there is no express contract for interest or attorneys’ fees, it is necessary to look to state law to measure the extent of the subcontractor’s obligation” (page 1013 of 332 F.2d). The Court of Appeals relied upon John Davis Co. and by footnote directed attention to cases from the 4th, 9th and 10th Circuits that had allowed interest or attorneys’ fees on the basis of state law “in situations where no express contract relating thereto existed” (see cases cited in footnote 4 on page 1013 of 332 F.2d).

The factual situation in regard to attorneys’ fees and the factual situation in regard to pre-judgment interest on this branch of the case are different. In regard to attorneys’ fees, Paragraph 36 of Exhibit D expressly provided that “in the event Contractor [¶] & L] engages the services of any attorneys for any action brought by either party on or under this contract, or by either party for its enforcement or in defending any action brought against the Contractor due to the fault of this Subcontractor, the Subcontractor agrees to pay reasonable at[818]*818torneys’ fees to the Contractor.” That paragraph also provided that the “Subcontractor agrees to hold the Contractor harmless by reason of any damages incurred by Subcontractor through the fault of the Subcontractor to fully and efficiently perform his contract and pay such costs, expenses, damages and/or attorneys’ fees which Contractor may incur by reason of failure of Subcontractor to fully and completely perform hereunder.” No such agreement existed in regard to the payment of pre-judgment interest.

The basic rationale of our memorandum opinion of October 5, 1964, and our application of the rule of decision of our controlling court in American Casualty Co. of Reading, Pa. v. Brezina Const. Co., 8th Cir. 1961, 295 F.2d 603, requires that we now hold that the express contractual agreement covering attorneys’ fees places that item of damage in the same category as the attorneys’ fees involved in our memorandum opinion of June 20, 1963, and that inquiry into state law is unnecessary.

The parties are in agreement as to the amount of fees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
238 F. Supp. 815, 1965 U.S. Dist. LEXIS 6823, Counsel Stack Legal Research, https://law.counselstack.com/opinion/triangle-electric-supply-co-v-mojave-electric-co-mowd-1965.