D & L Construction Company v. Triangle Electric Supply Company, Inc.

332 F.2d 1009, 1964 U.S. App. LEXIS 4971
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 22, 1964
Docket17493_1
StatusPublished
Cited by40 cases

This text of 332 F.2d 1009 (D & L Construction Company v. Triangle Electric Supply Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D & L Construction Company v. Triangle Electric Supply Company, Inc., 332 F.2d 1009, 1964 U.S. App. LEXIS 4971 (8th Cir. 1964).

Opinion

VAN OOSTERHOUT, Circuit Judge.

The issue presented by this appeal taken by defendants D & L Construction Company and its associates and Continental Casualty Company, its performance bond surety, is whether the trial court properly allowed plaintiff Triangle Electric Supply Company, Inc., interest and attorneys’ fees upon its claim for materials furnished Mojave Electric Company, Inc., a subcontractor upon a Cape-hart Housing Project upon which D & L was prime contractor.

Through pleadings, discovery proceedings, stipulations and pretrial conferences, the parties ultimately agreed that the reasonable value of electrical equipment furnished by Triangle to the subcontractor and used on the project is $14,592.12. Triangle’s right to judgment for such amount is not questioned. The parties stipulated in regard to their respective claims and the questions for decision as follows:

“(a) If plaintiff Triangle is entitled to interest, said interest shall run from date of plaintiff’s demand letter of March 28, 1960 to the defendants D & L and Continental, and such interest shall be calculated at the rate of six per cent per annum. * * * Defendants deny that interest is allowable on an award on such bond. This is an issue of law to be determined by the Court.
*1011 “(b) Plaintiff claims that if a recovery is allowed it for the principal amount of its claim under the payment bond in question, it is also entitled to an allowance for attorneys’ fees. Defendants deny that any attorneys’ fees can be awarded in connection with a recovery on the bonds in question. This is an issue of law to be determined by the Court.”

The court sustained Triangle’s motion for summary judgment and entered judgment for Triangle against D & L and its surety for $14,592.12 principal, $2,924.07 interest and $6,000 attorneys’ fees. 1 This appeal is from such judgment. 2

Defendants’ statement of points relied upon for reversal reads:

“The Court below erred in including in its summary judgment as a matter of ‘Federal Law’ under ‘Rules of Decision Developed under the Heard and Miller Act Decisions’ sums representing awards to this plaintiff of pre-judgment interest and attorneys’ fees in that:
“a. The rules of decision developed under the Miller and Heard Acts are not applicable to Capehart bond suits.
“b. Even under the decisions interpreting the Miller and Heard Acts, there is no ‘Federal Law’ entitling a claimant to pre-judgment interest or attorneys’ fees.”

Plaintiff’s answer to point “a” is that, for the purpose of solving the issues here presented, it is immaterial whether the Capehart Housing Project provisions are sui generis and that all provisions of the Miller Act may not apply to Capehart Housing. We agree. Continental Cas. Co. v. United States for the Use and Benefit of Robertson Lumber Co., 8 Cir., 305 F.2d 794, relied upon by defendants, has no direct bearing upon the problem we are here considering. There we held that 42 U.S.C.A. § 1594a gave the Secretary of Defense the right to prescribe the form of bond to be furnished on Capehart Projects and that when the bond prescribed and given contained more stringent provisions as to notice to be given than the Miller Act, the procedural provisions of the Capehart bond must be followed. We said nothing about the Miller Act decisions lacking persuasiveness in instances where the Miller Act bond and Capehart bond contained substantially similar provisions. We recognized that the Capehart bond is a bond required by federal law and stated that Congress intended that Capehart should have substantive bond protection essentially similar to that of Miller Act suppliers.

Plaintiff’s position is that, to the extent here material, the Capehart bond as prescribed by the Secretary of Defense pursuant to 42 U.S.C.A. § 1594a and given by the prime contractor is in substance the same as that required on Miller Act projects by 40 U.S.C.A. § 270b. The pertinent provisions of the bond here in suit are:

“ * * * every claimant * * * who has not been paid in full before the expiration of a period of ninety (90) days after the date on which the last of such claimant’s work or labor was done or performed or materials furnished by such claimant * * * may sue on this bond * * in the name of the claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon * *

The Miller Act, as shown by 40 U.S. C.A. § 270b (a) similarly provides bond *1012 coverage for persons furnishing labor or materials “for the sum or sums justly due him.”

It reasonably appears that the drafters of the Capehart bond adopted the Miller Act phraseology in the respects here material. Miller Act bonds and Capehart bonds are bonds required by federal law. Each of such bonds are designed to serve substantially the same purpose, that is, to protect parties furnishing labor and material used on federally sponsored projects. Upon the record before us, we believe that the trial court properly determined that “the rules of decision that will be applied to the factual situations involved in the various cases will be the rules of decision developed under the Heard and Miller Act decisions.” 3 217 F.Supp. 913, 914.

Defendants urge that in any event there are no decisions under the Heard and Miller Act which allow for recovery of pre-judgment interest or attorneys’ fees. The bond here in suit clearly permits Triangle to recover sums justly due for material and labor furnished on the project. What is included in the term “justly due” may vary with the facts and circumstances of individual cases. If labor and material is furnished under express contract, the contract will ordinarily measure the sum justly due. Here the court, upon the basis of undisputed evidence, found :

“All of the invoices of plaintiff Triangle to Mojave for materials here involved contain the following provision:
“ ‘All past due invoices bear interest at the rate of 6% per annum. Should it become necessary to place this or any subsequent invoice in the hands of an attorney for collection, reasonable attorneys’ fees shall be added.’
“Said provision expresses Triangle’s usual and normal terms of sale and constitute a part of the contract of purchase and sale between plaintiff Triangle and Mojave Electric Company.” 217 F.Supp. 913, 914.

The validity of the court’s determination that the contract between Triangle and the subcontractor provided for 6% interest on past due invoices and a reasonable attorneys’ fee in event of suit is in no way challenged. With respect to interest, the parties have agreed as to the amount of interest due in the event interest is allowable. The judgment for interest is based upon such agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Solsbury Hill v. Liberty Mut.
2012 NMCA 032 (New Mexico Court of Appeals, 2012)
State ex rel Solsbury Hill, LLC v. Liberty Mut. Ins. Co.
2012 NMCA 32 (New Mexico Court of Appeals, 2011)
Shaw Industries, Inc. v. Community College District No. 515
741 N.E.2d 642 (Appellate Court of Illinois, 2000)
GE Supply v. C & G Enterprises, Inc.
212 F.3d 14 (First Circuit, 2000)
United States v. St. Paul Fire & Marine Insurance
86 F.3d 332 (Fourth Circuit, 1996)
TransAmerica Premier Insurance v. Ober
894 F. Supp. 471 (D. Maine, 1995)
Allied Building Products Corp. v. United Pacific Insurance
549 A.2d 1163 (Court of Special Appeals of Maryland, 1988)
US, ETC. v. EJT Constr. Co., Inc.
517 F. Supp. 1178 (E.D. Pennsylvania, 1981)
Clow Corp. v. Metro Pipeline Co., Inc.
442 F. Supp. 583 (N.D. Georgia, 1977)
Boliver v. Surety Co.
72 Cal. App. Supp. 3d 22 (Appellate Division of the Superior Court of California, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
332 F.2d 1009, 1964 U.S. App. LEXIS 4971, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-l-construction-company-v-triangle-electric-supply-company-inc-ca8-1964.