US, ETC. v. EJT Constr. Co., Inc.

517 F. Supp. 1178
CourtDistrict Court, E.D. Pennsylvania
DecidedJuly 9, 1981
DocketCiv. A. Nos. 78-528, 78-4032 and 79-1024
StatusPublished
Cited by3 cases

This text of 517 F. Supp. 1178 (US, ETC. v. EJT Constr. Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
US, ETC. v. EJT Constr. Co., Inc., 517 F. Supp. 1178 (E.D. Pa. 1981).

Opinion

517 F.Supp. 1178 (1981)

UNITED STATES of America For the Use of BILLOWS ELECTRIC SUPPLY COMPANY, INC.
v.
E. J. T. CONSTRUCTION CO., INC., National Fire Insurance Company of Hartford, American Casualty Company of Reading and B. D. Thomas Company.

Civ. A. Nos. 78-528, 78-4032 and 79-1024.

United States District Court, E. D. Pennsylvania.

July 9, 1981.

*1179 Howard J. Creskoff, Adler, Barish, Levin & Creskoff, Philadelphia, Pa., for plaintiff.

Charles I. Richman, Richman, Romisher, Cook & Phillips, Philadelphia, Pa., George F. Gardner, III, Morris, Nichols, Arsht & Tunnell, Dover, Del., for defendants E.J.T. Const. Co., Inc., American Cas. Co. of Reading and Nat. Fire Ins. Co. of Hartford.

MEMORANDUM

RAYMOND J. BRODERICK, District Judge.

These actions, which arose under the Miller Act, 40 U.S.C.A. § 270a, et seq., were tried together before the Court, sitting without a jury, on April 20 and April 21, 1981. The defendants E.J.T. Construction Company, Inc. (the General Contractor), National Fire Insurance Company of Hartford (National), and American Casualty Company of Reading (American) were represented by the same counsel. Prior to the commencement of trial, defendant B. D. Thomas Company (the Subcontractor) settled with the plaintiff Billows Electric Supply Company, Inc. (the Materialman) and the other defendants. The issues to be decided by the Court are whether the Materialman complied with the notice provisions of the Miller Act, 40 U.S.C.A. § 270b, and if so, whether the Materialman is entitled to recover the unpaid balance for any or all of the materials it supplied to the Subcontractor, together with service charges on the unpaid balance.

At trial the parties stipulated that on or about June 26, 1975, the United States of America, acting through the Department of the Navy, Naval Facilities Engineering Command (Navy), and the General Contractor entered into a written contract whereby the General Contractor agreed to furnish all of the labor and material and perform all work required for the construction of a project known as the aircraft maintenance hangar and parking apron at the Naval Air Station, Willow Grove, Pennsylvania. The original contract was for the sum of $6,087,768.00. On or about June 26, 1975, the General Contractor as principal and National and American as sureties executed a payment bond and performance bond to the United States of America in reference to said project. These bonds were duly accepted by the United States of America, and upon acceptance the contract for the construction of the aircraft maintenance hangar and parking apron at Willow Grove, Pennsylvania was awarded to the General Contractor. All of the labor to be performed and materials to be furnished under this contract were to be supplied within the jurisdiction of the United States District Court for the Eastern District of Pennsylvania.

The parties further stipulated that the General Contractor and the Subcontractor entered into a written agreement whereby the Subcontractor agreed to furnish certain supervision, equipment, labor and materials required for the installation of all electrical work and all associated accessories in accordance with the plans and specifications of the contract between the Navy and the General Contractor. The original contract between the General Contractor and the Subcontractor, dated August 29, 1975, was *1180 for the sum of $600,500. The Navy, however, issued a total of approximately thirteen change orders to the General Contractor for certain additional work as the contract progressed, some of which involved the Subcontractor. The Materialman supplied material ordered by the Subcontractor for this subcontract, and has not been reimbursed for some of this material.

The Subcontractor testified that the electrical subcontract required him to supply certain kinds of electrical material for the job. The Subcontractor contacted the Materialman, a supplier of electrical equipment with whom he had previously done business, to obtain price quotations for the equipment and supplies needed for the job. The Materialman orally quoted prices for the electrical supplies and equipment and stated that these prices would not be increased for 90 days. The Subcontractor incorporated these prices into his bid and subsequently bought 70-75% of these materials from the Materialman within 90 days. The Subcontractor testified that the terms of payment for these materials was 2%/10, net 30 and a service charge of 1½% per month on any unpaid balance due for more than 60 days. The Subcontractor continued to buy material from the Materialman after the 90 day period had expired, and paid approximately the same price for the materials as was quoted to him by the Materialman. The Subcontractor testified that the last order he placed with the Materialman for material for the hangar job was delivered to the job site on or about November 21, 1978. The Materialman and the Subcontractor never entered into a written contract for any of the materials purchased, and testified that this practice was customary among electrical suppliers and electrical subcontractors.

The Subcontractor made prompt payments to the Materialman for materials he ordered until sometime in late 1976, when payments began to fall in arrears. Early in 1977, the General Contractor began to pay the Subcontractor for its work by issuing monthly checks on which the Subcontractor and the Materialman were joint payees. The Subcontractor would forward these checks to the Materialman after he had endorsed them. The Subcontractor testified that in November 1977, the Materialman informed him that he would not accept any further orders from him until the outstanding balance of approximately $60,000.00 was paid.

The Materialman testified that in November 1977 he spoke directly to the General Contractor and advised him that he was not accepting any further orders for material from the Subcontractor until the balance on the Subcontractor's account was paid. Shortly thereafter, the Materialman received a check from the General Contractor in the amount of $29,528.78, to be applied to the balance due. The Materialman testified that he agreed to continue to send materials to the job site pursuant to an agreement with the General Contractor. The Materialman sent a letter to the General Contractor (Exhibit "P-2") confirming this agreement on December 1, 1977. This letter stated:

Confirming our phone conversation of today, 12-1-77, we discussed the letter dated 11-28-77.
The agreement made by yourself with me is that we get an initial payment of $29,528.78 immediately. This has been received and a payment of $10,000 every 30 days thereafter against the old balance on the B.D. Thomas account. The account now shows a balance of $30,673.85. All material shipped from here will be paid for within 30 days after delivery.
If there is anything I can do to help, please contact me immediately. I am pushing now for a better delivery on the D.C. Rectifiers.

The Materialman testified that he resumed shipments to the job site but received no further payments from the General Contractor. The Materialman introduced into evidence 141 invoices (Exhibits "Pl-1 through 1-141") for electrical supplies sent to the job site for which he claimed that payment had not been received. The earliest shipment date on these *1181 invoices is July 21, 1977, and the latest shipment date is November 21, 1978. The Materialman did not ship any material to the job site between August 1978 and November 21, 1978.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
517 F. Supp. 1178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-etc-v-ejt-constr-co-inc-paed-1981.