Clifford F. MacEvoy Co. v. United States Ex Rel. Calvin Tomkins Co.

322 U.S. 102, 64 S. Ct. 890, 88 L. Ed. 1163, 1944 U.S. LEXIS 1213
CourtSupreme Court of the United States
DecidedApril 24, 1944
Docket483
StatusPublished
Cited by465 cases

This text of 322 U.S. 102 (Clifford F. MacEvoy Co. v. United States Ex Rel. Calvin Tomkins Co.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clifford F. MacEvoy Co. v. United States Ex Rel. Calvin Tomkins Co., 322 U.S. 102, 64 S. Ct. 890, 88 L. Ed. 1163, 1944 U.S. LEXIS 1213 (1944).

Opinion

Mr. Justice Murphy

delivered the opinion of the Court.

The United States entered into a contract with the petitioner Clifford F. MacEvoy Company whereby the latter agreed to furnish the materials and to perform the work necessary for the construction of dwelling units of a Defense Housing Project near Linden, New Jersey, on a cost-plus-fixed-fee basis. Pursuant to the Miller Act, 1 MacEvoy as principal and the petitioner Aetna Casualty and Surety Company as surety executed a payment bond in the amount of $1,000,000, conditioned on the prompt payment by MacEvoy “to all persons supplying labor and material in the prosecution of the work provided for in said contract.” The bond was duly accepted by the United States.

MacEvoy thereupon purchased from James H. Miller & Company certain building materials for use in the prosecution of the work provided for in MacEvoy’s contract with the Government. Miller in turn purchased these materials from the respondent, Calvin Tomkins Company. Miller failed to pay Tomkins a balance of $12,033.49. There is no allegation that Miller agreed to perform or did perform any part of the work on the construction project. *104 Nor is it disputed that MacEvoy paid Miller in full for the materials.

Within ninety days from the date on which Tomkins furnished the last of the materials to Miller, Tomkins gave written notice to MacEvoy and the surety of the existence and amount of Tomkins’ claim for materials furnished to Miller. Tomkins as use-plaintiff then instituted this action against MacEvoy and the surety on the payment bond. The District Court granted petitioners’ motion to dismiss the complaint for failure to state a claim against them. 49 F. Supp. 81. The Circuit Court of Appeals reversed the judgment. 137 F. 2d 565. We granted certiorari because of a novel and important question presented under the Miller Act. 320 U. S. 733.

Specifically the issue is whether under the Miller Act a person supplying materials to a materialman of a Government contractor and to whom an unpaid balance is due from the materialman can recover on the payment bond executed by the contractor. We hold that he cannot.

The Heard Act, 2 which was the predecessor of the Miller Act, required Government contractors to execute penal bonds for the benefit of “all persons supplying him or them with labor and materials in the prosecution of the work provided for in such contract.” We consistently applied a liberal construction to that statute, noting that it was remedial in nature and that it clearly evidenced “the intention of Congress to protect those whose labor or material has contributed to the prosecution of the work.” United States v. American Surety Co., 200 U. S. 197, 204. See also Mankin v. United States, 215 U. S. 533; U. S. Fidelity & Guaranty Co. v. Bartlett, 231 U. S. 237; Brogan v. National Surety Co., 246 U. S. 257; Fleischmann Construction Co. v. United States, 270 U. S. 349; Standard *105 Accident Insurance Co. v. United States, 302 U. S. 442. We accordingly held that the phrase “all persons supplying [the contractor] . . . with labor and materials” included not only those furnishing labor and materials directly to the prime contractor but also covered those who contributed labor and materials to subcontractors. United States v. American Surety Co., supra, 204; Mankin v. United States, supra, 539; Illinois Surety Co. v. John Davis Co., 244 U. S. 376, 380. We had no occasion, however, to determine under that Act whether those who merely sold materials to materialmen, who in turn sold them to the prime contractors, were included within the phrase and hence entitled to recover on the penal bond. 3

The Miller Act, while it repealed the Heard Act, reinstated its basic provisions and was designed primarily to eliminate certain procedural limitations on its beneficiaries. 4 There was no expressed purpose in the legis *106 lative history to restrict in any way the coverage of the Heard Act; the intent rather was to remove the procedural difficulties found to exist under the earlier measure and thereby make it easier for unpaid creditors to realize the benefits of the bond. Section 1 (a) (2) of the Miller Act requires every Government contractor, where the amount of the contract exceeds $2,000, to furnish to the United States a payment bond with a surety “for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract for the use of each such person.” Section 2 (a) further provides that “every person who has furnished labor or material in the prosecution of the work provided for in such contract” and who has not been paid in full therefor within ninety days after the last labor was performed or material supplied may bring suit on the payment bond for the unpaid balance. A proviso then states:

“Provided, however, That any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond ppon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor *107 or furnished or supplied the last of the material for which such claim is made. . . .”

The Miller Act, like the Heard Act, is highly remedial in nature. It is entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects. Fleisher Engineering Co. v. United States, 311 U. S. 15, 17, 18; cf. United States v. Irwin, 316 U. S. 23, 29, 30. But such a salutary policy does not justify ignoring plain words of limitation and imposing wholesale liability on payment bonds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Empire Enterprises JKB, Inc. v. Union City Contractors, Inc.
660 F. Supp. 2d 492 (W.D. New York, 2009)
Tuscany, LLC v. Western States Excavating Pipe & Boring, LLC
128 P.3d 274 (Colorado Court of Appeals, 2005)
Faircloth v. Lundy Packing Co.
91 F.3d 648 (Fourth Circuit, 1996)
United States Ex Rel. Capps v. Fidelity & Deposit Co.
875 F. Supp. 803 (M.D. Alabama, 1995)
Breeden v. Catron (In Re Catron)
158 B.R. 629 (E.D. Virginia, 1993)
Mai Steel Service Inc. v. Blake Construction Co.
981 F.2d 414 (Ninth Circuit, 1992)
Bigger v. American Commercial Lines, Inc.
862 F.2d 1341 (Eighth Circuit, 1988)
Allied Building Products Corp. v. United Pacific Insurance
549 A.2d 1163 (Court of Special Appeals of Maryland, 1988)
US FOR USE OF LABORERS'PEN. TR. v. Safeco Ins.
707 F. Supp. 286 (E.D. Michigan, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
322 U.S. 102, 64 S. Ct. 890, 88 L. Ed. 1163, 1944 U.S. LEXIS 1213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clifford-f-macevoy-co-v-united-states-ex-rel-calvin-tomkins-co-scotus-1944.