Mason v. Southern Sanitation, Inc. (In Re Underground Storage Tank Technical Services Group, Inc.)

212 B.R. 574, 1997 Bankr. LEXIS 1359
CourtUnited States Bankruptcy Court, E.D. Michigan
DecidedFebruary 13, 1997
Docket19-41311
StatusPublished
Cited by3 cases

This text of 212 B.R. 574 (Mason v. Southern Sanitation, Inc. (In Re Underground Storage Tank Technical Services Group, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mason v. Southern Sanitation, Inc. (In Re Underground Storage Tank Technical Services Group, Inc.), 212 B.R. 574, 1997 Bankr. LEXIS 1359 (Mich. 1997).

Opinion

OPINION REGARDING CROSS MOTIONS FOR SUMMARY JUDGMENT

ARTHUR J. SPECTOR, Bankruptcy Judge.

INTRODUCTION

Sverdrup Environmental, Inc., entered into an agreement with the United States, pursuant to which the former was to serve as general contractor for a construction project at the Fort Campbell Military Reservation, which is located on the border between Kentucky and Tennessee. In connection with this project, Sverdrup “subcontracted” with Underground Storage Tank Technical Services Group (“UST Tech”), which in turn entered into separate subcontracts with Southern Sanitation, Inc., and Gary Dirt Co., Inc. Southern and Gary were paid for the work which they performed by means of separate checks dated May 18, 1995, in the amounts of $36,953.41 and $11,025.00, respectively. These cheeks were issued by Sverdrup and made payable jointly to UST Tech and the respective sub-subcontractor. UST Tech endorsed the cheeks and delivered each to the joint payee.

*576 Within 90 days after these payments were made, UST Tech filed for bankruptcy relief. In these adversary proceedings, the chapter 7 trustee seeks to avoid the payments received by Southern and Gary pursuant to 11 U.S.C. § 547(b). Both parties filed a motion for summary judgment in each of the cases. For the reasons which follow, these motions will be denied.

DISCUSSION

To successfully invoke § 547(b), the challenged “transfer” must be “of an interest of the debtor in property.” 11 U.S.C. § 547(b). The Plaintiff must prove that UST Tech held such an interest. See 11 U.S.C. § 547(g); see also, e.g., In re Hartley, 825 F.2d 1067, 1069 (6th Cir.1987); Brown v. First Nat’l Bank of Little Rock, 748 F.2d 490, 491 (8th Cir.1984).

The motions filed by Southern and Gary asserted that this requirement is not met, advancing several theories in support of that proposition. First and foremost among them is the Defendants’ contention that they are entitled to summary judgment based on the Sixth Circuit’s decision in In re Arnold, 908 F.2d 52 (6th Cir.1990). That case is discussed at length in an opinion entered contemporaneously herewith, involving the same Plaintiff and a different defendant. See Mason v. Zorn Industries, 212 B.R. 564, 565-567 (Bankr.E.D.Mich.1997). In Zorn, this Court concluded that “Arnold should ... be construed as holding that the third party’s independent obligation established that the transfer did not constitute a seizure of the debtor’s account receivable.” Id. at 567.

As in Zorn, the Defendants here argued that they had an “independent” right to the payment by virtue of the Miller Act, 40 U.S.C. § 270a et seq. That Act generally requires that a party entering into a construction contract with the United States “furnish ... [a] payment bond with a surety ... satisfactory to ... [the] officer [awarding the contract] for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract.” 40 U.S.C. § 270a(a)(2).

Although the Defendants contracted with UST Tech rather than Sverdrup, they nevertheless had the right to make a claim on the payment bond if UST Tech was a “subcontractor” for purposes of a proviso in the Miller Act which confers such a right on “any person having [a] direct contractual relationship with a subcontractor” of the general contractor. 40 U.S.C. § 270b(a). See MacEvoy Co. v. United States ex rel. The Calvin Tomkins Co., 322 U.S. 102, 108-11, 64 S.Ct. 890, 894-95, 88 L.Ed. 1163 (1944) (holding that a party which contracted with a “materialman” could not recover from the payment bond because a materialman is not a “subcontractor”). UST Tech apparently meets this criterion, as the trustee did not dispute that the Defendants had rights against the bond.

The trustee did argue, however, that the Defendants’ reliance on the Miller Act is misplaced because their rights thereunder are only against the bond, and not against Sverdrup. Thus the issue of Arnold’s applicability boils down to whether the Defendants would have a cause of action against Sverdrup under the Miller Act.

It could be argued that, since the Act places the onus on the general contractor to furnish the payment bond, the statute must be premised on the proposition that that party is liable to second-tier subcontractors like the Defendants. See In re Glover Constr. Co., 30 B.R. 873, 880 n. 22 (Bankr.W.D.Ky.1983) (“The underlying objective of this legislation [i.e., the Miller Act] presupposes that the contractor has a fiduciary duty towards workers associated with the project.”). Indeed, it appears that Miller Act bonds routinely subject the general contractor to liability for all claims made on the bond. See Standard Form 25A (the standard payment bond provided by the government to the general contractor of a Miller Act construction job, which states that the obligation thereunder binds the principal and surety “jointly and severally,” and that the “obligation is void if the Principal promptly makes payment to all persons having a direct relationship with the Principal or a subcontractor of the Principal” (emphasis added)); *577 MacEvoy, 322 U.S. at 103, 64 S.Ct. at 891-92 (“Pursuant to the Miller Act, MacEvoy [the general contractor] ... and ... Aetna Casualty and Surety Company ... executed a payment bond ..., conditioned on the prompt payment by MacEvoy ‘to all persons supplying labor and material in the prosecution of the work provided for in said contract.’ ” (footnote omitted)).

The view that the Act “presupposes” liability on the general contractor’s part is reinforced by a provision therein which conditions the bond rights of sub-subcontractors on the “giving [of timely] .written notice to ... [the general] contractor ... stating ... the amount claimed.” 40 U.S.C. § 270b(a). That notice would seem to be misdirected if, as the trustee suggests, the general contractor has no liability on claims filed by such parties on the bond. See J.W. Bateson Co. v. United States ex rel. Board of Trustees,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
212 B.R. 574, 1997 Bankr. LEXIS 1359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mason-v-southern-sanitation-inc-in-re-underground-storage-tank-mieb-1997.