Dubois v. Imbr Crane (In re Scott Fabricating, Inc.)

478 B.R. 901
CourtUnited States Bankruptcy Court, N.D. Indiana
DecidedSeptember 28, 2012
DocketBankruptcy No. 09-24835 JPK; Adversary No. 11-2050
StatusPublished

This text of 478 B.R. 901 (Dubois v. Imbr Crane (In re Scott Fabricating, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, N.D. Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dubois v. Imbr Crane (In re Scott Fabricating, Inc.), 478 B.R. 901 (Ind. 2012).

Opinion

MEMORANDUM OF DECISION

J. PHILIP KLINGEBERGER, Bankruptcy Judge.

This adversary proceeding was commenced on April 1, 2011, by a complaint filed by David DuBois, Trustee of the Chapter 7 bankruptcy estate of Scott Fabricating, Inc. (“Trustee”). The complaint seeks to recover for the benefit of the estate an alleged preferential transfer received by the defendant IMBR Crane (“IMBR”).

Pursuant to the court’s order entered on August 24, 2011 (record # 16), this adversary proceeding was submitted to the court on a stipulated record: the record which controls the final determination in this case was filed as record # 21 on December 27, 2011, designated as the parties “Joint Stipulation of Facts”.1 Pursuant to the court’s order, the parties have also [903]*903submitted their respective legal memoran-da.

The parties have stipulated to the court’s jurisdiction with respect to this adversary proceeding, and with respect to the court’s entry of final judgment concerning the issues raised in this adversary proceeding.2

The factual record upon which the court’s determination will be based is comprised of paragraphs 3-20 of the Joint Stipulation of Facts. The entirety of that factual record will not be set out in this Memorandum of Decision. To the extent that particular facts are relevant to the determination, those facts will be stated hereinafter.

The Trustee has brought this action pursuant to 11 U.S.C. § 547(b). Both the Trustee and IMBR have focused upon one specific element of that statute as being determinative of this case, a focus with which the court agrees. The determinative issue is whether under the circumstances of payment made to IMBR, a “transfer of an interest of the debtor (Scott Fabricating, Inc.) in property” was made.

The Trustee asserts that the factual circumstances establish that IMBR received a preferential payment for its provision of a 30-ton crane for the erection of steel by Scott Fabricating at the Purdue University Calumet Student Housing Phase 11-2008 project [see paragraph 4 of the Joint Stipulation]. IMBR asserts that no preferential transfer was made with respect to monies which it received with respect to the provision of the crane for the project.

IMBR wins.

The material facts, as found by the court based upon the record before it, are the following:

1. Berglund Construction Company entered into a contract with Purdue University as the general contractor with respect to a construction project known as the Purdue University Calumet Student Housing Phase 11-2008 project.

2. Berglund Construction Company, as the general contractor, entered into a subcontract with the debtor Scott Fabricating, Inc. for work in relation to that project.

3. Scott Fabricating, Inc., as a subcontractor of Berglund, entered into a sub-subcontract with IMBR for the latter’s provision of a crane utilized/to be utilized by Scott Fabricating, Inc. with respect to the work to be performed on the project.

4. IMBR sent three invoices to Scott Fabricating for the provision of the crane. The negotiable instrument provided by Scott Fabricating, Inc. to IMBR with respect to those invoices was returned due to insufficient funds in Scott Fabricating, Inc.’s account. Therefore, IMBR received no payment from Scott Fabricating, Inc., its direct contractual party.

5. IMBR filed a bond claim with the Purdue University Board of Trustees pursuant to Indiana Code § 4-13.6-7-20 and 5-16-5-2 with respect to its claim for payment owed it by Scott Fabricating, Inc. The bond claim was transmitted to Travelers Insurance Company (the issuer of the bond) and to Berglund Construction Company on August 4, 2009.

5. Thereafter, negotiations occurred between Berglund and IMBR, which resulted in an agreement by which Berglund [904]*904paid IMBR $12,096.00 in exchange for a final waiver of lien and a letter agreeing to withdraw the bond claim made by IMBR. This agreement was effectuated: Berglund in fact paid IMBR $12,096.00; IMBR released any lien claims and its claim against the bond.

6. IMBR did not assert a claim which in any manner constituted a lien or other restriction of payment with respect to any payment to be made by Purdue University to Berglund.

7. IMBR did assert a claim against the bonding company which provided a performance/payment bond for Berglund as the obligor for the benefit of Purdue University as the obligee.

8. The court infers from the circumstances and relationships established by the record that the contract between Purdue University and Berglund required Berglund to hold Purdue University harmless from any claims for unpaid subcontractors with respect to the project. The court also infers that the bond provided by Berglund to Purdue University indemnified this contractual obligation in a manner such that IMBR was a third-party beneficiary of the bond, thereby entitling IMBR to assert a claim against the bond for the debt created by its performance of the subcontract between it and Scott Fabricating, Inc. when Scott Fabricating, Inc. did not pay IMBR with respect to that debt.3

9. The payment by Berglund to IMBR was done to avoid a breach of Berglund’s contract with Purdue University, and to avoid a reimbursement action by Travelers Insurance Company against Berglund with respect to the claim made by IMBR against the bond had the bonding company paid that claim.

In order to succeed on his complaint, the Trustee must establish that the payment made by Berglund to IMBR involved a transfer by Berglund to IMBR of property in which Scott Fabricating, Inc. had an interest. As stated in 11 U.S.C. § 547(g), the Trustee “has the burden of proving the avoidability of a transfer under subsection (b) of [11 U.S.C. § 547]”. As stated in 11 U.S.C. § 547(e)(3), for the purposes of 11 U.S.C. § 547, “a transfer is not made until the debtor has acquired rights in the property transferred”. As stated in 11 U.S.C. § 101(54), a “transfer” is defined as follows:

(54) The term “transfer” means—
(A) the creation of a lien;
(B) the retention of title as a security interest;
(C) the foreclosure of a debtor’s equity of redemption; or
(D) each mode, direct or indirect, absolute or conditional, voluntary or involuntary, of disposing of or parting with—
(i) property; or
(ii) an interest in property.

The Trustee’s assertion is essentially that Scott Fabricating, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
478 B.R. 901, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dubois-v-imbr-crane-in-re-scott-fabricating-inc-innb-2012.