In RE McSHANE, INC.

328 B.R. 430
CourtUnited States Bankruptcy Court, D. Maryland
DecidedJune 15, 2005
Docket15-11190
StatusPublished
Cited by1 cases

This text of 328 B.R. 430 (In RE McSHANE, INC.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In RE McSHANE, INC., 328 B.R. 430 (Md. 2005).

Opinion

328 B.R. 430 (2005)

In re McSHANE, INC. t/a MCS, Debtor.
McShane, Inc. t/a MCS, Plaintiff,
v.
Monumental Supply Co., Inc., Defendant.

Bankruptcy No. 02-54385-SD, Adversary No. 04-01313.

United States Bankruptcy Court, D. Maryland.

June 15, 2005.

*431 Curtis C. Coon, Esq., Law Office of Curtis C. Coon, LLC, Towson, MD, debtor.

MEMORANDUM AND ORDER DENYING PLAINTIFF'S MOTION FOR SUMMARY JUDGMENT AND GRANTING DEFENDANT'S MOTION FOR SUMMARY JUDGMENT

E. STEPHEN DERBY, Bankruptcy Judge.

Pending before the Court are cross motions for summary judgment filed by Plaintiff McShane, Inc. t/a MCS ("MCS") and Defendant Monumental Supply Co., Inc. ("Monumental"). The parties have filed responses and replies to the summary judgment motions, and a hearing will not materially aid the court in resolving the motions. For reasons stated below, the court will grant summary judgment in favor of Defendant Monumental and deny summary judgment as to Plaintiff MCS.

I. BACKGROUND AND RELEVANT FACTS

The material facts are not in dispute. In October, 2001, general contractor Kamtech, Inc. ("Kamtech") entered into an Agreement with Wells Fargo Northwest, N.A., for Procurement, Construction and Installation Services for the Possum Point Generation Facility ("Construction Contract") in Virginia ("Possum Point Project").

Pursuant to the Construction Contract, Kamtech was responsible for paying subcontractors and vendors and for ensuring that subcontractors paid their subcontractors and suppliers. Construction Contract, Section 10.2, attached as Exhibit A to Monumental's Motion for Summary Judgment. Section 10.2 states as follows:

Payments to Subcontractors and Vendors. Upon receipt of payment from, or on behalf of, Owner, Contractor shall promptly pay each Subcontractor and Vendor per its agreements with its Subcontractors and Vendors, out of the amount paid to Contractor on account of Subcontractor's or Vendor's work. Contractor shall require each Subcontractor or Vendor to make similar payments to its Subcontractors and Vendors. Except as otherwise provided in this Agreement, Owner shall have no right or obligation to pay, or cause the payment of, any money to any Subcontractor or Vendor or any other person acting through, under or on behalf of Contractor except as may otherwise be required by Laws and Codes, and then subject to Contractor's indemnity obligations under this Agreement. Notwithstanding the foregoing, any payments made by Owner to any Subcontractor or Vendor as permitted in this Agreement shall be reimbursed by Contractor to Owner or may be offset by Owner against, and deducted from, any future payments due to Contractor from Owner.

Construction Contract, § 10.2. The Construction Contract also provides that the Owner could withhold final payment from Kamtech under the Construction Contract to protect the Owner from losses from, inter alia, mechanics liens, unless Kamtech posted a performance bond under which such obligations would be paid. Construction Contract, § 11.7 Payments Withheld. Section 11.8.2 specifically authorized Kamtech to obtain a performance bond to indemnify the owner and lenders against mechanics liens in order to obtain final payment on the Project. If such a Performance Bond was posted, final payment to Kamtech could not be withheld.

Indeed, Kamtech executed a Payment Bond with United States Fidelity and *432 Guaranty ("USFG") to guaranty performance of the Construction Contract ("Payment Bond"). Pursuant to the Payment Bond, and as the joint and several co-obligor with USFG, Kamtech became obligated to pay for all "labor, materials, and equipment furnished for use in performance of the Construction Contract . . .". Payment Bond, ¶ 1, attached to Monumental's Motion for Summary Judgment, Exhibit A (Construction Contract). The Payment Bond creates a direct obligation for Kamtech to make payment to all Claimants, which are defined as "persons or entities having a direct contract with [Kamtech] or with any subcontractor of [Kamtech] to furnish labor materials or equipment for use in the [Construction] Contract." Payment Bond, ¶ 15. This direct obligation to any Claimant under the Payment Bond was only satisfied, and became null and void, if and when Kamtech promptly made payment, directly or indirectly, for all sums due. Payment Bond, ¶ 3.

On October 26, 2001 Kamtech executed a subcontract with MCS for MCS to supply piping materials for the Possum Point Project ("MCS Subcontract"). The MCS Subcontract was amended on several occasions to increase the amount of piping to be installed and the price to be paid. In turn, MCS executed a contract with Monumental for the supply of materials to MCS related to the MCS Subcontract ("Monumental Materials Contract").

As of February 7, 2002, Kamtech had paid Monumental $44,423.56, leaving a balance under the MCS Subcontract of $118,120.26. On or about February 18, 2002, Monumental notified Kamtech directly that Monumental had not been paid approximately $84,300 under the Monumental Materials Contract, and that unless Kamtech made payment Monumental would enforce mechanics lien rights against the project property. The lien waiver Kamtech requested from MCS in February, 2002 specifically removed the certification that MCS had paid all sums due for materials and supplies furnished or supplied by of for MCS for the Possum Point Project. MCS Lien Waiver, attached as Exhibit C to Monumental's Motion for Summary Judgment.

On March 14, 2002, Kamtech, MCS and Monumental Executed a Settlement Agreement and Release ("Settlement Agreement") relative to the Possum Point Project. Pursuant to the Settlement Agreement, Kamtech agreed to pay $80,000 directly to Monumental and $38,120 to MCS. The Settlement Agreement released all claims of Monumental and MCS against Kamtech and the Possum Point Project. Kamtech thereafter drafted a check in the amount of $80,000, which was presented to Monumental on or around March 19, 2002.

MCS filed for protection under Chapter 11 of the Bankruptcy Code on March 18, 2002. In this adversary proceeding, MCS seeks recovery of the $80,000 paid from Kamtech to Monumental as an avoidable preference under 11 U.S.C. Section 547(b). Alternatively, MCS maintains that the payment was a post-petition transfer of estate property in violation of 11 U.S.C. Section 549(a). Monumental takes the position that the $80,000 payment was neither property of the debtor nor property of the estate based on Kamtech's independent obligation to ensure payment to all suppliers, and that as a result the payment was neither a pre-petition preference nor a post-petition transfer of estate property. MCS and Monumental have both filed motions for summary judgment.

II. ANALYSIS

A. Summary Judgment Standard

Summary judgment is appropriate when "the pleadings, depositions, answers to interrogatories, *433 and admissions on file, together with the affidavits, if any," demonstrate the absence of a genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56( c), made applicable to these proceedings by Fed. R. Bankr.P. 7056.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
328 B.R. 430, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-mcshane-inc-mdb-2005.