City of Kansas City Ex Rel. Lafarge North America Inc. v. Ace Pipe Cleaning, Inc.

349 S.W.3d 399, 81 A.L.R. 6th 753, 2011 Mo. App. LEXIS 974, 2011 WL 3106958
CourtMissouri Court of Appeals
DecidedJuly 26, 2011
DocketWD 73044
StatusPublished
Cited by5 cases

This text of 349 S.W.3d 399 (City of Kansas City Ex Rel. Lafarge North America Inc. v. Ace Pipe Cleaning, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Kansas City Ex Rel. Lafarge North America Inc. v. Ace Pipe Cleaning, Inc., 349 S.W.3d 399, 81 A.L.R. 6th 753, 2011 Mo. App. LEXIS 974, 2011 WL 3106958 (Mo. Ct. App. 2011).

Opinion

CYNTHIA L. MARTIN, Judge.

Plaintiffs/Appellants Lafarge North America Inc. and Quicksilver 2005, LLC appeal the trial court’s judgment denying them the right to recover against statutory payment bonds issued to a general contractor on public works projects in the City of Kansas City. We affirm.

Factual Background

The facts of this case present a relatively straight-forward legal issue. Under Missouri’s Little Miller Act, can a supplier to a sub-subcontractor récover against a statutory payment bond obtained by a general contractor on a public works project? The answer is no.

The City of Kansas City (“City”) hired a general contractor, Ace Pipe Cleaning, Inc. (“Ace”) to construct, repair and replace five municipal sewer facilities. As required by Section 107.170, 1 also known as the Little Miller Act, Ace purchased a statutory payment bond from Travelers Casualty and Surety Company of America (“Travelers”) for each of the projects. 2

Ace entered into a subcontract with U.S. Constructall, Inc. (“US Constructall”) on four of the five projects (the “USC Projects”). US Constructall was owned by Henok Woldermariam and Daniel Hlavna (“Daniel”) 3 , and operated by Daniel. Ace authorized U.S. Constructall to subcontract certain trucking work to Excel Trucking, Inc. (“Excel”), a company fully owned and operated by Andi Hlavna (“Andi”), Daniel’s wife. 4 US Constructall also subcontracted its obligation to provide concrete for the USC Projects to Excel, although it did so without a written subcontract and without Ace’s knowledge. Excel then contracted with Lafarge 5 North America Inc. (“Lafarge”) 6 to supply the concrete for the USC Projects. La-farge did not ask Excel if it had a direct subcontract with Ace to provide the concrete for the USC Projects.

On the fifth project known as the “Phase J Project” Ace subcontracted directly with Excel for the provision of concrete. Excel also contracted with Lafarge to supply the concrete for the Phase J Project.

Excel failed to pay Lafarge for the concrete it supplied for the USC Projects and the Phase J Project in the total amount of $127,887.50. Lafarge filed suit against U.S. Constructall and Excel for this amount, and also filed claims against Ace *402 and Travelers on the statutory payment bonds for this amount.

The trial court entered judgment in favor of Lafarge and against U.S. Construc-tall and Excel in the amount of $127,887.50 on a theory of breach of contract. 7 Of this, $32,916.61 was attributable to the Phase J Project and $94,960.89 was attributable to the USC Projects.

The trial court entered judgment in the amount of $32,916.61 in favor of Lafarge and against Ace and Travelers on the statutory payment bond for the Phase J Project, finding that Ace was the general contractor, Excel was Ace’s subcontractor, and Lafarge was Excel’s supplier, and thus not too remote from Ace to recover on the statutory payment bond for that project. 8

The trial court entered judgment in favor of Ace and Travelers and against La-farge with respect to the claims asserted against the statutory payment bonds on the USC Projects. The trial court found that Ace was the general contractor, U.S. Constructall was Ace’s subcontractor, Excel was a sub-subcontractor to U.S. Constructall, and Lafarge was a supplier to Excel. The trial court found that Lafarge was too remote from Ace to permit recovery on the statutory payment bonds on the USC Projects given the construction of the Little Miller Act in City of St. Louis ex rel. Stone Creek Brick Co. v. Kaplan-McGowan Co., 233 Mo.App. 789, 108 S.W.2d 987 (1937).

At trial, Lafarge attempted to circumvent Stone Creek’s construction of the Little Miller Act, which limits recovery on statutory payment bonds to first tier subcontractors and those contracting directly with them. First, Lafarge argued that a theory known as “telescoping” should apply to collapse U.S. Constructall and Excel into one entity, rendering Lafarge a supplier of materials to a first tier subcontractor. The trial court held that the theory of telescoping, which looks at the substance of the relationship between parties as opposed to their technical form, is consistent with the purpose underlying the Little Miller Act. However, the trial court concluded that the facts of the case did not warrant the application of the theory of telescoping in part “because no party in this lawsuit participated in a sham or is in any way culpable, and because Ace was not unjustly enriched.”

Second, Lafarge argued that U.S. Con-structall and Excel were not separate entities and that the court should pierce the corporate veil to treat them as one. The trial court found that U.S. Constructall and Excel were indeed separate entities, and that U.S. Constructall did not exercise dominance and control over Excel. As a result, the trial court held that the “piercing the corporate veil doctrine is inapplicable to U.S. Constructall and Excel.”

Accordingly, the trial court refused to find that Lafarge was an eligible claimant *403 on the statutory payment bonds on the USC Projects.

Lafarge filed this timely appeal.

Standard of Review

In reviewing a court-tried case, we are governed by the familiar standards of Murphy v. Carron. 9 This court “will affirm the judgment of the trial court unless there is no substantial evidence to support it, it is against the weight of the evidence, or it erroneously declares or applies the law.” R.L. Polk & Co. v. Mo. Dept. of Rev., 309 S.W.3d 881, 884 (Mo.App. W.D.2010). Questions of law, including issues of statutory interpretation, are reviewed de novo. Motor Control Specialities, Inc. v. Labor and Indus. Relations Commn’n, 323 S.W.3d 843, 849 (Mo.App. W.D.2010). We review all evidence in a light most favorable to the judgment and disregard all evidence and inferences to the contrary. Dhyne v. State Farm Fire and Cas. Co., 188 S.W.3d 454, 456-457 (Mo.2006).

Analysis

Lafarge raises two points on appeal. First, Lafarge contends that the trial court erred by concluding that in order to telescope the subcontract between U.S. Con-structall and Excel, it was necessary to show the existence of a sham designed to insulate Ace from liability on the payment bond or that Ace was unjustly enriched.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
349 S.W.3d 399, 81 A.L.R. 6th 753, 2011 Mo. App. LEXIS 974, 2011 WL 3106958, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-kansas-city-ex-rel-lafarge-north-america-inc-v-ace-pipe-moctapp-2011.