Roeslein & Associates, Inc. v. Wendt, LLP

CourtDistrict Court, E.D. Missouri
DecidedMarch 24, 2025
Docket4:22-cv-01105
StatusUnknown

This text of Roeslein & Associates, Inc. v. Wendt, LLP (Roeslein & Associates, Inc. v. Wendt, LLP) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roeslein & Associates, Inc. v. Wendt, LLP, (E.D. Mo. 2025).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MISSOURI EASTERN DIVISION

ROESLEIN & ASSOCIATES, INC, ) ) Plaintiff, ) ) v. ) No. 4:22 CV 1105 RWS ) WENDT, LLP, ) ) Defendant. )

MEMORANDUM AND ORDER

This case arises out of a contract dispute between Plaintiff Roeslein & Associates, Inc. and Defendant Wendt, LLP regarding a construction project in Ohio. The case is now before me on a motion for partial summary judgment filed by Roeslein. In its motion, Roeslein argues that it is entitled to judgment on liability as to Counts I and II of its amended complain. For the reasons discussed below, Roeslein’s motion will be granted in part and denied in part. BACKGROUND1 Roeslein is an engineering and construction firm that designs, engineers, and constructs can-making and industrial plant buildings. In March 2021, Roeslein was hired to construct a canning plant in Huron, Ohio (the “Project”). In June 2021,

1 The information in this section is taken from the parties’ statements of uncontroverted material facts, ECF Nos. 103, 114 & 119, to the extent they are not specifically controverted by the opposing party as required by Local Rule 7–4.01(E). Wendt submitted lump-sum bids to serve as a subcontractor for two parts of the project: rigging installation and mezzanine installation. Roeslein accepted those

bids and sent two purchase orders: one for rigging installation for the lump sum of $3,967,849 and one for mezzanine installation for the lump sum of $2,936,755 (the “Purchase Orders”). Both Purchase Orders were subject to Roeslein’s Standard

Terms and Conditions (the “Agreements”). The Agreements contain the following relevant provisions governing subcontractors, security interests and liens, and default: 8. VENDOR, ITS EMPLOYEES AND SUBCONTRACTOR.

… [Wendt] shall have the right to hire or discharge its employees and designate their work classifications. [Wendt] shall have complete charge and control of its employees and those of its subcontractors engaged in the performance of the Work. [Wendt] shall maintain strict discipline and order among its employees and employees of its subcontractor. [Wendt] shall not engage unqualified subcontractors nor employ unfit persons nor anyone unskilled in the work assigned. …

9. ASSIGNMENTS AND SUBCONTRACTS.

(c) [Wendt] shall be as fully responsible for the acts and omissions of its subcontractors and of persons either directly or indirectly employed by them as it is for its own acts and omissions.

(f) [Wendt] shall require each of its subcontractors, to the extent of the Work to be performed by such subcontractor, to be bound to [Wendt] by the terms of this Contract and to assume towards [Wendt] all the obligations and responsibilities which [Wendt] assumes towards Roeslein under this Contract.

21. SECURITY INTERESTS; LIENS

(a) [Wendt] shall . . . deliver the Work free and clear of any and all security interests, liens, claims and encumbrances of any kind or nature arising out of or resulting from the performance of the Work by [Wendt] . . . . If any such lien, claim, security interest or encumbrance is filed, [Wendt] shall promptly cause it to be removed without cost to Roeslein. [Wendt] shall protect, defend, and indemnify Roeslein . . . from any and all claims, losses, damages, costs, actions, judgments, expenses, and liabilities of every kind and nature whatsoever (including, but not limited to, attorneys’ fees and costs and expenses of the preceding) which, either directly or indirectly, arise out of result from such liens, claims or encumbrances.

31. DEFAULT.

(a) The existence of any of the following circumstances shall constitute a default by [Wendt] under this Contract and shall entitle Roeslein to terminate the Contract immediately upon written notice to [Wendt].

(2) [Wendt]’s failure to comply strictly with any of the provisions of the Contract.

(5) [Wendt]’s disregarding of any applicable statute, law, ordinance, code, order, rule, regulation, proclamation or other governmental requirement.

(6) [Wendt]’s failure in any manner to perform the Work strictly in accordance with this Contract . . . .

… 38. COMPLIANCE WITH APPLICABLE LAWS

… [Wendt] shall comply with all applicable statutes, laws, ordinances, codes, orders, rules, regulations, proclamations and other governmental requirements, and all provisions required in the Contract are incorporated by reference[.]

ECF No. 103-1 at 4–6. In the fall of 2021, Wendt used Trillium Construction Services, Inc., a staffing agency, to provide additional labor and perform work on the Project. In March 2022, the Erie County, Ohio Sheriff’s Office received an anonymous tip that a Trillium employee had been selling marijuana to other workers on the worksite. After three rounds of surveillance, police arrested a Trillium employee for selling marijuana on the worksite on April 1, 2022.2 The police discovered 1.5 pounds of marijuana in the worker’s vehicle, which was individually bagged. Wendt placed one of its own workers on a ninety-day probation for being involved in the drug transactions. Following the arrest, Roeslein’s Construction Manager, Doug Wedge, directed Wendt to vacate the worksite. At 5:30 p.m. on April 1, 2022, Wedge called

Tom Shaw, Wendt’s Superintendent, to inform him that Roeslein had decided to release Wendt from the Project due to Wendt’s actions and the arrests that had occurred on the worksite. Over the next month, Roeslein and Wendt participated in

negotiations to close the Agreement,

2 Recreational marijuana was illegal in Ohio at this time. On April 19, 2022, Trillium filed an Affidavit for Mechanics’ Lien for the amount of $126,731.50 with the Erie County Recorder’s Office after Wendt failed

to pay Trillium for its work on the Project. On December 7, 2022, Trillium filed a Complaint to Validate Mechanics’ Lien and Other Relief in the Court of Common Pleas of Erie County, Ohio. Roeslein removed that complaint to the U.S. District

Court for the Northern District of Ohio on January 10, 2023. Roeslein then requested that Wendt remove the lien pursuant to the Agreements, which it did not do. As a result, Roeslein posted a mechanics’ lien bond, which remains in place, and paid premiums for that bond to remove the lien.

Roeslein filed this lawsuit against Wendt on October 17, 2022. Wendt filed its answers and counterclaims on November 23, 2022, and filed a third-party complaint against Trillium. This Court dismissed Trillium from the case for lack of

personal jurisdiction after finding that Trillium was not aware of the terms of the Agreement between Roeslein and Wendt and could not be bound by the Agreement’s forum selection clause. See ECF No. 44. Roeslein now requests partial summary judgment on Wendt’s liability for

breach of contract as alleged in Counts I and II of its amended complaint. Roeslein argues that Wendt breached the Agreements when it (1) allowed the illegal sale of drugs on its work site; (2) refused to remove Trillium’s lien on the Project; and (3)

did not ensure that Trillium agreed to be bound by the terms of the Agreements. LEGAL STANDARD Summary judgment is appropriate if “there is no genuine dispute as to any

material fact and the movant is entitled to judgment as a matter of law.” Cox v. First Nat’l Bank, 792 F.3d 936, 938 (8th Cir. 2015) (quoting Fed. R. Civ. P. 56(a)). In ruling on a motion for summary judgment, I must “‘view the evidence in the light

most favorable to the opposing party’ and draw all reasonable inferences in favor of that party.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Torgerson v. City of Rochester
643 F.3d 1031 (Eighth Circuit, 2011)
United States v. Aetna Casualty Insurance Company
908 F.2d 375 (Eighth Circuit, 1990)
Superior Insurance Co. v. Universal Underwriters Insurance Co.
62 S.W.3d 110 (Missouri Court of Appeals, 2001)
Harris v. DeSisto
932 S.W.2d 435 (Missouri Court of Appeals, 1996)
Tolan v. Cotton
134 S. Ct. 1861 (Supreme Court, 2014)
Stacy Cox v. First National Bank
792 F.3d 936 (Eighth Circuit, 2015)
State Ex Rel. Brauer v. City of Del Rio
92 S.W.2d 287 (Court of Appeals of Texas, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
Roeslein & Associates, Inc. v. Wendt, LLP, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roeslein-associates-inc-v-wendt-llp-moed-2025.