Roeslein & Associates, Inc. v. Wendt, LLP

CourtDistrict Court, E.D. Missouri
DecidedApril 11, 2024
Docket4:22-cv-01105
StatusUnknown

This text of Roeslein & Associates, Inc. v. Wendt, LLP (Roeslein & Associates, Inc. v. Wendt, LLP) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roeslein & Associates, Inc. v. Wendt, LLP, (E.D. Mo. 2024).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MISSOURI EASTERN DIVISION

ROESLEIN & ASSOCIATES, INC, ) ) Plaintiff, ) ) v. ) No. 4:22 CV 1105 RWS ) WENDT, LLP, ) ) Defendant. )

MEMORANDUM AND ORDER

This case arises out of a contract dispute between Plaintiff Roeslein & Associates, Inc. and Defendant Wendt, LLP regarding Wendt’s termination by Roeslein from a construction project. The case is now before me on a motion for partial summary judgment filed by Wendt. In its motion, Wendt argues that it is entitled to judgment finding that Roeslein cannot recover any excess costs under the contract because Roeslein did not effect termination for default as required by their Agreement. For the reasons discussed below, Wendt’s motion will be granted. BACKGROUND1 Roeslein is an engineering and construction firm that designs, engineers, and constructs can-making and industrial plant buildings. In March 2021, Roeslein was

1 The information in this section is taken from the parties’ statements of uncontroverted material facts, ECF Nos. 65, 73 & 81, to the extent they are not specifically controverted by the opposing party as required by Local Rule 7–4.01(E). hired to construct a canning plant in Huron, Ohio (the “Project”). In June 2021, Wendt submitted lump-sum bids to serve as a subcontractor for two parts of the

project: rigging installation and mezzanine installation. Roeslein accepted those bids and sent two purchase orders: one for rigging installation for the lump sum of $3,967,849 and one for mezzanine installation for the lump sum of $2,936,755 (the

“Purchase Orders”). Both Purchase Orders were subject to Roeslein’s Standard Terms and Conditions (the “Agreement”). The Agreement contained the following relevant provisions governing subcontractors, default, and termination:

8. VENDOR, ITS EMPLOYEES AND SUBCONTRACTOR.

… [Wendt] shall have the right to hire or discharge its employees and designate their work classifications. [Wendt] shall have complete charge and control of its employees and those of its subcontractors engaged in the performance of the Work. [Wendt] shall maintain strict discipline and order among its employees and employees of its subcontractor. [Wendt] shall not engage unqualified subcontractors nor employ unfit persons nor anyone unskilled in the work assigned. …

9. ASSIGNMENTS AND SUBCONTRACTS.

(c) [Wendt] shall be as fully responsible for the acts and omissions of its subcontractors and of persons either directly or indirectly employed by them as it is for its own acts and omissions.

… 31. DEFAULT.

(a) The existence of any of the following circumstances shall constitute a default by [Wendt] under this Contract and shall entitle Roeslein to terminate the Contract immediately upon written notice to [Wendt].

(2) [Wendt]’s failure to comply strictly with any of the provisions of the Contract.

(5) [Wendt]’s disregarding of any applicable statute, law, ordinance, code, order, rule, regulation, proclamation or other governmental requirement.

(6) [Wendt]’s failure in any manner to perform the Work strictly in accordance with this Contract . . . .

(b) In the event of termination for default, [Wendt] shall be and shall remain liable to Roeslein for all loss and damage which Roeslein may suffer by reason of such default and for any breaches by [Wendt] of its obligations or warranties under this Contract. …

(c) Termination for default shall be effected by written notice from Roeslein stating the circumstances of default and the date upon which Roeslein intends to complete the removal from the worksite of the Work in its current state (emphasis added). (d) … If it is subsequently determined that [Wendt] was not in default or that its failure to strictly perform this Contract was due to causes beyond its control and without its fault or negligence, the termination shall be deemed to have been for the convenience of Roeslein, and Roeslein’s sole obligation or liability to [Wendt] shall be to settle with [Wendt] in accordance with section 32(e). 32. TERMINATION.

(b) Roeslein shall have the right to terminate this Contract at any time for any reason upon written notice to [Wendt]. …

(e) Upon any termination of this Contract, other than termination due to the default of [Wendt], final settlement of all claims of [Wendt] arising out of this Contract shall be made as follows:

(2) If this is a lump sum contract, Roeslein shall pay [Wendt] an amount which, when added to any payments theretofore made to [Wendt] under this Contract, bears the same ratio to the total Contact price as the amount of the Work completed by [Wendt] prior to the effective date of termination bears to the total amount of the Work.

(f) If the termination of this Contract is due to the default of [Wendt] or as a result of strikes, lockouts, or other labor disputes, final settlement of all claims of [Wendt] arising out of this Contract shall be made as follows and no payments, other than any payments made in accordance with this section, shall be due until the Work has been fully completed.

(2) If this is a lump sum contract, Roeslein shall pay [Wendt] an amount which, when added to any payments theretofore made to [Wendt] under this Contract, bears the same ratio to the total Contact price as the amount of the Work completed by [Wendt] prior to the effective date of termination bears to the total amount of the Work; provided, however, that if Roeslein’s costs to complete the Work exceed the unpaid balance of the Contract price (taking into account all previous payments to [Wendt]), [Wendt] shall be liable to Roeslein for such excess costs. Roeslein shall be entitled to deduct the amount of such excess costs from any amounts payable to [Wendt] under this Contract including, but not limited to, any amounts payable in accordance with this section.

ECF No. 73-2 at 2–5. In the fall of 2021, Wendt used Trillium Construction Services, Inc., a staffing agency, to provide additional labor and perform work on the Project. In March 2022, the Erie County, Ohio Sheriff’s Office received an anonymous tip that a Trillium employee had been selling marijuana to other workers on the worksite. After three rounds of surveillance, police arrested a Trillium employee for selling marijuana on the worksite on April 1, 2022.2 The police discovered 1.5 pounds of marijuana in the worker’s vehicle, which was individually bagged. Wendt placed one of its own workers on a ninety-day probation for being involved in the drug transactions. Following the arrest, Roeslein’s Construction Manager, Doug Wedge, directed Wendt to vacate the worksite. At 5:30 p.m. on April 1, 2022, Wedge called Tom Shaw, Wendt’s Superintendent, to inform him that Roeslein had decided to

release Wendt from the Project due to Wendt’s actions and the arrests that had occurred on the worksite. On April 8, 2022, Tim Allen, Wendt’s Director of Operations, emailed Roeslein requesting written notice of why Wendt was released

2 Recreational marijuana was illegal in Ohio at this time. from the project and for the names of the individuals selling drugs. Roeslein decided to respond to that email with the names of the individuals, but “nothing more.”

Over the next month, Roeslein and Wendt participated in negotiations to close the Agreement, including how much of the project Wendt had completed. On May 12, 2022, Roeslein sent an email to Wendt stating that based on Wendt’s completion

percentage, Roeslein owed Wendt $127,000 beyond the amounts already paid. Roeslein further stated that Wendt was removed from the project for cause, that Roeslein would incur additional expenses beyond $127,000 to complete the project, that the additional costs were Wendt’s account, and that Roeslein would not make

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Torgerson v. City of Rochester
643 F.3d 1031 (Eighth Circuit, 2011)
Dunn Industrial Group, Inc. v. City of Sugar Creek
112 S.W.3d 421 (Supreme Court of Missouri, 2003)
Graham v. Goodman
850 S.W.2d 351 (Supreme Court of Missouri, 1993)
Burrus v. HBE Corp.
211 S.W.3d 613 (Missouri Court of Appeals, 2006)
Crabby's, Inc. v. Hamilton
244 S.W.3d 209 (Missouri Court of Appeals, 2008)
Stacey v. Redford
226 S.W.3d 913 (Missouri Court of Appeals, 2007)
Baker v. Missouri National Life Insurance Company
372 S.W.2d 147 (Missouri Court of Appeals, 1963)
Tolan v. Cotton
134 S. Ct. 1861 (Supreme Court, 2014)
Stacy Cox v. First National Bank
792 F.3d 936 (Eighth Circuit, 2015)
Southland Metals, Inc. v. American Castings, LLC
800 F.3d 452 (Eighth Circuit, 2015)
St. Louis Housing Authority v. Thompson
657 S.W.2d 390 (Missouri Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
Roeslein & Associates, Inc. v. Wendt, LLP, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roeslein-associates-inc-v-wendt-llp-moed-2024.