Four Star Enterprises Equipment, Inc., RGH v. Employers Mutual Casualty Co.

451 S.W.3d 776, 2014 Mo. App. LEXIS 1371, 2014 WL 6961704
CourtMissouri Court of Appeals
DecidedDecember 9, 2014
DocketNo. SD 32781
StatusPublished
Cited by2 cases

This text of 451 S.W.3d 776 (Four Star Enterprises Equipment, Inc., RGH v. Employers Mutual Casualty Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Four Star Enterprises Equipment, Inc., RGH v. Employers Mutual Casualty Co., 451 S.W.3d 776, 2014 Mo. App. LEXIS 1371, 2014 WL 6961704 (Mo. Ct. App. 2014).

Opinion

PER CURIAM.

This case involving section 107.1701 comes to us on a $20,000 claim, with two separate lawsuits and seventeen years of litigation. Under section 107.170, “[s]tatutory payment bonds shift the ultimate risk of nonpayment from [eligible] workman and suppliers to the surety on public work projects,” and offer eligible “laborers and materialmen some assurance of payment.” City of Kansas City, Missouri ex rel. Lafarge North America Inc. v. Ace Pipe Cleaning, Inc., 349 S.W.3d 399, 403-04 (Mo.App.W.D.2011). In Missouri, public property “is protected from,” and “cannot be encumbered by,” mechanic’s liens.' Id. Four Star Enterprises Equipment, Inc. (“Four Star”)2 claims it rented equipment to a subcontractor on a public work project and, as a result, was eligible to seek recovery under the general contractor’s section 107.170 statutory payment bond for items covered by the bond. Id. at 404-07. Four Star obtained a default judgment against the subcontractor, and then filed suit against Employers Mutual Casualty Company (“EMC”), the surety for the statutory payment bond. The trial court, however, denied Four Star’s claim for collection of the judgment. We reverse and remand.

Factual and Procedural Background

From what can be gleaned from the record, Four Star sold and rented equipment — “mainly” construction equipment. The underlying cause of action began when Four Star leased construction equipment to Fred and Mark Townlian doing business as T & T Construction (collectively, “T & T” or “Subcontractor”), which Four Star alleged was for use on Greene 'County’s Plainview Road project. D & E Plumbing and Heating, Inc. (“D & E” or “General Contractor”) was the general contractor for the project and hired T & T. As required by section 107.170, D & E issued a payment bond for the road project with EMC as surety. T & T did not fully pay Four Star for the rental of the equipment. In May 1997, Four Star sued T & T, D & E, and EMC to recover payment for rental of the equipment. All three defendants were served with a summons.

Subcontractor did not appear or file an answer. General Contractor and EMC appeared, filed and argued several motions, and engaged in discovery before filing answers in June 2003. After General Contractor and EMC filed answers in June 2003, Four Star3 filed an affidavit of Fred Townlian and an affidavit of a representative of Four Star that same month. After filing answers, General Contractor and EMC also requested and were granted two changes of judge, engaged in further discovery, and requested and were granted at least one continuance of trial.

On September 1, 2005, the case was set for trial before a jury on November 21, 2005. At Four Star’s request, and apparently without any advance notice to D & E or EMC, the trial court then entered a default judgment in favor of Four Star [779]*779against Subcontractor on November 16, 2005. Two days later, Four Star voluntarily dismissed D & E and EMC from the suit without prejudice, making the default judgment final. The default judgment remains in effect as it was not appealed and has not been set aside.

The November 16, 2005 docket entry states, “Formal judgment is signed and filed.” The judgment itself is entitled “Judgment,” is signed by the trial court, is dated November 16, 2005, and entered judgment in favor of Four Star against Subcontractor in the amount of $18,873.18 for the “unpaid principal” attributable to Subcontractor’s rental of a 553 Gehl forklift and bucket used on the Plainview Road project from September 17, 1996 through January 17, 1997, $29,725.26 for accrued interest from February 21, 1997,. and $4,000 for attorney’s fees. The judgment also indicates that the “evidence adduced” included the “affidavits” of Fred Townlian and a Four Star representative, and the “admissions” of Fred Townlian. The docket sheet for the case shows that a copy of the docket sheet was mailed to counsel for General Contractor and EMC on November 16, 2005.

Subsequently, in September 2006, RGH, LLC, and Four Star filed suit against EMC to: (1) collect the default judgment under the statutory payment bond issued by General Contractor for Greene County’s Plainview Road project and for which EMC was surety (Count I), and (2) recover additional damages for “vexatious[] re-fus[al] to pay” the default judgment pursuant to sections 375.296 and 375.420 (Count II).

Four Star’s evidence tended to show that Four Star rented a Gehl forklift and bucket to Subcontractor that Subcontractor used on Greene County’s Plainview Road project from September 17, 1996 through January 17, 1997, but did not fully pay Four Star the amount owed under the rental agreement. EMC’s evidence tended to show that General Contractor terminated Subcontractor before September 17, 1996, and that Subcontractor did not perform any work on the Plainview Road project after being terminated. At trial, counsel for EMC acknowledged that the earlier lawsuit that gave rise to the default judgment was “very similar to this lawsuit, same parties, same set of facts.” The statutory payment bond issued by General Contractor, and for which EMC was surety, was admitted by agreement of the parties.

At trial, EMC steadfastly objected to certain documents offered into evidence by Four Star. Although the trial court noted those objections, all documents offered by Four Star during trial were admitted into evidence. Before trial, Four Star requested that the trial court issue “specific findings as to any reason or basis for the denial of any portion of [Four Star’s] bond claim.”

More than a year after the trial concluded, the trial court adopted verbatim the forty-three pages of EMC’s proposed findings and incorporated those findings into its judgment denying both of Four Star’s claims. The judgment reversed numerous evidentiary rulings made during the trial admitting documents offered by Four Star and excluded those documents from evidence and consideration by the trial court in arriving at its judgment. Four Star now appeals this judgment.

Four Star raises six claims on appeal: (1) The trial court failed to comply with Four Star’s Rule 73.014 request for findings of fact; (2) The trial court erroneously declared the law of a surety’s liability [780]*780under a statutory payment bond; (3) The trial court’s judgment was against the weight of the evidence; (4) The trial court erroneously declared that the claims were barred by the statute of limitations; (5) The trial court abused its discretion by reversing evidentiary rulings sua sponte after trial; and (6) The trial court erred by refusing to hold EMC liable for vexatious refusal to pay on the bond.5

Because all of Four Star’s points involve in some manner documentary evidence that was admitted during the trial and then excluded from evidence after trial by the judgment, we begin our review with Four Star’s fifth point, which we find dis-positive of this appeal.

Standard of Review

The admission or exclusion of evidence is within the sound discretion of the trial court. Where evidence is excluded, the issue is whether or not the trial court abused its discretion, not whether the evidence was admissible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
451 S.W.3d 776, 2014 Mo. App. LEXIS 1371, 2014 WL 6961704, Counsel Stack Legal Research, https://law.counselstack.com/opinion/four-star-enterprises-equipment-inc-rgh-v-employers-mutual-casualty-co-moctapp-2014.